Soltage Drops Battery Storage Plans, Secures Extensions for Two Crete Solar Projects
Will County Board Meeting | February 19, 2026
Article Summary: The Will County Board granted second extensions to special use permits for two solar energy projects in Crete Township. The developer, Soltage, has removed battery energy storage systems from the plans.
Crete Solar Extensions Key Points:
-
Projects: Crete Cottage Grove Solar 1, LLC and Crete Goodenow Solar 1, LLC.
-
Locations: Northwest corner of Munz Road/South Cottage Grove Ave; Northeast corner of E. Goodenow Road/Dutton Road.
-
Change: Battery Energy Storage Systems (BESS) removed from both projects.
-
Vote: Both extensions passed 16-3.
The Will County Board on Thursday, February 19, 2026, approved second extensions for two commercial solar energy facilities in Crete Township, extending their special use permits through August 2026.
The projects, owned by Soltage, are located at the northwest corner of Munz Road and South Cottage Grove Avenue, and the northeast corner of East Goodenow Road and Dutton Road.
Land Use staff confirmed that while the original approvals included battery energy storage systems (BESS), the applicant has decided not to pursue battery storage at these locations.
“The applicant has decided to not move forward with the battery energy storage system for this site; the special use permit for the BESS is considered null and void,” stated Marguerite Kenny of the Land Use Department in a memo to the board.
Board Member Judy Ogalla (R-Monee) sought clarification on the ownership. “Is the current owner for this also Soltage?” she asked. Staff confirmed Soltage is the owner and noted that the original zoning cases were handled by a different applicant before being sold.
The board voted 16-3 to approve both extensions. Voting against the extensions were members Deane-Schlottman, Balich, and Berkowicz.
Latest News Stories
Public Works Facility and Firemen’s Park Set for Grand Openings
Meeting Summary and Briefs: Will County Board for September 18, 2025
Monee Approves 5-Year Police Contract with Retroactive Pay
County Board Abates Over $25 Million in Property Taxes for Bond Payments
Trucking Facility Proposal Sparks Debate Over Pavement and De-Annexation
Meeting Summary and Briefs: Monee Township Board for Aug. 2025
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Will County Grants Extensions to Five Solar Projects Sold to New Developers
Will County Board Approves Controversial Drug Recovery Retreat in Crete Township
Attorney Advises Board Against Reissuing 18-Year-Old Check