Public Works Committee: $18.8 Million Contract Awarded for Lorenzo Road Bridge Over BNSF Railway
Will County Public Works & Transportation Committee Meeting | January 6, 2026
Article Summary: A contract for nearly $18.9 million was confirmed for the construction of a new bridge carrying Lorenzo Road over the BNSF Railway. The project, fully funded by BNSF, is critical for safety and serves as a nuclear evacuation route.
Lorenzo Road Bridge Project Key Points:
-
Contractor: “D” Construction, Inc. of Coal City, IL.
-
Bid Amount: $18,872,967.20.
-
Project Scope: Construction of a new grade separation (bridge) to replace the at-grade crossing.
-
Timeline: Construction is estimated to start in February 2026 with completion by November 2027.
The Will County Board Public Works & Transportation Committee on Tuesday, January 6, 2026, confirmed the award of an $18,872,967.20 contract to “D” Construction, Inc. for the construction of a bridge carrying Lorenzo Road (County Highway 80) over the BNSF Railway.
The project is located in County Board District 1. According to Director of Transportation Jeff Ronaldson, the project is being funded entirely by BNSF Railway but administered by the county.
“They are funding the entirety of this project. We have to build it because we’re named in the ICC order and related to the grant, but they will reimburse us in total,” Ronaldson said.
The project addresses a significant bottleneck caused by the BNSF rail yard expansion. Trains often slow down or stop while entering the yard, blocking the crossing for extended periods.
“You got those two-mile trains closing that crossing for a significant amount of time,” Ronaldson explained.
Committee Member Dave Oxley (R-Lockport) noted the road’s importance as an evacuation route for the nearby nuclear power plant. Ronaldson confirmed this factor contributed to the project’s priority.
A temporary runaround road will be constructed to keep traffic flowing during the project. The contract calls for completion by November 19, 2027.
Latest News Stories
Meeting Summary and Briefs: Will County Board Public Works & Transportation Committee for May 5, 2026
Will County Legislative Committee: Pushes Forward with Ban on Cryptocurrency Kiosks
Monee Elementary ‘Bike Bus’ Initiative Promotes Safe Routes and Healthy Habits
Will County Health Department Warns of Potential Federal Funding Cuts and Rising Healthcare Costs for FY2027
Highland Liquors Cleared for Video Gaming Expansion Following Zoning Approval
Rich Township Edges Crete-Monee in 10-9 Conference Thriller
Crete-Monee Offense Powers 18-3 Rout of Rich Township
Access Will County Dial-A-Ride Reports Massive Growth After Consolidating Paratransit Services
Crete-Monee School Board Advances $17 Million Abatement for Ongoing Capital Projects
Legislative Committee Advances Resolution Opposing Kidney Disease Treatment Delegation Act
Commission Approves Massive Lake Michigan Water Infrastructure Project for Troy Township
Committee: Capital Improvements Committee Weighs $300 Million Options for Downtown Joliet Campus
Rich Township Offense Powers Past Crete-Monee, 21-4
Crete-Monee Offense Powers 18-8 Victory Over Rich Township