Capital Imp Committee: Health Dept Elevator Repair Costs Significantly Lower Than Estimates
Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026
Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to $20,000, avoiding a potential replacement cost of over $1 million. Facilities staff confirmed the unit is suitable for the building’s needs.
Facilities Key Points:
-
Repair Cost: The final repair bill is estimated between $18,000 and $20,000.
-
Cost Avoidance: Initial fears suggested a full replacement could have exceeded $1 million.
-
In-House Projects: Facilities staff saved money by framing and hanging judge photos at the courthouse internally.
-
Efficiency: The department completed over 750 work orders in the last month with a 98% completion rate.
JOLIET — A potentially budget-breaking elevator issue at the Will County Health Department was resolved for a fraction of the feared cost, Facilities Director William Fern reported to the Capital Improvements and IT Committee on Tuesday, Jan. 6, 2026.
During a facilities update, Chair Mica Freeman (D-Plainfield) requested the final cost for the elevator repair, noting that previous discussions had raised concerns about the unit’s suitability and the potential need for a total replacement.
“I think it was about $18,000 to $20,000,” Fern said.
Freeman noted this was significantly under the $30,000 to $40,000 estimates discussed previously, and far below the cost of a full replacement.
“Or the over million to replace, right?” Fern added. “So I think they got to the root cause of the issue from the initial install and were able to repair it.”
Fern confirmed that the existing elevator was deemed suitable for the space, eliminating the need for major construction.
In other facilities news, Fern highlighted a project at the Will County Courthouse where maintenance staff framed and hung photos of current and past judges on the third floor.
“Originally, we got a quote. It was pretty expensive. It was over like $18,000 for a contractor to do it,” Fern said.
By utilizing the Sheriff’s carpentry staff and county facilities personnel, the project was completed in-house for a “fraction of the cost.” However, Fern noted that a few photos were hung out of order and will be corrected.
Fern also reported that the department continues to operate efficiently, saving the county over $118,000 in evaporation credits on cooling towers at the courthouse to date.
Latest News Stories
WATCH: Gun ban with SCOTUS; ICE enforcement pushback; End of life options bill with gov
Meeting Summary and Briefs: Crete-Monee School District 201-U for November 2025
U.S. Supreme Court takes up Michigan foreclosure case
Grand jury declines to re-indict Letitia James
U.S. Supreme Court upholds Texas’ new congressional maps
In last four years, five northern states saw most illegal crossings
Illinois quick hits: Another attack on CTA passenger; plaintiffs move to dismiss their ICE use of force case
Some push for FDA approval of psychedelic treatments for veterans
WATCH: Pritzker: ‘No’ to state taxpayer-funded guaranteed income
WATCH: IL congresswoman willing to withhold highway dollars over CDL issues
Disability group, coroners press governor ahead of assisted suicide decision
35 lawmakers unveil bipartisan health care proposal, beg leadership to adopt it