—Photo by Glenn P. Knoblock

Forest Preserve District Advances Major Extensions and Repairs on Plum Creek Greenway Trail in Crete Township

Spread the love

Article Summary: The Forest Preserve District is currently undertaking dual construction projects on the Plum Creek Greenway Trail, initiating a massive 1.5-mile southern extension through Plum Valley Preserve and commencing repairs on an 80-foot bridge damaged by a fallen tree in Goodenow Grove Nature Preserve.

Plum Creek Greenway Trail Projects Key Points:

  • A new 1.5-mile trail extension will connect Plum Valley Preserve to Goodenow Grove Nature Preserve in Crete Township, with an estimated completion date of fall 2026.

  • The extension features the installation of 800 feet of elevated concrete boardwalks and a 150-foot bridge over Plum Creek, which will become the District’s largest single-span bridge.

  • Repairs began in early March on an 80-foot bridge in Goodenow Grove that was heavily damaged by a fallen tree in January 2025. Contractors are installing new footings, supports, and decking.

  • Future phases of the trail extension aim to connect the path north into Cook County and south to Beecher via the proposed Vincennes Trail.

  • The projects are locally funded by the Forest Preserve District’s Capital Improvement Program and a 2024–2028 grant from the Chicago Metropolitan Agency for Planning.

The Forest Preserve District announced in early March that dual construction projects are currently underway to expand and repair the Plum Creek Greenway Trail, promising significant upgrades for outdoor recreation in Crete Township and the surrounding Will County communities.

The most expansive of the two projects is a new 1.5-mile trail extension that will head south, winding through a hilly section of Plum Valley Preserve. The new multi-use trail will feature a 10-foot-wide path with 3-foot turf shoulders on each side. The extension will consist of a half-mile of crushed limestone, a half-mile of asphalt, and a half-mile street route.

The short street connection will be marked with explicit street signs and pavement directions, leading path users from the newly built trail section to an existing 3.15-mile leg of the Plum Creek Greenway Trail at Goodenow Grove Nature Preserve. The new construction is being added to an existing 1-mile crushed limestone segment that extends south from the Plum Valley Preserve entrance and dog park.

“Upon completion, the project will eliminate a gap in the existing trail system, resulting in a continuous greenway trail connection between Goodenow Grove Nature Preserve and the Plum Valley Preserve – Burville Road access,” said Colleen Novander, the Forest Preserve District’s director of planning and land preservation.

To navigate sensitive ecological areas, contractors are actively installing sections of a precast concrete pedestrian boardwalk to elevate the path. Crews will lay down one 600-foot section and another 200-foot section of boardwalk, utilizing massive concrete components that weigh 4,000 pounds each.

Additionally, concrete abutments are being poured and cured to support a new bridge spanning Plum Creek. Expected to be installed later in April, the 150-foot structure will be the largest single-span bridge in the District.

To minimize environmental impact to existing natural features like wetlands, ravines, and sensitive habitats, the engineering phase dictated that construction remain confined to a designated corridor with a maximum width of 100 feet.

The extension project, which carries an estimated completion date of fall 2026, is funded by the Forest Preserve District’s Capital Improvement Program. Supplemental funding support is provided through the Chicago Metropolitan Agency for Planning’s (CMAP) 2024–2028 Locally Programmed Transportation Alternatives Program (TAP-L).

Looking ahead, District officials noted that future phases of the trail will provide a critical north–south connection, eventually extending the path north into Cook County and south to the Village of Beecher via the proposed Vincennes Trail.

Goodenow Grove Bridge Repairs
While the extension moves forward, a separate set of contractors began repair work in early March on an existing bridge located in the eastern section of Goodenow Grove Nature Preserve, near East Bemes Road.

The 80-foot bridge, which sits just north of the preserve’s well-known “big bridge,” was significantly damaged in January 2025 when a large tree fell on the structure. Following the incident, the District consulted engineers to determine if the bridge required a total replacement or if it could be salvaged. Engineers ultimately concluded that the structure could be repaired.

Originally built in 2011 in tandem with the initial construction of the Plum Creek Greenway Trail and a capital redesign project at Goodenow Grove, the bridge requires extensive rehabilitation. Contractors are currently replacing one of the bridge’s main support structures and pouring new concrete footings. Additionally, all of the bridge’s decking and railings will be entirely replaced.

“It will look like a brand new bridge,” stated Chris Moeller, a Forest Preserve operations department supervisor.

The section of the Plum Creek Greenway Trail affected by the damage has been closed to the public since the tree fell in January. District officials anticipate the repairs will take several weeks to complete, noting that weather and other factors could impact the timeline. The trail segment will officially reopen once the reconstruction is finalized.

—Photo by Glenn P. Knoblock

Leave a Comment





Latest News Stories

Will County Board Graphic.04

Legislative Committee: Lobbyists Report on Federal Shutdown and Legislative Outlook

Legislative Committee Meeting | February 3, 2026 Article Summary: Federal lobbyists provided the Legislative Committee with an update on the partial government shutdown and the status of appropriations bills. While...
Illinois proposal makes businesses financially liable for climate change

Illinois proposal makes businesses financially liable for climate change

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – A proposal to create an Illinois Climate Change Superfund is drawing sharp criticism from Republican lawmakers...
Illinois unemployment rate tops national average; state ends 2025 with fewer jobs

Illinois unemployment rate tops national average; state ends 2025 with fewer jobs

By Glenn Minnis | The Center Square contributorThe Center Square (The Center Square) – Illinois State Rep. Chris Miller argues numbers tell the story as new U.S. Bureau of Labor...
Dozens arrested during ongoing unrest in Minneapolis

Dozens arrested during ongoing unrest in Minneapolis

By Elyse ApelThe Center Square Anti-ICE protests continued in Minneapolis over the weekend, resulting in dozens of arrests by local law enforcement. Protesters gathered at the Bishop Henry Whipple Federal...
Illinois Quick Hits: Iowa wants Illinois' counties

Illinois Quick Hits: Iowa wants Illinois’ counties

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – An Iowa state lawmaker has introduced legislation that would establish a committee to study the potential transfer...
Despite vast elderly population, Florida lags other states in stopping Medicaid fraud

Despite vast elderly population, Florida lags other states in stopping Medicaid fraud

By Mark StricherzThe Center Square (The Center Square)—In Florida, a state with more elderly people than any other, state government officials lag their peers in deterring fraud in a popular...
Will County Finance Logo

County Authorizes Financial Study of Homer Glen Law Enforcement Contract

Finance Committee Meeting | February 3, 2026 Article Summary: The Finance Committee voted to authorize a professional study to evaluate the true cost of providing law enforcement services to the...
Will County Board Graphic.01

Will County Public Works Debates Future Bridge Needs as 159th Street Closure Looms

Public Works & Transportation Committee Meeting | February 3, 2026 Article Summary: A discussion regarding the future deck repair of the 159th Street bridge in Lockport sparked a debate about...
Everyday Economics: Cooling jobs, a cautious Fed, and a housing recovery that needs confidence

Everyday Economics: Cooling jobs, a cautious Fed, and a housing recovery that needs confidence

By Orphe DivounguyThe Center Square The week ahead is framed by three macro threads that are increasingly pulling against each other: a Federal Reserve that is debating how restrictive policy...
Fierce races to determine control of Congress

Fierce races to determine control of Congress

By Andrew RiceThe Center Square Even as states across the country introduce and pass legislation to reshape congressional districts to favor one political party over another, several states that have...
EXCLUSIVE: Superintendent group webinar details school response to ICE

EXCLUSIVE: Superintendent group webinar details school response to ICE

By Esther WickhamThe Center Square The American Association of School Administrators hosted a members-only virtual webinar last week, providing school leaders with guidance on how to respond to potential encounters...
11 of 37 Mexican nationals extradited to U.S. being prosecuted in Texas

11 of 37 Mexican nationals extradited to U.S. being prosecuted in Texas

By Bethany BlankleyThe Center Square Eleven of 37 Mexican nationals extradited to the U.S. from Mexico are being prosecuted in Texas. The extradition was the largest transfer of fugitives in...
Will County Board Graphic.02

Capital Imp Committee: Veterans Assistance Commission Set to Move into New Facility

Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026 Article Summary: The Will County Veterans Assistance Commission (VAC) is scheduled to move into its new headquarters at...
will county board meeting.6

Capital Imp Committee: Health Dept Elevator Repair Costs Significantly Lower Than Estimates

Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026 Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to...
will county board graphic

Legislative Committee Adopts 2026 Federal Legislative Agenda

Legislative Committee Meeting | February 3, 2026 Article Summary: The Will County Legislative Committee finalized and approved the 2026 Federal Legislative Agenda, outlining the county's top priorities for Congress. The...