Summer Construction Projects Transforming Peotone Schools
Major construction projects are progressing on schedule across Peotone School District 207-U, with significant HVAC upgrades, new secure entrances, and extensive paving work transforming campuses ahead of the new school year.
Facilities director Mike Singleton provided the Board of Education with a detailed update on the summer’s work during its July 21 meeting. The removal of the mobile classroom units at Peotone Junior High School is complete, and large-scale mechanical projects are well underway.
At Peotone High School, a new chiller has been installed, with the factory startup scheduled for the following day. At Peotone Elementary School, a 150-foot crane was recently on-site to lift new rooftop HVAC units into place. Inside, the installation of copper piping is 100% complete and duct work is approximately 85% finished, keeping the project on track for a phased turnover to cleaning crews starting in early August.
The district’s security is also being enhanced with the installation of new secure vestibules. The inner set of doors at the junior high has been installed, with the outer doors and new concrete work scheduled for the coming weeks. Similar work is being completed at Peotone Elementary and Peotone Intermediate Center.
Additionally, extensive concrete patching and seal coating have been completed or are in progress at the junior high, high school, and Connor Shaw Center, refreshing the appearance and safety of parking lots and drop-off areas. While the projects create a tight turnaround for teachers to prepare classrooms, administrators are “very cautiously optimistic” that all buildings will be ready for the start of school.
Latest News Stories
Frankfort Board Approves New Wendy’s on Route 30 With Numerous Modifications
Historic Downtown Frankfort Property Granted Deck and Patio Variances
Frankfort Approves $1.3 Million in Bills, Including Annual Insurance Payment
Meeting Briefs: Frankfort Village Board for June 2, 2025
Frankfort Park Board Holds Closed-Door Talks on Five Oaks HOA Dispute
Frankfort Township Approves Employee Raises, Details Major Infrastructure and Service Projects
New High-End Bar ‘Ace & Vine’ Gets Green Light from Township Board
Golf Carts Not Permitted on Township Roads, Supervisor Clarifies
Meeting Briefs: Frankfort Township Board for May 19, 2025
Will County Board Rejects Two Solar Farm Projects After Heated Public Opposition
County Approves $15 Million Water System Takeover for Southeast Joliet Area
Board Postpones County Purchasing Code Overhaul Amid Union Contractor Debate
Monee Township approves $12,000 in community funding, fills planning commission vacancy
New Frankfort Square Park Board Takes Helm Amid Strong Financials, Maksymiak and Moore Elected Leaders