Monee Board Approves $455,580 Payment for Fireman’s Park Phase 2 Construction
Village of Monee Board of Trustees Meeting | May 13, 2026
Article Summary: The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for work completed on the second phase of improvements at Fireman’s Park, after the village’s engineer and staff certified the invoice.
Fireman’s Park Phase 2 Key Points:
- The board approved Pay Request No. 2 to Metropolitan Corporation in the amount of $455,580.
- The payment covers work completed through the pay period ending April 30, 2026.
- Farnsworth Group and village staff reviewed the invoice and found the work in substantial compliance with the contract and engineering plans.
- The vote was 6-0.
MONEE — The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for ongoing construction at Fireman’s Park, advancing the second phase of improvements at the village’s growing recreation complex.
The payment, processed as Pay Request No. 2, covers work completed during the pay period ending April 30, 2026, the village administrator told the board in presenting the item. He said the Farnsworth Group, the village’s engineering consultant, and village staff had reviewed the invoice and found the work to be in substantial compliance with the contract and engineering plans, certifying it for payment.
The board action requested was a motion to approve the payment to Metropolitan Corporation in the amount of $455,580. Following a motion and a second, the board approved it on a 6-0 roll-call vote.
The payment continues a multi-phase buildout of Fireman’s Park. According to Mayor Therese Bogs’s State of the Village remarks earlier in the meeting, the park’s first phase was completed in September and included a football, soccer and lacrosse field; two sand volleyball courts; a youth baseball field with a retractable pitching mound and two batting cages; bleachers; a concession stand with restrooms; a new parking lot; an ADA-compliant playground; and connecting ADA sidewalks. A pet “micro pantry” was also installed. Trustee Heidi Gonzalez noted during the parks and recreation report that the Fireman’s baseball field recently held a grand opening.
Latest News Stories
Supreme Court could redefine 14th Amendment application
Missouri year in review: capital gains eliminated, Medicaid increased
2025 in review: Historic border security actions taken by Trump
Free speech under fire nearly 300 times in 2025 on campus
IL rep: As if Bears ‘had a plan to rob the bank’ before considering Indiana
Meeting Summary and Briefs: Crete-Monee Board of Education for December 16, 2025
Undersheriff Brian Conser Retires After 29 Years of Service
FBI to scrap $5 billion move, Patel says
AGs say ‘As You Sow’ may violate antitrust laws with anti-fossil fuel alliance
IL dyslexia screening takes effect Jan. 1, drawing reading instruction debate
Colorado Springs, Denver residents pay among lowest property taxes in U.S.
Illinois quick hits: Pope reacts to Pritzker bill signing