Monee Board Approves $455,580 Payment for Fireman’s Park Phase 2 Construction
Village of Monee Board of Trustees Meeting | May 13, 2026
Article Summary: The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for work completed on the second phase of improvements at Fireman’s Park, after the village’s engineer and staff certified the invoice.
Fireman’s Park Phase 2 Key Points:
- The board approved Pay Request No. 2 to Metropolitan Corporation in the amount of $455,580.
- The payment covers work completed through the pay period ending April 30, 2026.
- Farnsworth Group and village staff reviewed the invoice and found the work in substantial compliance with the contract and engineering plans.
- The vote was 6-0.
MONEE — The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for ongoing construction at Fireman’s Park, advancing the second phase of improvements at the village’s growing recreation complex.
The payment, processed as Pay Request No. 2, covers work completed during the pay period ending April 30, 2026, the village administrator told the board in presenting the item. He said the Farnsworth Group, the village’s engineering consultant, and village staff had reviewed the invoice and found the work to be in substantial compliance with the contract and engineering plans, certifying it for payment.
The board action requested was a motion to approve the payment to Metropolitan Corporation in the amount of $455,580. Following a motion and a second, the board approved it on a 6-0 roll-call vote.
The payment continues a multi-phase buildout of Fireman’s Park. According to Mayor Therese Bogs’s State of the Village remarks earlier in the meeting, the park’s first phase was completed in September and included a football, soccer and lacrosse field; two sand volleyball courts; a youth baseball field with a retractable pitching mound and two batting cages; bleachers; a concession stand with restrooms; a new parking lot; an ADA-compliant playground; and connecting ADA sidewalks. A pet “micro pantry” was also installed. Trustee Heidi Gonzalez noted during the parks and recreation report that the Fireman’s baseball field recently held a grand opening.
Latest News Stories
Will County Board Upholds Zoning Denials, Rejecting Developer Appeals
Split Vote Halts Monee Truck Terminal Project
Future Quarry Fight Looms as Board Approves ‘Tequila Barrel’ Retreat
News Briefs from the Will County Board June 18 Meeting
Board Promotes Collaboration as Construction Progresses on New Athletic Complex
District Finances Show Marked Improvement After Revenue Challenges
C-M School Board June 17 Meeting Briefs
Frankfort Approves Outdoor Patios for The Loft and Grounded Coffee Bar, Waives All Parking Requirements
Frankfort Police Department to Get Four New Vehicles in Fleet Upgrade
Indoor Pickleball Facility ‘Pickled!’ Gets Green Light in Frankfort
Frankfort to Install Public Wi-Fi at Breidert Green
Frankfort Board Approves Indoor Recreation Facility and Setback Variance
Meeting Briefs: Frankfort Village Board for June 16, 2025
Mental Health Board Awards $5 Million in Grants to Will County Organizations