Construction Payments Approved for Crete-Monee Facility Upgrades

Spread the love

Crete-Monee Board of Education Meeting | December 16, 2025

Article Summary: The Crete-Monee School District 201-U Board of Education on Tuesday, Dec. 16, 2025, approved several large payments totaling more than $550,000 for ongoing construction and athletic facility projects at the high school and middle school. Officials also noted that major structural work at the middle school is scheduled to take place over the winter break.

Construction Update Key Points:

  • High School Concession Stand: The board approved a $345,476.37 payment to Bear Construction for work on the new concession facility.

  • Middle School Addition: A payment of $109,069.66 was approved for Bear Construction for renovations at the University Park campus.

  • Athletics Facility: The board authorized $103,931.90 for Byrne & Jones Construction for work completed on the high school athletics facility.

  • Winter Break Timeline: Steel beams are scheduled to be set at the middle school starting Monday, Dec. 22.

The Crete-Monee School District 201-U Board of Education on Tuesday, Dec. 16, 2025, authorized significant expenditures to settle invoices for major facilities projects nearing completion. The payments are part of a broader effort to modernize district campuses and athletic infrastructure.

A payment of $345,476.37 was issued to Bear Construction for the Crete-Monee High School concession stand project. According to financial documents, the project has reached a current contract total of approximately $4.5 million, with only a small balance remaining to finish.

The board also approved $109,069.66 for Bear Construction for the addition and renovations at Crete-Monee Middle School in University Park. Assistant Superintendent for Business and Operations Jason Okrasinski informed the board that construction is progressing rapidly.

“It’s our intention to start to set the steel beams Monday, Dec. 22, and work diligently on that over winter break,” Okrasinski said. He noted that the goal is to have the structural steel set before students return to the building to ensure maximum safety.

Additionally, the board cleared a payment of $103,931.90 to Byrne & Jones Construction for work on the high school’s athletics facility. When asked about the final details of the sports facilities, administrators noted that while the primary work is complete, crews are still finishing dugouts, installing furniture, and waiting for light installations on the baseball and softball fields.

Leave a Comment





Latest News Stories

Illinois Quick Hits: Pritzker wants tariffs refund after court ruling

Illinois Quick Hits: Pritzker wants tariffs refund after court ruling

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Gov. J.B. Pritzker says President Donald Trump owes the families of Illinois and the United States about...
Municipal League: Housing reform could strip authority from local communities

Municipal League: Housing reform could strip authority from local communities

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Illinois Municipal League says a new proposal for housing reform could allow the state to take...
Illinois Quick Hits: 15-year-old charged with machine gun possession

Illinois Quick Hits: 15-year-old charged with machine gun possession

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – Two teens are facing weapons charges after Illinois State Police executed search warrants in Carbondale on Wednesday....
Screenshot 2026-02-18 at 2.04.09 PM

Trustees Approve Over $445,000 for Pond Restoration and Park Improvements

Monee Village Board Meeting | Feb. 11, 2026 Article Summary: The Village Board approved two significant infrastructure expenditures regarding the restoration of the Iris Lane West Pond and ongoing improvements at...
Illinois quick hits: Illinois Supreme Court sued over judge's removal

Illinois quick hits: Illinois Supreme Court sued over judge’s removal

By Jim Talamonti | The Center SquareThe Center Square Illinois Supreme Court sued over judge's removal The Liberty Justice Center has filed a federal civil rights lawsuit against Illinois Supreme...
CPA gives tips for avoiding red flags for NGOs getting taxpayer money

CPA gives tips for avoiding red flags for NGOs getting taxpayer money

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – A certified public accountant that works with nonprofits says if they’re getting public money, they should have...
Pritzker 'very disappointed' as Bears, Indiana move closer to stadium deal

Pritzker ‘very disappointed’ as Bears, Indiana move closer to stadium deal

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Chicago Bears are one step closer to leaving Illinois after an Indiana House committee approved stadium...
Chicago Loop retail vacancy rate on decline

Chicago Loop retail vacancy rate on decline

By Glenn Minnis | The Center Square contributorThe Center Square (The Center Square) – Chicago Loop Alliance President Michael Edwards argues change is good when it comes to the new...
Op-Ed: Illinois’ lawsuit climate is hurting small businesses

Op-Ed: Illinois’ lawsuit climate is hurting small businesses

By Keith BattagliaThe Center Square Running a small business in Illinois already means navigating high taxes, rising insurance premiums, and increasing regulatory and operational costs. For many of us, just...
Screenshot 2026-02-18 at 2.18.25 PM

C-M Committee of Whole: District Considers Sale of Life Safety Bonds to Fund $9 Million in Improvements

Crete-Monee School Board Meeting | Feb. 10, 2026 Article Summary: The School Board discussed selling Life Safety Bonds to proactively address facility maintenance at Monee Elementary and Crete-Monee High School without...
Screenshot 2026-02-18 at 2.18.10 PM

C-M Committee of Whole: Staff Survey Reveals Split Opinion on Calendar; Board Set to Approve Traditional Schedule

Crete-Monee School Board Meeting | Feb. 10, 2026 Article Summary: The Crete-Monee School Board reviewed survey results showing a nearly even split among staff regarding how to handle emergency closures, with...
Screenshot 2026-02-18 at 2.03.55 PM

Monee Board Authorizes Negotiations for Voortman Steel Redevelopment Agreement

Monee Village Board Meeting | Feb. 11, 2026 Article Summary: The Monee Village Board voted to allow village administration to negotiate a redevelopment agreement with Voortman Steel to assist the company...
Meeting Briefs

Meeting Summary and Briefs: Public Health & Safety Committee for February 5, 2026

Public Health & Safety Committee Meeting | February 5, 2026 Meeting SummaryThe Will County Board Public Health & Safety Committee met on Tuesday, February 5, 2026, to review departmental reports...
Will County Finance Logo

Meeting Summary and Briefs: Finance Committee for February 3, 2026

Finance Committee Meeting | February 3, 2026 The Will County Finance Committee met on Tuesday, February 3, 2026, to address critical facility needs and review the county's financial standing. The...
Will County P&Z Logo Planning Zoning

Fairmont Neighborhood Plan Update Prioritizes Infrastructure and Beautification Following Demographic Shift

Planning and Zoning Commission Meeting | February 3, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously approved an update to the Fairmont Neighborhood Plan, addressing significant demographic...