Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

Screenshot 2026-04-16 at 7.16.08 AM

Meeting Summary and Briefs: Monee Planning & Zoning Board of Appeals for April 15, 2026

Monee Planning & Zoning Board of Appeals Meeting | April 15, 2026 The Monee Planning and Zoning Board of Appeals convened on Wednesday, April 15, 2026, under the acting chairmanship...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board Executive Committee for April 9, 2026

Will County Board Executive Committee Meeting | April 9, 2026 The Will County Board Executive Committee met on Thursday, April 9, 2026, to process a diverse agenda featuring major strategic,...
Rock Run Preserve —Photo by Chad Merda

On the road to 100 years: How the Forest Preserve District expanded

As the Forest Preserve District approaches its centennial year in 2027 with a total of nearly 24,000 protected acres, it’s a good time to reflect on how the District grew...
peotone library graphic logo.4

Peotone Library Board Appoints Rebecca Markus to Fill Vacant Trustee Seat

Peotone Public Library District Meeting | March 19, 2026 Article Summary: The Peotone Public Library District Board of Trustees selected Rebecca Markus to fill a vacant seat on the board...
Crete Monee Warriors Baseball Graphic

Aggen’s Perfect Day at the Plate, Late Surge Power Tinley Park Past Crete-Monee 15-9

The Tinley Park varsity baseball team unleashed a relentless offensive assault on Saturday, pounding out 17 hits and pulling away late to defeat host Crete-Monee 15-9 in a high-scoring non-conference...
Screenshot 2026-04-16 at 7.16.08 AM

P&Z Advances Residential Variances for Garage and Aluminum Fence Additions

Monee Planning & Zoning Board of Appeals Meeting | April 15, 2026 Article Summary:The Monee Planning and Zoning Board of Appeals advanced two residential variance requests, endorsing the construction of...
Will County Board Graphic.04

Meeting Summary and Briefs: Will County Board Ad-Hoc Ordinance Review Committee for April 14, 2026

Will County Board Ad-Hoc Ordinance Review Committee Meeting | April 14, 2026 The Will County Board Ad-Hoc Ordinance Review Committee held a highly efficient meeting on Tuesday, April 14, 2026,...
Will County Board Graphic.01

Executive Committee Advances Sweeping Updates to Adult Entertainment and Wireless Facilities Ordinances

Will County Board Executive Committee Meeting | April 9, 2026 Article Summary: The Will County Board Executive Committee advanced two major ordinances completely rewriting the county's regulations for Adult Entertainment...
Crete Monee Warriors Softball Graphic

Ramirez, Robinson Power Crete-Monee’s 25-Hit Barrage in Wild 28-17 Win Over Bloom

The Crete-Monee varsity softball team unleashed a staggering 25-hit offensive onslaught on Thursday, outlasting conference rival Bloom in a wild, high-scoring 28-17 home victory. The marathon contest featured a combined...
Crete Monee Warriors Baseball Graphic

Love’s Shutout, Offensive Explosion Propel Crete-Monee Past Bloom 18-0

Staking an early claim with a massive first inning, the Crete-Monee varsity baseball team delivered a commanding all-around performance to defeat host Bloom 18-0 in a four-inning conference matchup on...
Will County Board Graphic.02

Ad-Hoc Committee: County Lowers Air Rifle Age to 13, Finds Airsoft Guns Beyond Local Regulatory Reach

Will County Board Ad-Hoc Ordinance Review Committee Meeting | April 14, 2026 Article Summary: The Will County Ad-Hoc Ordinance Review Committee advanced updates to its public peace ordinances, lowering the...
Will County Board Graphic.03

Executive Committee Approves Local Fire District Appointments, Faces Pushback Over Delayed Elwood Seat

Will County Board Executive Committee Meeting | April 9, 2026 Article Summary: The Will County Executive Committee approved a slate of appointments for several fire protection districts, including Manhattan and...
Will County Finance Logo

Meeting Summary and Briefs: Will County Board Finance Committee for April 7, 2026

Briefs: Will County Board Finance Committee Meeting | April 7, 2026 The Will County Board Finance Committee met on Tuesday, April 7, 2026, to review and finalize the county's 2025...
Screenshot 2026-04-10 at 1.52.12 PM

Meeting Summary and Briefs: Monee Village Board for April 8, 2026

Monee Village Board Meeting | April 8, 2026 The Monee Village Board met on Wednesday, April 8, 2026, to advance several infrastructure payouts and begin hashing out the financial priorities...
Will County Board Graphic.03

Ad-Hoc Committee: County’s Lack of Home Rule Stifles Effort to Ban Kratom and Non-Nicotine Vapes

Will County Board Ad-Hoc Ordinance Review Committee Meeting | April 14, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee approved updates to its tobacco and alternative nicotine...