Emily Anderson of CBBEL speaks with a concerned resident at the WCDOT Open House on March 19-photo by Andrea Arens

Will County DOT Hosts Open House on Manhattan-Monee Road Project

Spread the love

By Andrea Arens

Article Summary:

Will County officials are in the early planning stages of a long-term improvement project along Manhattan-Monee Road, with construction likely years away. At a March 19 open house in Peotone, residents learned the project is part of a larger corridor effort involving three separate projects, each with different timelines and funding sources. While the county now oversees the roadway, key decisions—such as intersection design—will ultimately be made by the state.

Green Garden, IL: The Will County Department of Transportation (WCDOT) held a public open house on March 19 at Peotone Intermediate Center to present early plans and gather community input on a proposed improvement project along Manhattan-Monee Road.

The project covers a two-mile stretch from U.S. Route 45 to Center Road in unincorporated Green Garden Township. The roadway was recently transferred from the Illinois Department of Transportation (IDOT) to WCDOT, giving the county responsibility for planning and future improvements.

Currently in Phase I, the project is focused on evaluating existing conditions. Engineers are reviewing roadway design, drainage, traffic patterns, and crash data while developing and comparing potential improvement options. This phase also includes identifying any future property acquisition needs.

According to project materials, the county’s goals include improving pavement conditions, enhancing roadside safety, accommodating current and future traffic demand, minimizing utility impacts, and supporting multi-modal transportation.

The project is one of three separate efforts along the Manhattan-Monee Road corridor. Another project involving intersection improvements at Center Road has drawn local attention due to its connection to ongoing discussions about the closure of Peotone Intermediate Center within Peotone School District 207U.

Emily Anderson of CBBEL Engineering, the firm overseeing this specific project, said her team is only responsible for this segment. She noted that each corridor project is being handled by different engineering firms but coordinated through Will County.

Officials also clarified that, unlike some of the other corridor improvements, this project is not funded with federal dollars, which affects its timeline. While Phase II engineering is tentatively scheduled for 2026–2027 and construction (Phase III) for 2028, attendees were told that actual construction may not begin until 2031, when funding is expected to be available.

During construction, planners anticipate keeping at least one lane of traffic open to reduce disruptions.

Questions from residents also focused on future intersection design, particularly whether a traffic signal or roundabout would be installed. Officials explained that although WCDOT now oversees the roadway, IDOT retains jurisdiction over intersections, meaning the state will make the final decision on traffic control features.

Residents were encouraged to provide feedback either at the open house or through the project website (www.manhattan-monee-study.com) as planning continues.

A poster board discussed alternatives for the corridor-photo by Andrea Arens.

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Monee Village Board for July 23, 2025

The Monee Village Board of Trustees heard a detailed presentation for a major industrial redevelopment, approved a significant payment for its nearly-completed public works facility, and gave final clearance for...
Meeting Briefs

Meeting Summary: Peotone School District 207-U for July 21, 2025

District Weighs Budget Cuts vs. More Debt: Peotone schools must create a state-mandated deficit reduction plan to address a recurring ~$2 million operating shortfall. The Board of Education is debating whether...
Peotone-School-Cmte-Of-Whole-July-21.4

Summer Construction Projects Transforming Peotone Schools

Major construction projects are progressing on schedule across Peotone School District 207-U, with significant HVAC upgrades, new secure entrances, and extensive paving work transforming campuses ahead of the new school...
Meeting Briefs

Meeting Summary and Briefs: Monee Township Board for June 19, 2025

Monee Township Board Meeting | June 19, 2025 The Monee Township Board met on Thursday, June 19, 2025, to handle monthly business, including the approval of building maintenance contracts and...
Peotone-School-Cmte-Of-Whole-July-21.2

Peotone Schools to Launch “Go Big Blue” Unity Initiative

Peotone School District 207-U will rally under a new theme, “Go Big Blue,” for the 2025-26 school year in a comprehensive initiative aimed at unifying the district around common character...
Peotone-School-Cmte-Of-Whole-July-21.2

Peotone FFA Alumni Propose Privately Funded Greenhouse to Expand Program

The Peotone High School agriculture program could see a major expansion after the Peotone FFA Alumni and Friends group presented a proposal to the Board of Education to privately fund...
peotone library graphic logo.2

Peotone Library Faces ‘Enormous’ Cost for Major Plumbing Replacement

Article Summary: The Peotone Public Library District is facing a significant and unexpected expense after a construction consultant recommended a full replacement of a cast iron plumbing pipe. Library Director...
peotone library graphic logo.4

Peotone Library Faces ‘Enormous’ Cost for Major Plumbing Replacement

Article Summary: The Peotone Public Library District is facing a significant and unexpected expense after a construction consultant recommended a full replacement of a cast iron plumbing pipe. Library Director...
peotone library graphic logo.1

Peotone Library District to Explore Potential Expansion into Monee

Article Summary: The Peotone Public Library District is officially considering an expansion of its physical services after the Board of Trustees agreed to form a committee to study the possibility...
peotone library graphic logo.1

Peotone Library District to Explore Potential Expansion into Monee

Article Summary: The Peotone Public Library District is officially considering an expansion of its physical services after the Board of Trustees agreed to form a committee to study the possibility...
peotone library graphic logo.4

Library Board Adopts New Spending and Conduct Policies

Article Summary: The Peotone Public Library Board of Trustees approved two key governance documents, an "Authority to Spend" policy and a "Board Code of Conduct," to clarify financial procedures and...
peotone library graphic logo.4

Library Board Adopts New Spending and Conduct Policies

Article Summary: The Peotone Public Library Board of Trustees approved two key governance documents, an "Authority to Spend" policy and a "Board Code of Conduct," to clarify financial procedures and...
Meeting Briefs

Meeting Summary and Briefs: Peotone Public Library District Board for June 17, 2025

The Peotone Public Library District Board of Trustees tackled significant issues at its June meeting, highlighted by news of a potentially "enormous" cost to repair major plumbing infrastructure in the...
Meeting Briefs

Meeting Summary and Briefs: Peotone Public Library District Board for June 17, 2025

The Peotone Public Library District Board of Trustees tackled significant issues at its June meeting, highlighted by news of a potentially "enormous" cost to repair major plumbing infrastructure in the...
Peotone-School-Cmte-Of-Whole-July-21.3

Peotone Schools Face Mandatory Deficit Plan, Weighs Cuts Against More Debt

Peotone School District 207-U is facing a state-mandated deficit reduction plan as its tentative fiscal year 2026 budget projects a nearly $2 million annual operating shortfall, a recurring issue that...