Monee Village Board Meeting | May 27, 2026

Article Summary: The Monee Village Board on Wednesday, May 27, 2026, approved a $158,723.98 payment to contractor M&J Underground, Inc. for the 2025 Monee Sidewalk Improvements project, even as a resident pressed the board about extending sidewalks to another section of Main Street.

Monee Sidewalk Project Key Points:

  • The board approved Pay Request #2 to M&J Underground in the amount of $158,723.98, on a 5-0 vote.
  • The project carries a contract sum of $379,772.91 and is roughly 67% complete, with $254,531.58 earned to date.
  • A resident asked about a possible sidewalk on Main Street between Ruby and Will Center, but officials said drainage and open ditches make it a costly, lower-priority job.

MONEE — The Monee Village Board on Wednesday, May 27, 2026, approved a second progress payment of $158,723.98 to M&J Underground, Inc. for the village’s 2025 Sidewalk Improvements project, advancing a roadway-and-walkway program that residents say they are already putting to use.

The payment was presented as the second board action request under the administrator’s report. According to the board packet, Village Administrator Ruben Bautista told trustees that staff and the village’s consulting firm, Robinson Engineering, Ltd., had confirmed the contractor’s invoice met contract requirements before recommending payment.

Funding and Project Status Detailed

The packet laid out the payment in detail. M&J Underground has earned $254,531.58 to date on the project. From that figure, the village withheld 10% retention, or $25,453.16, and subtracted $70,354.44 in previous billings, leaving the $158,723.98 due on this request. In a May 8, 2026, letter to the village, Robinson Engineering Project Engineer Geoff Aggen wrote that the firm had reviewed the work and found it in substantial compliance with the plans and specifications.

Supporting documents in the packet show the project’s contract sum stands at $379,772.91 — an original contract of $376,086.46 plus a $3,686.45 change order — and that work completed and stored to date represents about 67% of the contract value. The application for payment lists a remaining balance to finish, including retainage, of $150,694.49.

The motion to approve passed 5-0, with Trustees Heidi Gonzalez, Doug Horne, Chuck Rakis, Michael Wilson and Scott Youdris voting in favor. Trustee John Henson was absent.

Before the vote, one trustee, noting the spring weather, encouraged residents to “go out and walk-test our new sidewalks, especially the one on Will Center Road,” describing that stretch as one that “looks exceptionally well.”

Residents Eye More Sidewalks

The sidewalk program drew renewed interest during the meeting’s public comment period, when resident Linda Marshall of 5032 West Herbert Court asked whether the village had plans for a sidewalk between Ruby and Will Center along Main Street, noting that only a single home along that stretch currently has a walkway and that families with school-age children live on the street.

Officials said the idea has been discussed but faces significant obstacles. Unlike the Will Center Road work, which required relatively minimal regrading, much of that section of Main Street remains lined with open drainage ditches that would have to be reconfigured with storm sewer service, a village official explained. “It’s on the radar,” the official said, “but not a priority.”

The 2025 sidewalk work follows earlier reporting that landscaping restoration tied to the project had been substantially completed, and village officials have indicated a separate 2026 sidewalk project is in the works.

Leave a Comment





Latest News Stories

WCO-Public-Safety.2

Will County Reports Progress in Opioid Fight, Highlights New FDA Labeling Rules

Article Summary: Will County is seeing a reduction in opioid overdose deaths and is expanding access to the reversal drug Narcan, health officials reported. The department also drew attention to...
WCO-Cap-Imp-8.5.4

In-House Staff Completes Major Renovations at Will County Adult Detention Facility

ARTICLE SUMMARY: Maintenance staff at the Will County Adult Detention Facility recently completed extensive renovations in-house, including a new control center and the full restoration of a 48-cell housing unit, saving...
Land-use-8.5.25

Will County Advances Truck Repair Facility Plan on Manhattan Road Despite Resident Objections

Article Summary: A proposal to rezone nearly 14 acres on Manhattan Road for a truck repair facility advanced after receiving a recommendation for approval from the Will County Land Use...
WCO-PZ-8.12.1

PZC Grants Variance for Oversized Garage in Joliet Township, Reversing Staff Recommendation

Article Summary: The Will County Planning and Zoning Commission unanimously approved a variance for a Joliet Township homeowner to build a garage addition that exceeds the county's size limits. The...
WCO-PZ-Aug-5.5

Will County Public Works Committee Approves Over $1.1 Million in New Agreements for 80th Avenue Project

ARTICLE SUMMARY: The Will County Public Works & Transportation Committee authorized two agreements totaling over $1.1 million for the ongoing reconstruction and widening of 80th Avenue between 191st and 183rd Streets....
Meeting Briefs

Meeting Summary and Briefs: Will County Board Legislative Committee for August 5, 2025

The Will County Board’s Legislative Committee focused on shaping its advocacy efforts at both the state and federal levels during its August 5 meeting. The primary discussion centered on crafting...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Capital Improvements & IT Committee for August 5, 2025

The future of several key county facilities dominated the Will County Capital Improvements & IT Committee meeting on Tuesday. A major topic of discussion was the ongoing buildout of the...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for August 7, 2025

The Will County Board Public Health & Safety Committee on Thursday heard urgent requests for facility and funding support from two of the county’s key public-facing departments. The committee took...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Public Health & Safety Committee for August 7, 2025

The Will County Board Public Health & Safety Committee on Thursday heard urgent requests for facility and funding support from two of the county’s key public-facing departments. The committee took...
Meeting Briefs

Meeting Summary and Briefs: Will County Land Use & Development Committee for August 7, 2025

The Will County Land Use & Development Committee tackled two contentious zoning cases during its August 7 meeting, denying a special use permit for a landscaping business in a residential...

Meeting Summary and Briefs: Will County Planning and Zoning Commission for August 5, 2025

The Will County Planning and Zoning Commission backed two controversial projects at its August 5 meeting, unanimously approving a large-scale landscaping business on a residential lot in DuPage Township despite...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for August 5, 2025

The Will County Public Works & Transportation Committee received a detailed presentation on "Our Way Forward 2050," a new 25-year long-range plan designed to guide the region's transportation infrastructure through...
Fire-Ambulance-Rescue-Logo

Indiana Woman Identified as Victim in Fatal Wilmington-Peotone Road Crash

The Will County Coroner’s Office has officially identified the woman killed in Tuesday’s fatal crash on Wilmington-Peotone Road as 70-year-old Judith L. Stirm of Delphi, Indiana. In a statement, Coroner...
Frankfort-Police-Rescue

Multiple Agencies Rescue Person in Mental Health Crisis from Frankfort Pond

A person experiencing a mental health crisis was safely rescued from a pond near 80th Avenue in Lakeview Estates on Wednesday after a coordinated response by multiple emergency agencies. Frankfort...
Green-Garden-Logo.WP

Green Garden Township Forges Ahead with New Town Hall Plan, Faces Budget and Neighbor Concerns

The Green Garden Township Board is advancing an ambitious plan to build a new, larger town hall and community center on a six-acre parcel south of its current location, a...