Article Summary: The Landfill Committee voted to move forward with engineering estimates for a fourth compressor at the Prairie View Renewable Natural Gas (RNG) facility. The $1.8 million investment aims to reduce downtime and increase revenue, despite concerns about funding sources and timing.

RNG Plant Key Points:

  • Downtime Costs: Data shows that feed compressor failures account for nearly 36% of plant downtime, costing the county an estimated $600,000 annually in lost revenue.

  • Proposed Solution: Installing a fourth compressor would ensure three units are always operational, maximizing gas production and revenue. The estimated cost is $1.8 million with a 3-5 year return on investment.

  • Budget Concerns: The purchase was not included in the current fiscal year budget. Officials discussed using remaining funds from the previous year or splitting the cost across two budget cycles due to a 46-week lead time for the equipment.

Will County officials are taking steps to boost efficiency and revenue at the Prairie View Renewable Natural Gas (RNG) plant by pursuing the addition of a fourth feed compressor.

At the Landfill Committee meeting on Tuesday, January 13, 2026, Dave Hartke, Director of the Resource Recovery & Energy Division, presented data highlighting the financial impact of equipment failures. The facility’s three existing compressors are the primary cause of outages, leading to significant revenue losses.

“If we have three feed compressors operating at all times… we’re going to be producing closer to 27 to 2900 mm BTUs,” Hartke explained, noting this would allow the plant to hit higher revenue tiers faster each month.

The proposed fourth unit, estimated at $1.8 million fully installed, would provide redundancy. However, the plan faced scrutiny regarding its financing. Board Member Sherry Newquist questioned the timing, noting, “This kind of stuff is so much easier to deal with during the budget process.”

Hartke admitted the request was not in the original budget due to a prior focus on austerity. “I wasn’t quite expecting the response… that we should move forward with it,” he said, referencing earlier informal discussions with committee leadership.

Despite the budget hurdle, the committee saw the long-term value. With a 46-week lead time for the equipment, Finance Director Marcy indicated the cost could potentially be split across two fiscal years.

Board Member Jim Richmond emphasized the need for a deeper analysis before cutting a check. “This is a massive business decision… We need to actually look at that plant and make sure that it is spec’d properly from the front door to the back door,” Richmond said.

Ultimately, the committee voted unanimously to authorize staff to proceed with obtaining firm engineering costs and a project plan, which will then be brought back for final financial approval.

Leave a Comment





Latest News Stories

Illinois bill sparks debate over police privacy vs. public access

Illinois bill sparks debate over police privacy vs. public access

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – An Illinois lawmaker and law enforcement officer says a controversial proposal to change how police records...
Signature process begins to ban large data centers in Ohio

Signature process begins to ban large data centers in Ohio

By David BeasleyThe Center Square Sponsors of a proposed constitutional amendment that would ban the construction of any new large data centers in Ohio have cleared another hurdle in getting...
U.S. Supreme Court agrees to hear veteran's benefits challenge

U.S. Supreme Court agrees to hear veteran’s benefits challenge

By Andrew RiceThe Center Square The U.S. Supreme Court agreed on Monday to hear an Army veteran's challenge over reduced disability benefits. The court agreed to hear Johnson v. United...
Supreme Court declines to hear challenge to Illinois public transport gun ban

Supreme Court declines to hear challenge to Illinois public transport gun ban

By Andrew RiceThe Center Square The U.S. Supreme Court on Monday declined to decide whether individuals can carry firearms on public transportation. The court declined to take up Schoenthal v....
Illinois Quick Hits: Report says Pekin Bowling Center 'taxed out of business'

Illinois Quick Hits: Report says Pekin Bowling Center ‘taxed out of business’

By Jim Talamonti | The Center SquareThe Center Square Sunset Lanes in Pekin is set to close later this month as the bowling center’s owner says it is being “taxed...
Tiffany vows to end subsidies for data centers in Wisconsin

Tiffany vows to end subsidies for data centers in Wisconsin

By Jon StyfThe Center Square Wisconsin congressman and candidate for governor Tom Tiffany said that he will “end subsidies for data centers in Wisconsin” if he becomes governor. Tiffany was...
Crete Monee School Board Graphic.1

Meeting Summary and Briefs: Crete-Monee School District 201-U for March 10, 2026

Crete-Monee School District 201-U Meeting | March 10, 2026 The Crete-Monee School District 201-U Board of Education met as a Committee of the Whole on Tuesday, March 10, 2026, to...
Monee Graphic.1

Meeting Summary and Briefs: Monee Village Board of Trustees for March 25, 2026

Monee Village Board of Trustees Meeting | March 25, 2026 The Monee Village Board of Trustees met on Wednesday, March 25, 2026, to approve major economic development agreements, amend local...
Monee Township Graphic.3

Monee Township Reports Over $4,200 in General Assistance, Highlights Community Programs

Monee Township Board of Trustees Meeting | February 19, 2026 Article Summary: Monee Township distributed over $4,200 in General and Emergency Assistance to residents between mid-January and mid-February. Supervisor Donna...
Firefighter age bill stalled despite union backing

Firefighter age bill stalled despite union backing

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – A proposed Illinois bill aimed at addressing firefighter shortages by lowering the minimum hiring age has...
Will County Board Land Use Committee Graphic.3

County Board Members Pitch “Granny Flats,” Hobby Farm Zoning, and Farmland Mitigation in LRMP Brainstorm

Will County Board Land Use & Development Committee Meeting | March 26, 2026 Article Summary: During a brainstorming workshop for the county's new Land Resource Management Plan, Will County Board...
Monee elementary School

Financing Fails for MEC Property Buyer, Board Weighs Keeping Earnest Money

Crete-Monee School District 201-U Meeting | March 10, 2026 Article Summary: The prospective buyer of the district's MEC building failed to secure financing, prompting the Crete-Monee Board of Education to consult...
Hyundai Translead

Will County Board Approves Tax Abatement for $345 Million Hyundai Translead Project

Will County Board Meeting | March 19, 2026 Article Summary: The Will County Board has authorized an agreement of intent to abate taxes for a massive $345 million manufacturing project...
Lawmaker criticizes surplus spending bill

Lawmaker criticizes surplus spending bill

By Catrina Baker | The Center Square contributorThe Center Square (The Center Square) – A proposal aimed at helping local governments manage retiree health care costs is drawing differing views...
Village of Monee Graphic

Monee Updates Dumpster Ordinance to Include ‘Bagsters,’ Issues Code Compliance Reminders

Monee Village Board of Trustees Meeting | March 25, 2026 Article Summary: The Village of Monee officially amended its municipal code to restrict the use of soft-sided "bagster" dumpsters and issued...