Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion
Article Summary:
The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a mid-August occupancy following the recent installation of a long-delayed electrical panel.
Public Works Building Key Points:
-
Payment request #13 for $566,134.16 to Professional Building Services Inc. was unanimously approved.
-
The facility is nearing completion after a key electrical panel, which had been on back order, was installed this week.
-
Occupancy is anticipated by mid-August, with a grand opening to be scheduled at a later date.
MONEE — The Village of Monee’s new Public Works facility is nearing the finish line, with the Village Board approving another major payment for the project at its Wednesday meeting.
Trustees unanimously authorized pay request #13 in the amount of $566,134.16 to the project’s construction manager, Professional Building Services Inc. The payment covers work completed through July 10, including significant progress from contractors for concrete, masonry, general construction, and flooring.
Public Works Trustee Doug Horne provided a construction update, highlighting a critical milestone. “If you recall last time we met here, there was a discussion of a delayed electrical panel and it was on back order,” Horne said. “Well, I’m happy to report that that is being installed this week.”
With the panel in place, the factory startup of essential systems is scheduled for the week of July 28. A preliminary walkthrough for building staff is planned for the week of August 4.
“We’re hopeful to have occupancy of the building by mid-August,” Horne added. “The grand opening is yet to be scheduled. We’ll worry about that once it’s online.”
The payment request was reviewed and certified by the Farnsworth Group and village staff, who confirmed it met the project’s plans and specifications.
Latest News Stories
Meeting Summary and Briefs: Will County Finance Committee for March 3, 2026
Comptroller, state lawmaker call for federal tax credit scholarships
Peotone Public Library District Hires Product Architecture for Feasibility Study
Nash Brubaker’s Two Home Runs Power Herscher Past Crete-Monee, 5-2
Meeting Summary and Briefs: Monee Village Board of Trustees for March 11, 2026
Monee Adopts Resolution to Waive Surety Bonds for Municipal Work in IDOT Right-of-Ways
Monee Approves $39,114 Purchase of John Deere Gator for Winter Sidewalk Maintenance
Ramirez Homers, Steals Four Bases as Crete-Monee Offense Overwhelms Thornton Fractional South, 18-8
Monee Village Board Approves Tax Increment Financing Agreement for Voortman Steel Facility
Meeting Summary and Briefs: Monee Village Board of Trustees for February 25, 2026
Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road
Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition