Monee Village Board Approves Tax Increment Financing Agreement for Voortman Steel Facility

Spread the love

Monee Village Board of Trustees Meeting | March 11, 2026

Article Summary: The Monee Village Board of Trustees unanimously approved a redevelopment agreement for Voortman USA Corp., pledging 80% of eligible Tax Increment Financing (TIF) funds to reimburse the developer for infrastructure costs, while securing a $351,000 donation for a new community park.

Voortman Redevelopment Agreement Key Points:

  • The village will reimburse 80% of TIF-eligible project costs, up to approximately $5.6 million, funded entirely by incremental property taxes generated by the site with zero interest.

  • Village Attorney Lawrence R. Gryczewski clarified that the $7.9 million eligible cost figure listed on the agenda was a typo, stating the actual eligible costs are roughly $6.9 million.

  • Upon receiving an occupancy permit, Voortman will donate $351,000 to the village to offset the cost of building a community park near Ridgeland Avenue, which will be named after the company.

  • The developer is constructing a manufacturing facility off Ridgeland Avenue, expected to be completed by June 2026.

MONEE, Ill. — The Monee Village Board of Trustees on Wednesday, March 11, 2026, finalized a major redevelopment agreement with Voortman USA Corp., granting the manufacturer significant tax increment financing (TIF) incentives in exchange for local infrastructure improvements and a substantial community park donation.

Village Attorney Lawrence R. Gryczewski presented the agreement to the board, noting that Voortman is currently constructing a facility off Ridgeland Avenue that should be completed by June of this year. While the draft Redevelopment Agreement in the agenda packet described the project as a 411,000-square-foot manufacturing facility, Gryczewski stated during the meeting that the facility will be “roughly 120,000 square foot.”

Gryczewski also corrected a typo listed on the meeting’s public agenda. While the agenda stated the developer requested 80% of $7.9 million in TIF-eligible costs, Gryczewski clarified the actual eligible costs sit at $6.9 million.

“The village is offering 80% of those TIF costs, which is about $5.6 million, as collateral for that payment,” Gryczewski explained. “The village would pledge 80% of the tax increment to pay that obligation to Voortman. There is no interest on this money.”

The attorney emphasized that the reimbursement is not a general obligation of the village. The payments will be made strictly from the Special Tax Increment Allocation Fund (STAF), generated by the increased property taxes of the newly developed site. Once the developer is reimbursed or the TIF expires, the village’s obligation ends.

According to the granular details of the Redevelopment Agreement provided in the agenda packet, the village secured a direct community benefit as part of the negotiations. Upon the issuance of the occupancy permit, Voortman is required to submit $351,000 to the village. The funds will be used to help offset the cost of building a new community park near Ridgeland Avenue. In recognition of the donation, the village has agreed to name the site “Voortman Industries, Inc. Park” for as long as the developer maintains a presence in Monee.

The board approved the redevelopment agreement unanimously. Gryczewski noted that a formal TIF note, establishing the payment schedule—which the village requested be processed annually in January—will be brought before the board for final approval at the next meeting.

Leave a Comment





Latest News Stories

Medicaid-logo

Federal Reconciliation Bill Targets Medicaid, SNAP Programs

Will County Legislators Briefed on Potential Local Impacts Federal legislation making sweeping cuts to Medicaid and food assistance programs could significantly impact Will County residents and services, county legislators learned...
will-county-board.2

Will County Approves Modified $756 Million Transportation Plan Despite Terminology Debate

Will County's Public Works and Transportation Committee approved a five-year, $756 million transportation improvement plan on June 3, but not before a heated debate over whether to call it a...
will-county-board.3

Will County completes major projects while others move forward

Will County's facilities team has completed several major projects while advancing others throughout the county, officials reported during a Capital Improvements & IT Committee meeting Monday. The Old Courthouse Plaza...
will-county-board.3

Will County Accepts $140,000 Developer Donation for Road Improvements

Will County's Public Works and Transportation Committee accepted a $140,143.90 donation from a developer in lieu of constructing traffic improvements along Laraway Road. The donation comes from the Lakes Park...
will-county-board.2

State Legislative Session Wrap-Up Shows Mixed Results

Will County's state legislative priorities saw mixed results as the Illinois General Assembly concluded its spring session on May 31, with several key bills advancing while others stalled. The Legislative...
will-county-board.2

Will County expands safety initiatives across facilities

Will County has implemented new safety protocols and training programs across its facilities, including the selection of department safety monitors and participation in community health education events. Each county department...
will-county-board.3

Leglislative Committee Meeting Briefs

Federal Grant Deadline Extended: The Surface Transportation Reauthorization deadline has been extended to May 30 for policy submissions, with both House and Senate committees actively seeking stakeholder input ahead of...
will-county-board.3

Speed Limits Reduced on Two Township Roads

The committee approved new speed zones for two township roads based on engineering studies showing current limits exceed safe driving speeds. Offner Road in Green Garden Township will have a...
will-county-board.2

Will County Finance Committee Approves Juvenile Detention Center Upgrades

Committee votes to keep facility operational, moves forward with compliance modifications Will County Finance Committee members voted unanimously Monday to recommend keeping the River Valley Detention Center operational and making...
will-county-board.2

Major Grade Separation Projects Advance with Engineering Contracts

The committee approved two significant engineering agreements for major railroad overpass projects totaling over $4 million. TranSystems Corporation received a $4,003,256 contract for construction engineering services on the Lorenzo Road...
County-Board-Room

County Authorizes Condemnation for Francis Road Project

The committee authorized the State's Attorney's Office to proceed with condemnation cases for right-of-way acquisition needed for Francis Road improvements between Gougar Road and Interstate 80. Eight property parcels are...
will-county-board

Solar Farm Access Approved for Manhattan-Arsenal Road

The committee granted access approval for a solar farm development on Manhattan-Arsenal Road approximately 1,000 feet east of Cherry Hill Road. The MCH Solar 1 project, developed by Soltage LLC,...
will-county-board.3

Will County Finance Committee Meeting Briefs

Budget Transfers Approved: The Finance Committee approved transferring $18,643 within the Supervisor of Assessments budget to move funds from software licensing to computer hardware purchases. Animal Protection Services Funding: Committee...
will-county-board.2

Public Works Committee Briefs

Major Projects Update: Construction continues on several major projects including the 80th Avenue expressway overpass, Laraway Road widening near Cedar Road, and Bell Road improvements. The Bell Road project at...
will-county-board

Capital Improvements & IT Committee Briefs

Bed donation program: Will County donated old beds from Sunny Hill Nursing Home to Joliet Junior College and Project Cure after the nursing home received all new beds for residents....