Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Monee Weather Full forecast →
⚠️ Hydrologic Outlook issued June 8 at 12:44PM CDT by NWS Chicago IL
Today Jun 7
Showers And Thunderstorms Likely
70°

Showers And Thunderstorms Likely

Leave a Comment





Latest News Stories

Will County P&Z: Washington Township Lot Variance Granted

A variance to reduce the minimum lot area from 10 acres to 5 acres was unanimously approved for a property at 1444 E. Corning Road in Washington Township. The owner,...
solar panels photovoltaics in solar farm

Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition

Article Summary: The Will County Planning and Zoning Commission recommended approval for a new commercial solar farm in Crete Township, moving the project forward despite being informed by staff of...
P&Z 8.19.25

Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition

Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a long-term residential recovery program on a 68-acre horse farm, despite vocal opposition from Crete...

Will County P&Z: Green Garden Township Variances Granted in Monee

Roy F. Erikson received unanimous approval for two variances for his property at 26409 S. 80th Avenue in Monee. The Will County Planning and Zonning Commission approved reducing the minimum...

Will County P&Z: Manhattan Township Rezoning Approved

The Will County Planning and Zonning Commission unanimously approved a map amendment for a vacant property on South Kankakee Street in Manhattan Township. The request, brought by James and Julie...
Planning & Zoning Graphic.4

Will County P&Z: Green Garden Township Rezoning Approved Amid Concerns Over Lack of a Final Plan

Article Summary: The Will County Planning and Zoning Commission unanimously approved rezoning a large agricultural parcel in Green Garden Township for potential residential development, despite a township official expressing concern...
Two orange map markers on city map

Zoning Commission Overrules Staff, Approves Greeen Garden Twp Variance for 3-Acre Agricultural Lot

Article Summary: The Will County Planning and Zoning Commission approved a variance for a 3-acre lot in an agricultural zone, going against a staff recommendation to deny the request in...
Monee Township Graphic.3

Monee Township Board Authorizes $300,000 Loan for Food Pantry Construction

Monee Township Board Meeting | July 2025 Article Summary: The Monee Township Board approved a measure allowing the Supervisor to secure a loan of up to $300,000 to complete the construction...
Screenshot 2025-11-26 at 7.32.27 AM

Monee Acquires Properties, Postpones Governor’s Highway Bid

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Village of Monee moved forward with strategic real estate acquisitions on Monee-Manhattan Road but decided to postpone action...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for August 14, 2025

The Will County Board Executive Committee received a comprehensive update on the county's expenditure of $134 million in federal ARPA pandemic relief funds, learning that 61% of the total has...
Peotone-Committee-8.18.25.2

Peotone Schools Face ‘Fiscal Cliff,’ Board Considers School Closures and New Construction

Committee of the Whole Article Summary: Facing a severe financial crisis and a rapidly approaching deadline from a major road project, the Peotone School District 207-U board is now seriously...
Screenshot-2025-08-19-at-6.16.25-PM

Committee of the Whole Eyes School Closures and New Construction Amid Budget Crisis

Committee of the Whole Article Summary: Facing a severe financial crisis with a projected $4.2 million operating deficit, the Peotone School District 207-U board is now seriously exploring the closure...
Screenshot-2025-08-19-at-6.11.05-PM

Acting, Consulting Superintendents to Lead Peotone Schools During Owens’ Absence

Article Summary: Superintendent Brandon Owens is recuperating at home following a vehicle accident, prompting the Peotone Board of Education to establish an interim leadership team. Assistant Superintendent Carole Zurales will...
Screenshot-2025-08-19-at-6.09.01-PM

Peotone School Board Rejects Mandating Live-Streaming in 4-3 Vote

Article Summary: The Peotone school board has opted against requiring its meetings to be live-streamed, finalizing a new committee policy after a 4-3 vote defeated the mandate. The decision followed...
Meeting Briefs

Meeting Summary and Briefs: Peotone Board of Education for August 18, 2025

The Peotone Board of Education’s August 18 meeting was defined by the district’s precarious financial situation. With a projected $4.2 million operating deficit and its borrowing capacity nearly exhausted, the...