Monee Board Approves $455,580 Payment for Fireman’s Park Phase 2 Construction
Village of Monee Board of Trustees Meeting | May 13, 2026
Article Summary: The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for work completed on the second phase of improvements at Fireman’s Park, after the village’s engineer and staff certified the invoice.
Fireman’s Park Phase 2 Key Points:
- The board approved Pay Request No. 2 to Metropolitan Corporation in the amount of $455,580.
- The payment covers work completed through the pay period ending April 30, 2026.
- Farnsworth Group and village staff reviewed the invoice and found the work in substantial compliance with the contract and engineering plans.
- The vote was 6-0.
MONEE — The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for ongoing construction at Fireman’s Park, advancing the second phase of improvements at the village’s growing recreation complex.
The payment, processed as Pay Request No. 2, covers work completed during the pay period ending April 30, 2026, the village administrator told the board in presenting the item. He said the Farnsworth Group, the village’s engineering consultant, and village staff had reviewed the invoice and found the work to be in substantial compliance with the contract and engineering plans, certifying it for payment.
The board action requested was a motion to approve the payment to Metropolitan Corporation in the amount of $455,580. Following a motion and a second, the board approved it on a 6-0 roll-call vote.
The payment continues a multi-phase buildout of Fireman’s Park. According to Mayor Therese Bogs’s State of the Village remarks earlier in the meeting, the park’s first phase was completed in September and included a football, soccer and lacrosse field; two sand volleyball courts; a youth baseball field with a retractable pitching mound and two batting cages; bleachers; a concession stand with restrooms; a new parking lot; an ADA-compliant playground; and connecting ADA sidewalks. A pet “micro pantry” was also installed. Trustee Heidi Gonzalez noted during the parks and recreation report that the Fireman’s baseball field recently held a grand opening.
Latest News Stories
Illinois Quick Hits: State gaming board renew Rockford casino license
Arizona GOP pushes to protect Colorado River’s limited water
Republicans challenge Clyde in Georgia’s 9th District
Fort Bragg soldier’s case continues Tuesday in New York
Justice Department drops Federal Reserve probe, kicks to watchdog
Pritzker: ‘Need for speed’ for megaprojects bill with tax breaks
NYC schools probed over claims of antisemitism
Illinois Quick Hits: AFP says tax breaks would be more at Soldier Field
Soldier’s insider trading case puts prediction markets to the test
U.S. will continue blockade ‘as long as it takes,’ Hegseth says
Will County Takes Jurisdiction of Countyline Road in $1.84 Million Agreement with Kankakee County
Green Garden Township’s Wildflower Farm Granted Third Special Use Extension