Monee Village Board Meeting | May 27, 2026

Article Summary: The Monee Village Board on Wednesday, May 27, 2026, approved a $158,723.98 payment to contractor M&J Underground, Inc. for the 2025 Monee Sidewalk Improvements project, even as a resident pressed the board about extending sidewalks to another section of Main Street.

Monee Sidewalk Project Key Points:

  • The board approved Pay Request #2 to M&J Underground in the amount of $158,723.98, on a 5-0 vote.
  • The project carries a contract sum of $379,772.91 and is roughly 67% complete, with $254,531.58 earned to date.
  • A resident asked about a possible sidewalk on Main Street between Ruby and Will Center, but officials said drainage and open ditches make it a costly, lower-priority job.

MONEE — The Monee Village Board on Wednesday, May 27, 2026, approved a second progress payment of $158,723.98 to M&J Underground, Inc. for the village’s 2025 Sidewalk Improvements project, advancing a roadway-and-walkway program that residents say they are already putting to use.

The payment was presented as the second board action request under the administrator’s report. According to the board packet, Village Administrator Ruben Bautista told trustees that staff and the village’s consulting firm, Robinson Engineering, Ltd., had confirmed the contractor’s invoice met contract requirements before recommending payment.

Funding and Project Status Detailed

The packet laid out the payment in detail. M&J Underground has earned $254,531.58 to date on the project. From that figure, the village withheld 10% retention, or $25,453.16, and subtracted $70,354.44 in previous billings, leaving the $158,723.98 due on this request. In a May 8, 2026, letter to the village, Robinson Engineering Project Engineer Geoff Aggen wrote that the firm had reviewed the work and found it in substantial compliance with the plans and specifications.

Supporting documents in the packet show the project’s contract sum stands at $379,772.91 — an original contract of $376,086.46 plus a $3,686.45 change order — and that work completed and stored to date represents about 67% of the contract value. The application for payment lists a remaining balance to finish, including retainage, of $150,694.49.

The motion to approve passed 5-0, with Trustees Heidi Gonzalez, Doug Horne, Chuck Rakis, Michael Wilson and Scott Youdris voting in favor. Trustee John Henson was absent.

Before the vote, one trustee, noting the spring weather, encouraged residents to “go out and walk-test our new sidewalks, especially the one on Will Center Road,” describing that stretch as one that “looks exceptionally well.”

Residents Eye More Sidewalks

The sidewalk program drew renewed interest during the meeting’s public comment period, when resident Linda Marshall of 5032 West Herbert Court asked whether the village had plans for a sidewalk between Ruby and Will Center along Main Street, noting that only a single home along that stretch currently has a walkway and that families with school-age children live on the street.

Officials said the idea has been discussed but faces significant obstacles. Unlike the Will Center Road work, which required relatively minimal regrading, much of that section of Main Street remains lined with open drainage ditches that would have to be reconfigured with storm sewer service, a village official explained. “It’s on the radar,” the official said, “but not a priority.”

The 2025 sidewalk work follows earlier reporting that landscaping restoration tied to the project had been substantially completed, and village officials have indicated a separate 2026 sidewalk project is in the works.

Leave a Comment





Latest News Stories

Screenshot 2025-11-26 at 7.41.53 AM

Monee Implements Local Grocery Tax to Replace Expired State Tax

Village of Monee Board Meeting | August 27, 2025 Article Summary:In response to the state of Illinois eliminating the grocery tax, the Monee Village Board approved an ordinance implementing a...
Screenshot 2025-11-26 at 7.40.39 AM

Monee Proposes Expansion of TIF District 5 to Spur Development

Village of Monee Board Meeting | August 27, 2025 Article Summary:The Monee Village Board held a public hearing regarding the proposed expansion of Tax Increment Financing (TIF) District No. 5...
fall-festival-b2adf834-992f-4ebd-ac09-edfc1d11b40a-circle

Your Ultimate Guide to the 2025 Frankfort Fall Fest: Everything to Know for the Nationally-Ranked Event

FRANKFORT, IL – The heart of historic downtown Frankfort is set to transform into a vibrant hub of art, music, and community spirit for the 57th annual Frankfort Fall Festival. Running...
Meeting-Briefs

Meeting Summary and Briefs: Monee Township Board for July 2025

Monee Township Board Meeting | July 2025 The Monee Township Board met on Thursday, July 17, 2025, to conduct monthly business, including the approval of financial reports and discussion of...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for August 13, 2025

Village of Monee Board Meeting | August 13, 2025 Meeting Summary: The Monee Village Board of Trustees met on Wednesday, August 13, 2025, for a session dominated by significant infrastructure...
Monee Township Logo.1

Clerk Reports Single Bid of $635,000 for Road Improvements

Monee Township Board Meeting | July 2025 Article Summary: Township Clerk Bobby Lathan reported that a recent bid opening for road improvements yielded only one proposal. The lone bid from Iroquois...
Screenshot 2025-11-26 at 7.32.32 AM

Board Advances Development Plans for Industrial Drive

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Monee Village Board authorized legal and administrative staff to begin negotiating a redevelopment agreement with LS Realty, Inc....
WCO Board Aug 21.4

After Initial Rejection and Tense Debate, Board Reconsiders and Approves Contested DuPage Township Business

Article Summary: In a rare reversal, the Will County Board approved a special use permit for a landscaping business in a residential area of DuPage Township after the measure initially...
Meeting Briefs

Meeting Summary and Briefs: Will County Board for August 21, 2025

The Will County Board received County Executive Jennifer Bertino-Tarrant’s proposed $791 million budget for fiscal year 2026, which holds the line on the property tax levy while funding key services....
Will County Recorder Graphic.1

Will County Board Approves New Fee Schedule for Recorder of Deeds

Article Summary: The Will County Board has approved a revised fee schedule for the Recorder of Deeds office, which will take effect on October 1, 2025. The changes, based on...
WCO Board Aug 21.3

Will County Board Formally Opposes Heavier, Longer Trucks on National Roadways

Article Summary: The Will County Board unanimously passed a resolution opposing any federal legislation that would increase the size and weight limits for commercial trucks on the nation's roadways. The...
will county board meeting graphic.5

Will County Board Approves Permits for Landscaping Business and Restaurant Liquor Service in Frankfort Area

Article SummaryThe Will County Board unanimously approved three separate special use permits for businesses in the Frankfort area, allowing a landscaping operation in Green Garden Township to continue and two...
will county board meeting graphic.5

Board Approves Engineering Contracts for Mokena Road Widening

Article SummaryThe Will County Board approved over $1.1 million in supplemental engineering contracts to advance the ongoing 80th Avenue improvement project in Mokena. The additional funding addresses project delays and...
will county board meeting.6

Will County Awards $1.46 Million Contract for Kankakee Street Bridge Replacement in Manhattan Township

Article SummaryThe Will County Board has awarded a $1.46 million contract to "D" Construction, Inc. of Coal City to replace the Kankakee Street Bridge over Jackson Creek in Manhattan Township....
will county board meeting.6

Crete Township Community Center to Get New Digital Sign

Article Summary: The Will County Board approved a special use permit and two variances for Crete Township, allowing for the installation of a new on-premise dynamic display sign at its...