Will County Board Graphic.03

Landfill Committee Advances Plan to Purchase Fourth Compressor for RNG Plant

Spread the love

Will County Landfill Committee Meeting | Jan. 13, 2026

Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Monee Weather Full forecast →
⚠️ Flood Advisory issued June 7 at 4:31PM CDT until June 7 at 7:30PM CDT by NWS Chicago IL
Sun Jun 7
Chance Showers And Thunderstorms then Showers And Thunderstorms
81° 70°

Chance Showers And Thunderstorms then Showers And Thunderstorms

💨 10 to 15 mph 💧 78%

Leave a Comment





Latest News Stories

WCO-PZ-8.12.1

PZC Grants Variance for Oversized Garage in Joliet Township, Reversing Staff Recommendation

Article Summary: The Will County Planning and Zoning Commission unanimously approved a variance for a Joliet Township homeowner to build a garage addition that exceeds the county's size limits. The...
WCO-PZ-Aug-5.5

Will County Public Works Committee Approves Over $1.1 Million in New Agreements for 80th Avenue Project

ARTICLE SUMMARY: The Will County Public Works & Transportation Committee authorized two agreements totaling over $1.1 million for the ongoing reconstruction and widening of 80th Avenue between 191st and 183rd Streets....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for August 5, 2025

The Will County Board’s Legislative Committee focused on shaping its advocacy efforts at both the state and federal levels during its August 5 meeting. The primary discussion centered on crafting...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for August 5, 2025

The future of several key county facilities dominated the Will County Capital Improvements & IT Committee meeting on Tuesday. A major topic of discussion was the ongoing buildout of the...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for August 7, 2025

The Will County Board Public Health & Safety Committee on Thursday heard urgent requests for facility and funding support from two of the county’s key public-facing departments. The committee took...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for August 7, 2025

The Will County Board Public Health & Safety Committee on Thursday heard urgent requests for facility and funding support from two of the county’s key public-facing departments. The committee took...
Meeting Briefs

Meeting Summary and Briefs: Will County Land Use & Development Committee for August 7, 2025

The Will County Land Use & Development Committee tackled two contentious zoning cases during its August 7 meeting, denying a special use permit for a landscaping business in a residential...

Meeting Summary and Briefs: Will County Planning and Zoning Commission for August 5, 2025

The Will County Planning and Zoning Commission backed two controversial projects at its August 5 meeting, unanimously approving a large-scale landscaping business on a residential lot in DuPage Township despite...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for August 5, 2025

The Will County Public Works & Transportation Committee received a detailed presentation on "Our Way Forward 2050," a new 25-year long-range plan designed to guide the region's transportation infrastructure through...
Fire-Ambulance-Rescue-Logo

Indiana Woman Identified as Victim in Fatal Wilmington-Peotone Road Crash

The Will County Coroner’s Office has officially identified the woman killed in Tuesday’s fatal crash on Wilmington-Peotone Road as 70-year-old Judith L. Stirm of Delphi, Indiana. In a statement, Coroner...
Frankfort-Police-Rescue

Multiple Agencies Rescue Person in Mental Health Crisis from Frankfort Pond

A person experiencing a mental health crisis was safely rescued from a pond near 80th Avenue in Lakeview Estates on Wednesday after a coordinated response by multiple emergency agencies. Frankfort...
Green-Garden-Logo.WP

Green Garden Township Forges Ahead with New Town Hall Plan, Faces Budget and Neighbor Concerns

The Green Garden Township Board is advancing an ambitious plan to build a new, larger town hall and community center on a six-acre parcel south of its current location, a...
Meeting-7.28.25

IT Consultant Urges Green Garden Township to Adopt Modern Cybersecurity Measures

Green Garden Township’s digital infrastructure is vulnerable to cybercrime and requires an immediate overhaul, including adopting a modern, secure email system and multifactor authentication, an IT consultant told the board...
Sanchez

Sanchez Family Unveils Major Redevelopment Plan for Monee Industrial Property

Article Summary: Developer Luis Sanchez, a key figure in Monee's commercial growth for two decades, presented a plan to revitalize an industrial property on Industrial Drive. The project, which includes...
Screenshot-2025-08-13-at-2.15.28-PM

Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion

Article Summary: The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a...