Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
Meeting Summary and Briefs: Will County Board Public Works & Transportation Committee for May 5, 2026
Will County Legislative Committee: Pushes Forward with Ban on Cryptocurrency Kiosks
Monee Elementary ‘Bike Bus’ Initiative Promotes Safe Routes and Healthy Habits
Will County Health Department Warns of Potential Federal Funding Cuts and Rising Healthcare Costs for FY2027
Highland Liquors Cleared for Video Gaming Expansion Following Zoning Approval
Rich Township Edges Crete-Monee in 10-9 Conference Thriller
Crete-Monee Offense Powers 18-3 Rout of Rich Township
Access Will County Dial-A-Ride Reports Massive Growth After Consolidating Paratransit Services
Crete-Monee School Board Advances $17 Million Abatement for Ongoing Capital Projects
Legislative Committee Advances Resolution Opposing Kidney Disease Treatment Delegation Act
Commission Approves Massive Lake Michigan Water Infrastructure Project for Troy Township
Committee: Capital Improvements Committee Weighs $300 Million Options for Downtown Joliet Campus
Rich Township Offense Powers Past Crete-Monee, 21-4
Crete-Monee Offense Powers 18-8 Victory Over Rich Township