Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

Will County Board Graphic.01

Meeting Summary and Briefs: Will County Public Health & Safety Committee for April 2, 2026

Will County Public Health & Safety Committee Meeting | April 2, 2026 The Will County Board Public Health and Safety Committee met on Thursday, April 2, 2026, to review comprehensive...
law and authority lawyer concept, judgment gavel hammer in court courtroom for crime judgement legislation and judicial decision, judge having justice of punishment guilt and criminal verdict legal

Indiana Man Faces Federal Indictment, Potential Death Penalty for Momence Bar Owner’s Murder

Article Summary: State prosecutors have officially transferred the first-degree murder case against Julius Burkes to the U.S. Department of Justice. The 47-year-old Indiana man now faces federal charges, including the...
Crete Monee Warriors Softball Graphic

Ramirez’s Historic Day, 22-Hit Barrage Power Crete-Monee Softball Past Bloom 20-8

Fueled by an unstoppable offensive performance, the Crete-Monee varsity softball team pounded out 22 hits and cruised to a 20-8, six-inning conference victory over host Bloom on Wednesday afternoon. Crete-Monee...
Crete Monee Warriors Baseball Graphic

Bloom Survives Early Onslaught, Holds Off Crete-Monee 7-6

The Crete-Monee varsity baseball team showcased tremendous fight and aggressive baserunning, but ultimately fell a run short as visiting Bloom escaped with a 7-6 conference victory on Wednesday afternoon. The...
Will County Board Graphic.01

Ad-Hoc Committee: New State Laws Force Shift in How Police Handle Student Cannabis and Tobacco Violations

Will County Board Ad-Hoc Ordinance Review Committee Meeting | April 14, 2026 Article Summary: As Will County updates its drug offense ordinances to align with changing state cannabis laws, officials...
Will County P&Z Logo Planning Zoning.2

Peotone Township Homeowner Secures Porch P&Z Variance Despite Local Objection

Will County Planning and Zoning Commission Meeting | April 7, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously approved a street yard setback variance for an unpermitted...
Will County P&Z Logo Planning Zoning.2

Manhattan Township Property Owners Secure Zoning P&Z Approvals for Pole Barn Addition, Parcel Consolidation

Will County Planning and Zoning Commission Meeting | April 7, 2026 Article Summary: The Will County Planning and Zoning Commission unanimously approved two separate zoning requests in Manhattan Township, granting...
Fire-Ambulance-Rescue-Logo

Mercaptan Pipeline Leak Causes Strong Odors Across University Park and Monee

Article Summary: A mercaptan pipeline leak near Hamilton and Bond in University Park has prompted local fire departments to issue urgent safety guidance as utility crews work to repair the...
FTC takes action against ad giants for avoiding certain sites

FTC takes action against ad giants for avoiding certain sites

By Jay Brown | Legal NewslineThe Center Square WASHINGTON - The Federal Trade Commission and eight states have sued three of the country’s largest advertising agencies for allegedly conspiring not...
Illinois Quick Hits: Feds put card swipe fees prohibition on hold

Illinois Quick Hits: Feds put card swipe fees prohibition on hold

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The U.S. Treasury Department’s Office of the Comptroller of the Currency has released notice of a pending...
Calif. climate change lawsuits paused during SCOTUS review

Calif. climate change lawsuits paused during SCOTUS review

By John O’Brien | Legal NewslineThe Center Square Lawsuits over climate change in California will be on hold while the U.S. Supreme Court decides whether they can be pursued. San...
U.S. will strike Iran infrastructure with no deal, Hegseth warns

U.S. will strike Iran infrastructure with no deal, Hegseth warns

By Andrew RiceThe Center Square The U.S. military is prepared to strike Iran's energy infrastructure if it does not agree to a peace deal, War Secretary Pete Hegseth said on...
Screenshot 2026-04-16 at 7.16.08 AM

Prime Diesel Repair Earns Favorable Recommendation for Outside Storage Use

Monee Planning & Zoning Board of Appeals Meeting | April 15, 2026 Article Summary: The Monee Planning and Zoning Board of Appeals on Wednesday gave a favorable recommendation for Prime...
New North Carolina law, question on facts pivotal to Mosley appeal

New North Carolina law, question on facts pivotal to Mosley appeal

By Alan WootenThe Center Square Action by North Carolina’s General Assembly has changed the timing for medical malpractice, and enough evidence to ask a jury to resolve contested facts favor...
Will County Board Graphic.02

Meeting Summary and Briefs: Will County Board Legislative Committee for April 7, 2026

Will County Board Legislative Committee Meeting | April 7, 2026 The Will County Board Legislative Committee met on Tuesday, April 7, 2026, to review a packed agenda of state and...