Will County Planning and Zoning Commission Meeting | April 7, 2026

Article Summary: The Will County Planning and Zoning Commission unanimously granted a final deadline extension for a commercial solar developer in Joliet Township, giving the company until September 2026 to plant specialized native pollinator ground cover beneath its solar arrays.

Joliet Solar Farm Key Points:

  • Nexamp Solar, operating as Moon Shoal Renewables and Summer Stone Renewables, requested Variance Extensions #VEXT-26-001 and #VEXT-26-002.

  • The extensions apply to previously approved variances that reduced required mowing from five times a year to one time, and increased maximum plant height from 13 inches to 36 inches.

  • The extensions were necessary because the property’s farmer planted traditional crops last season, preventing the solar developer from seeding the required native pollinators before the original variance expired.

On Tuesday, April 7, 2026, the Will County Planning and Zoning Commission granted a final round of variance extensions to Nexamp Solar, ensuring the developer has the legal runway to establish native pollinator habitats at its forthcoming commercial solar facilities in Joliet Township.

The developer is currently permitting two 5-megawatt commercial solar facilities, operating under the names Moon Shoal Renewables LLC and Summer Stone Renewables LLC. The projects are located near 2618 S. Chicago Street and W. Schweitzer Road, just west of the Chicagoland Speedway.

In October 2024, the commission approved special use permits for the facilities alongside specific variances regarding ground cover. To participate in the Illinois Pollinator-Friendly Solar Site Act and create deep-rooted habitats that manage stormwater, the developer required variances to reduce the county’s required number of mowings from five times a year to just once, and to increase the maximum allowed plant height from 13 inches to 36 inches.

Because variances legally expire if a project is not established within one year, the developer had to seek extensions.

Land Use Planner Marguerite Kenny explained that the developer was unable to plant the specialized native seed mix last year because the land was still actively being farmed.

“What happened was last spring the farmer planted the field before the solar facility can go in and establish a ground cover section,” Kenny said.

Because the applicant could not plant the section of the field to establish the native pollinators before the previous extension expired on March 30, 2026, they applied for their second and final 180-day extension, as permitted by the Will County Zoning Ordinance.

The commission held separate votes for each variance extension (#VEXT-26-001 and #VEXT-26-002), unanimously approving both. The extensions are now valid through September 26, 2026, giving the developer the spring and summer seasons to establish the native plantings as their building permits finalize.

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Crete-Monee School District 201-U for September 2025

Crete-Monee School District 201-U Meeting | September 2025 Overall Meeting SummaryThe Crete-Monee School District 201-U Board of Education met on Tuesday, September 16, 2025, to conduct essential business including the...
Screenshot 2025-11-26 at 7.54.47 AM

Monee Considers Major Solar Farm Proposal with $100,000 Incentive

Village of Monee Board Meeting | September 24, 2025 Article Summary: Representatives from Earthrise Energy presented plans for "Plum Valley Solar," a massive 2,400-acre solar facility proposed for the Monee...
Screenshot 2025-11-25 at 9.39.35 PM

Attendance Matters’ Campaign Kicks Off to Combat Truancy

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The district introduced a new "Attendance Matters" campaign led by Truancy Officer Eric Green, aimed at proactively improving student attendance...
Screenshot 2025-11-25 at 9.39.24 PM

District Launches ‘ParentSquare’ to Unify School Communications

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: Crete-Monee School District 201-U is rolling out ParentSquare, a new unified communication platform designed to replace multiple existing apps and...
Monee Township Logo.1

Public Hearings Set for I-57 Freight Route and Monee TIF District

Monee Township Board Meeting | August 2025 Article Summary: Local and county officials alerted the Monee Township Board to upcoming public hearings regarding major regional developments. The hearings concern a proposed...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for September 10, 2025

Village of Monee Board Meeting | September 10, 2025 Meeting Summary: The Monee Village Board of Trustees met on Wednesday, September 10, 2025, for a session focused on infrastructure spending...
Screenshot 2025-11-25 at 9.39.05 PM

Board Awards $4 Million Contract for Middle School Renovations

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The Board of Education awarded a $4 million contract to BEAR Construction for renovations at Crete-Monee Middle School, a project...
Monee Township Graphic.4

Monee Township Food Pantry Expansion Phase 2 Pushed to 2026

Monee Township Board Meeting | August 2025 Article Summary: The Monee Township Board announced a significant schedule adjustment for the ongoing food pantry expansion project. While the first phase is complete,...
peotone library graphic logo.1

Peotone Library to Install $25,000 Smart Lockers in Monee to Expand Service

Article Summary: The Peotone Public Library District is moving forward with a plan to purchase and install a $25,000 smart locker system in Monee, providing a convenient pickup point for residents...
Screenshot 2025-11-25 at 9.38.51 PM

Crete-Monee Board Approves 2025-2026 Budget with Focus on Capital Projects

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The Crete-Monee School District 201-U Board of Education voted to adopt the fiscal year 2025-2026 budget, which projects a deficit...
Screenshot 2025-11-26 at 7.49.21 AM

Village Officials Celebrate Fall Fest Success; Reappoint Key Staff

Village of Monee Board Meeting | September 10, 2025 Article Summary: Following a successful Fall Fest, Monee officials praised village staff and volunteers for a safe and well-attended event. The...
Screenshot 2025-11-26 at 7.49.14 AM

Monee Approves Nearly $700,000 for Sidewalks and Drainage Improvements

Village of Monee Board Meeting | September 10, 2025 Article Summary: The Monee Village Board awarded two major infrastructure contracts totaling nearly $700,000 to address sidewalk connectivity and pond remediation....
Screenshot 2025-11-26 at 7.49.02 AM

Monee Board Rejects “Up Front” Cash Requests from Hotel Developer

Village of Monee Board Meeting | September 10, 2025 Article Summary: The Monee Village Board reached a consensus to reject new terms proposed by the developer of the Quality Inn...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for August 27, 2025

Village of Monee Board Meeting | August 27, 2025 Meeting Summary:The Monee Village Board of Trustees met on Wednesday, August 27, 2025, to address significant financial and development matters. The...
Monee village Graphic.1

Board Approves $1.2 Million Payout for Road Construction and New Park Accessibility Lift

Village of Monee Board Meeting | August 27, 2025 Article Summary:The Monee Village Board authorized a payment of over $1.2 million for the ongoing reconstruction of Industrial Drive and Cleveland...