Summer Construction Projects Transforming Peotone Schools
Major construction projects are progressing on schedule across Peotone School District 207-U, with significant HVAC upgrades, new secure entrances, and extensive paving work transforming campuses ahead of the new school year.
Facilities director Mike Singleton provided the Board of Education with a detailed update on the summer’s work during its July 21 meeting. The removal of the mobile classroom units at Peotone Junior High School is complete, and large-scale mechanical projects are well underway.
At Peotone High School, a new chiller has been installed, with the factory startup scheduled for the following day. At Peotone Elementary School, a 150-foot crane was recently on-site to lift new rooftop HVAC units into place. Inside, the installation of copper piping is 100% complete and duct work is approximately 85% finished, keeping the project on track for a phased turnover to cleaning crews starting in early August.
The district’s security is also being enhanced with the installation of new secure vestibules. The inner set of doors at the junior high has been installed, with the outer doors and new concrete work scheduled for the coming weeks. Similar work is being completed at Peotone Elementary and Peotone Intermediate Center.
Additionally, extensive concrete patching and seal coating have been completed or are in progress at the junior high, high school, and Connor Shaw Center, refreshing the appearance and safety of parking lots and drop-off areas. While the projects create a tight turnaround for teachers to prepare classrooms, administrators are “very cautiously optimistic” that all buildings will be ready for the start of school.
Monee Events
Latest News Stories
Board Approves $1.2 Million Payout for Road Construction and New Park Accessibility Lift
Monee Implements Local Grocery Tax to Replace Expired State Tax
Monee Proposes Expansion of TIF District 5 to Spur Development
Your Ultimate Guide to the 2025 Frankfort Fall Fest: Everything to Know for the Nationally-Ranked Event
Meeting Summary and Briefs: Monee Township Board for July 2025
Meeting Summary and Briefs: Village of Monee Board for August 13, 2025
Clerk Reports Single Bid of $635,000 for Road Improvements
Board Advances Development Plans for Industrial Drive
After Initial Rejection and Tense Debate, Board Reconsiders and Approves Contested DuPage Township Business
Meeting Summary and Briefs: Will County Board for August 21, 2025
Will County Board Approves New Fee Schedule for Recorder of Deeds
Will County Board Formally Opposes Heavier, Longer Trucks on National Roadways