Will County P&Z Commission Grants Extensions for Joliet Township Solar Farm Ground Cover

Spread the love

Will County Planning and Zoning Commission Meeting | April 7, 2026

Article Summary: The Will County Planning and Zoning Commission unanimously granted a final deadline extension for a commercial solar developer in Joliet Township, giving the company until September 2026 to plant specialized native pollinator ground cover beneath its solar arrays.

Joliet Solar Farm Key Points:

  • Nexamp Solar, operating as Moon Shoal Renewables and Summer Stone Renewables, requested Variance Extensions #VEXT-26-001 and #VEXT-26-002.

  • The extensions apply to previously approved variances that reduced required mowing from five times a year to one time, and increased maximum plant height from 13 inches to 36 inches.

  • The extensions were necessary because the property’s farmer planted traditional crops last season, preventing the solar developer from seeding the required native pollinators before the original variance expired.

On Tuesday, April 7, 2026, the Will County Planning and Zoning Commission granted a final round of variance extensions to Nexamp Solar, ensuring the developer has the legal runway to establish native pollinator habitats at its forthcoming commercial solar facilities in Joliet Township.

The developer is currently permitting two 5-megawatt commercial solar facilities, operating under the names Moon Shoal Renewables LLC and Summer Stone Renewables LLC. The projects are located near 2618 S. Chicago Street and W. Schweitzer Road, just west of the Chicagoland Speedway.

In October 2024, the commission approved special use permits for the facilities alongside specific variances regarding ground cover. To participate in the Illinois Pollinator-Friendly Solar Site Act and create deep-rooted habitats that manage stormwater, the developer required variances to reduce the county’s required number of mowings from five times a year to just once, and to increase the maximum allowed plant height from 13 inches to 36 inches.

Because variances legally expire if a project is not established within one year, the developer had to seek extensions.

Land Use Planner Marguerite Kenny explained that the developer was unable to plant the specialized native seed mix last year because the land was still actively being farmed.

“What happened was last spring the farmer planted the field before the solar facility can go in and establish a ground cover section,” Kenny said.

Because the applicant could not plant the section of the field to establish the native pollinators before the previous extension expired on March 30, 2026, they applied for their second and final 180-day extension, as permitted by the Will County Zoning Ordinance.

The commission held separate votes for each variance extension (#VEXT-26-001 and #VEXT-26-002), unanimously approving both. The extensions are now valid through September 26, 2026, giving the developer the spring and summer seasons to establish the native plantings as their building permits finalize.

Leave a Comment





Latest News Stories

Screenshot 2025-10-10 at 11.52.24 AM

Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings

Will County Executive Committee Meeting October 9, 2025 Article Summary: A proposal to move the final public hearing for zoning and land use cases from the full Will County Board...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for September 24, 2025

Village of Monee Board Meeting | September 24, 2025 Meeting Summary: The Monee Village Board of Trustees met on Tuesday, September 24, 2025, handling a mix of long-term planning and...
Screenshot 2025-11-26 at 7.56.09 AM

Public Works Facility and Firemen’s Park Set for Grand Openings

Village of Monee Board Meeting | September 24, 2025 Article Summary: Monee officials announced upcoming grand opening celebrations for two major capital projects: the new Public Works facility and the...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
Screenshot 2025-11-26 at 7.55.56 AM

Monee Approves 5-Year Police Contract with Retroactive Pay

Village of Monee Board Meeting | September 24, 2025 Article Summary: The Monee Village Board unanimously approved a new collective bargaining agreement with Teamsters Local Union #700, representing village police...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Screenshot 2025-11-26 at 7.54.57 AM

Trucking Facility Proposal Sparks Debate Over Pavement and De-Annexation

Village of Monee Board Meeting | September 24, 2025 Article Summary: The Monee Village Board reviewed a preliminary annexation agreement for a 56-acre industrial development across from Amazon, which includes...
Meeting Briefs

Meeting Summary and Briefs: Monee Township Board for Aug. 2025

Monee Township Board Meeting | August 2025 The Monee Township Board met on Thursday, August 21, 2025, to handle monthly administrative business and plan for upcoming fall community events. Supervisor...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
Monee Township Graphic.3

Attorney Advises Board Against Reissuing 18-Year-Old Check

Monee Township Board Meeting | August 2025 Article Summary: The Monee Township Board discussed a request to reimburse a vendor for an uncashed check dating back to 2007. The Township Attorney...