Solar Project Extensions Approved as Industry Faces Permitting Delays
Three solar energy projects received 180-day extensions from Will County’s Land Use & Development Committee Thursday as developers continue working through lengthy permitting processes with utility companies and other agencies.
The extensions cover projects in Peotone, Channahon, and Crete townships that received special use permits in 2023 but haven’t yet obtained building permits. Under county rules, special use permits expire within two years unless construction permits are issued.
A Peotone Township solar project by Turning Point Energy received its extension after experiencing delays with updated conservation plans and changing fire district requirements. Joseph Chessup, representing the developer, said soil and water conservation standards were updated last year, requiring them to restart their conservation planning process.
The Manhattan Fire Protection District also changed safety standards as recently as May 20, requiring wider access roads and higher weight capacity to accommodate 80,000-pound fire equipment.
“There’s been a few unexpected delays with getting the permits finalized for this project,” Chessup said.
Staff also provided an update on solar interconnection requirements after meeting with ComEd officials. The utility company clarified that they don’t require above-ground power connections for solar projects, contrary to claims made by some developers.
ComEd uses a five-step process taking about 180 days for interconnection agreements. While they typically install four riser poles for connections, they can accommodate underground lines for 12KV systems, though 34KV lines remain economically impractical to bury.
The committee expressed interest in requiring more underground infrastructure for future solar projects to preserve rural aesthetics. “I would like to see us have them put it underground as much as they possibly can,” said Committee member Judy Ogala.
Latest News Stories
Meeting Summary and Briefs: Monee Village Board of Trustees for March 11, 2026
Monee Adopts Resolution to Waive Surety Bonds for Municipal Work in IDOT Right-of-Ways
Monee Approves $39,114 Purchase of John Deere Gator for Winter Sidewalk Maintenance
Ramirez Homers, Steals Four Bases as Crete-Monee Offense Overwhelms Thornton Fractional South, 18-8
Monee Village Board Approves Tax Increment Financing Agreement for Voortman Steel Facility
Meeting Summary and Briefs: Monee Village Board of Trustees for February 25, 2026
Will County Public Works Approves Access for 56-Acre Truck Services Hub on Manhattan-Monee Road
Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition
State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks
Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers
Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment
Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington