Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Monee Weather Full forecast →
Today Jun 7
Chance Showers And Thunderstorms then Showers And Thunderstorms Likely
82° 70°

Chance Showers And Thunderstorms then Showers And Thunderstorms Likely

💨 10 to 15 mph 💧 78%

Leave a Comment





Latest News Stories

Committee of teh Whole 8.12.25

Will County Board Gets Back to Basics with Robert’s Rules of Order Training

Article Summary: The Will County Board Committee of the Whole received a detailed training session on Robert's Rules of Order from parliamentary expert Matthew Prochaska to clarify procedures for conducting...
Exec Cmte 8.14.25.1

Executive Committee Approves Amended Houbolt Bridge Agreement to Settle Litigation

Article Summary: The Will County Executive Committee has approved an amendment to the Houbolt Road Toll Bridge agreement, formalizing a settlement between the bridge operators and the City of Joliet....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Committee of the Whole for August 12, 2025

The Will County Board’s Committee of the Whole dedicated its August 12 meeting to an in-depth training session on Robert’s Rules of Order, aiming to foster more efficient and orderly...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for August 12, 2025

The Will County Ad-Hoc Ordinance Review Committee advanced several updated chapters of the county’s public works code during its August 12 meeting, addressing topics from solid waste to waste hauler...
Screenshot 2025-11-26 at 7.30.24 AM

Monee Board Approves $1.7 Million Payment for Critical Water Main Redundancy

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Monee Village Board authorized a substantial payment of over $1.7 million to Iroquois Paving for the Ridgeland and...
WCO-Landfill-8.5.25.2

Report Finding Few Trucks Littering Sparks Debate on Cleanup Responsibility

Article Summary: A Will County report found that a very small percentage of waste-hauling trucks are the source of litter on roadways near the county landfill, sparking a debate among...
crete-monee school district graphic.3

Crete-Monee Spotlights Summer School Success with STEM, Arts, and Academic Gains

Article Summary: The Crete-Monee school district’s 2025 summer school program was a major success, serving nearly 500 students with a blend of academic support and hands-on enrichment activities, including robotics,...
crete-monee school district graphic.2

Crete-Monee School Board Tables Vote on Arming Security Director Amid Debate

Article Summary: A proposal to allow Crete-Monee 201-U’s Director of Safety and Security to carry a firearm on school grounds was tabled by the Board of Education following a lengthy...
WCO-Landfill-8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary: The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on...
Meeting Briefs

Meeting Summary and Briefs: Will County Landfill Committee for August 7, 2025

The Will County Landfill Committee on Thursday heard a detailed technical update on the ongoing investigation for the county landfill expansion, confirming that the complex project remains on schedule. Consultants...
crete-monee school district graphic.1

Crete-Monee 201-U Board Reviews Tentative Budget with Projected $722,000 Deficit

Article Summary: The Crete-Monee School District 201-U Board of Education reviewed a tentative 2025-2026 budget that projects a $722,209 operating deficit, driven largely by a nearly $2.75 million reduction in...
Green-Garden-Logo.WP

Green Garden Township Moves Forward with New Town Hall Plans, Awaits Grant Approval

ARTICLE SUMMARY: Green Garden Township is advancing with preliminary work for a new town hall, having met with architects and a civil engineer, while awaiting Will County's final approval to...
Green-Garden-Township-Graphic.1

Township Board Approves Budget Transfers to Fund Assessor’s Staff and Correct Rent Payment

ARTICLE SUMMARY: The Green Garden Township Board approved Resolution 2025-005, which reallocates a total of $25,200 within the town fund to provide necessary staffing funds for the assessor's office and to...
solar panels photovoltaics in solar farm

County Rep Cites Solar Lawsuits, Grant Shortfalls as Key Issues Facing Will County

ARTICLE SUMMARY: Will County Board member Sherry Newquist reported that the county is navigating lawsuits related to solar farm approvals and anticipating budget challenges from the loss of federal grant money....
Assessor

Assessor’s Office Hires Staff to Handle Workload After 6% Multiplier Hits Property Owners

ARTICLE SUMMARY: Following the application of a 6% property assessment multiplier across Green Garden Township, the assessor's office has hired a new staff member to help manage the increased workload and...