Monee Village Board Meeting | May 27, 2026

Article Summary: The Monee Village Board on Wednesday, May 27, 2026, approved a $158,723.98 payment to contractor M&J Underground, Inc. for the 2025 Monee Sidewalk Improvements project, even as a resident pressed the board about extending sidewalks to another section of Main Street.

Monee Sidewalk Project Key Points:

  • The board approved Pay Request #2 to M&J Underground in the amount of $158,723.98, on a 5-0 vote.
  • The project carries a contract sum of $379,772.91 and is roughly 67% complete, with $254,531.58 earned to date.
  • A resident asked about a possible sidewalk on Main Street between Ruby and Will Center, but officials said drainage and open ditches make it a costly, lower-priority job.

MONEE — The Monee Village Board on Wednesday, May 27, 2026, approved a second progress payment of $158,723.98 to M&J Underground, Inc. for the village’s 2025 Sidewalk Improvements project, advancing a roadway-and-walkway program that residents say they are already putting to use.

The payment was presented as the second board action request under the administrator’s report. According to the board packet, Village Administrator Ruben Bautista told trustees that staff and the village’s consulting firm, Robinson Engineering, Ltd., had confirmed the contractor’s invoice met contract requirements before recommending payment.

Funding and Project Status Detailed

The packet laid out the payment in detail. M&J Underground has earned $254,531.58 to date on the project. From that figure, the village withheld 10% retention, or $25,453.16, and subtracted $70,354.44 in previous billings, leaving the $158,723.98 due on this request. In a May 8, 2026, letter to the village, Robinson Engineering Project Engineer Geoff Aggen wrote that the firm had reviewed the work and found it in substantial compliance with the plans and specifications.

Supporting documents in the packet show the project’s contract sum stands at $379,772.91 — an original contract of $376,086.46 plus a $3,686.45 change order — and that work completed and stored to date represents about 67% of the contract value. The application for payment lists a remaining balance to finish, including retainage, of $150,694.49.

The motion to approve passed 5-0, with Trustees Heidi Gonzalez, Doug Horne, Chuck Rakis, Michael Wilson and Scott Youdris voting in favor. Trustee John Henson was absent.

Before the vote, one trustee, noting the spring weather, encouraged residents to “go out and walk-test our new sidewalks, especially the one on Will Center Road,” describing that stretch as one that “looks exceptionally well.”

Residents Eye More Sidewalks

The sidewalk program drew renewed interest during the meeting’s public comment period, when resident Linda Marshall of 5032 West Herbert Court asked whether the village had plans for a sidewalk between Ruby and Will Center along Main Street, noting that only a single home along that stretch currently has a walkway and that families with school-age children live on the street.

Officials said the idea has been discussed but faces significant obstacles. Unlike the Will Center Road work, which required relatively minimal regrading, much of that section of Main Street remains lined with open drainage ditches that would have to be reconfigured with storm sewer service, a village official explained. “It’s on the radar,” the official said, “but not a priority.”

The 2025 sidewalk work follows earlier reporting that landscaping restoration tied to the project had been substantially completed, and village officials have indicated a separate 2026 sidewalk project is in the works.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Will County Board Committee of the Whole for August 12, 2025

The Will County Board’s Committee of the Whole dedicated its August 12 meeting to an in-depth training session on Robert’s Rules of Order, aiming to foster more efficient and orderly...
Meeting Briefs

Meeting Summary and Briefs: Will County Ad-Hoc Ordinance Review Committee for August 12, 2025

The Will County Ad-Hoc Ordinance Review Committee advanced several updated chapters of the county’s public works code during its August 12 meeting, addressing topics from solid waste to waste hauler...
Screenshot 2025-11-26 at 7.30.24 AM

Monee Board Approves $1.7 Million Payment for Critical Water Main Redundancy

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Monee Village Board authorized a substantial payment of over $1.7 million to Iroquois Paving for the Ridgeland and...
WCO-Landfill-8.5.25.2

Report Finding Few Trucks Littering Sparks Debate on Cleanup Responsibility

Article Summary: A Will County report found that a very small percentage of waste-hauling trucks are the source of litter on roadways near the county landfill, sparking a debate among...
crete-monee school district graphic.3

Crete-Monee Spotlights Summer School Success with STEM, Arts, and Academic Gains

Article Summary: The Crete-Monee school district’s 2025 summer school program was a major success, serving nearly 500 students with a blend of academic support and hands-on enrichment activities, including robotics,...
crete-monee school district graphic.2

Crete-Monee School Board Tables Vote on Arming Security Director Amid Debate

Article Summary: A proposal to allow Crete-Monee 201-U’s Director of Safety and Security to carry a firearm on school grounds was tabled by the Board of Education following a lengthy...
WCO-Landfill-8.5.25.1

Will County Receives Detailed Update on Landfill Expansion Investigation

Article Summary: The Will County Landfill Committee received a comprehensive technical update on the site investigation for the planned horizontal expansion of the county landfill, confirming the project remains on...
Meeting Briefs

Meeting Summary and Briefs: Will County Landfill Committee for August 7, 2025

The Will County Landfill Committee on Thursday heard a detailed technical update on the ongoing investigation for the county landfill expansion, confirming that the complex project remains on schedule. Consultants...
crete-monee school district graphic.1

Crete-Monee 201-U Board Reviews Tentative Budget with Projected $722,000 Deficit

Article Summary: The Crete-Monee School District 201-U Board of Education reviewed a tentative 2025-2026 budget that projects a $722,209 operating deficit, driven largely by a nearly $2.75 million reduction in...
Green-Garden-Logo.WP

Green Garden Township Moves Forward with New Town Hall Plans, Awaits Grant Approval

ARTICLE SUMMARY: Green Garden Township is advancing with preliminary work for a new town hall, having met with architects and a civil engineer, while awaiting Will County's final approval to...
Green-Garden-Township-Graphic.1

Township Board Approves Budget Transfers to Fund Assessor’s Staff and Correct Rent Payment

ARTICLE SUMMARY: The Green Garden Township Board approved Resolution 2025-005, which reallocates a total of $25,200 within the town fund to provide necessary staffing funds for the assessor's office and to...
solar panels photovoltaics in solar farm

County Rep Cites Solar Lawsuits, Grant Shortfalls as Key Issues Facing Will County

ARTICLE SUMMARY: Will County Board member Sherry Newquist reported that the county is navigating lawsuits related to solar farm approvals and anticipating budget challenges from the loss of federal grant money....
Assessor

Assessor’s Office Hires Staff to Handle Workload After 6% Multiplier Hits Property Owners

ARTICLE SUMMARY: Following the application of a 6% property assessment multiplier across Green Garden Township, the assessor's office has hired a new staff member to help manage the increased workload and...
SSUCv3H4sIAAAAAAAACnSRz07DMAzG70i8Q5XzKpY10I0jB248wcTBdcwaLUum/AGhae9O0rQjB7jFP9uf/cWX+7umYQN4hey5ueQoxUrr6IODoKxJeL2auSMjydWEpArWKdA1HCDgaOBECZqodcbXKcl8gBA9+TxsRgiBDkmjwJtE2Whf4mZJTMnUkVKMrSrm4zCxBRXxfzpfoleGvH94VQYM0l9Kb8ojaQ2GbPS/suXxvliFAxn8ntxULh1pguJyX0rZ8SuQO9W+IUplK8ufFkHngq5SOjuFyhyqNhvG6QRLG9pogssr3D6EaWvPMOj8/x9JkxY+gvepXC68GoTp4PZUzTE2TAZmVSbTmXLIu023E6Lre7HlohNPYi4opx1V0pnWWYRSjEcla+sqb8AIibbYb1qOXLZih7wdeNe3m+6Ry4H3fECRPv76AwAA//8DAJrJGBCkAgAA

Township Appoints Temporary FOIA Officer During Trustee’s Leave of Absence

ARTICLE SUMMARY: The Green Garden Township Board appointed resident Belinda Olszewski as a temporary, non-paid Administrative Assistant and FOIA Officer to fill the roles while Trustee Sarah Boxer is on a...
Meeting Briefs

Meeting Summary and Briefs: Green Garden Township Board for August 11, 2025

The Green Garden Township Board pushed forward with plans for a new town hall and approved key budget transfers to support the assessor's office during its August 11th meeting. Supervisor...