Monee Board Approves $455,580 Payment for Fireman’s Park Phase 2 Construction

Spread the love

Village of Monee Board of Trustees Meeting | May 13, 2026

Article Summary: The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for work completed on the second phase of improvements at Fireman’s Park, after the village’s engineer and staff certified the invoice.

Fireman’s Park Phase 2 Key Points:

  • The board approved Pay Request No. 2 to Metropolitan Corporation in the amount of $455,580.
  • The payment covers work completed through the pay period ending April 30, 2026.
  • Farnsworth Group and village staff reviewed the invoice and found the work in substantial compliance with the contract and engineering plans.
  • The vote was 6-0.

MONEE — The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for ongoing construction at Fireman’s Park, advancing the second phase of improvements at the village’s growing recreation complex.

The payment, processed as Pay Request No. 2, covers work completed during the pay period ending April 30, 2026, the village administrator told the board in presenting the item. He said the Farnsworth Group, the village’s engineering consultant, and village staff had reviewed the invoice and found the work to be in substantial compliance with the contract and engineering plans, certifying it for payment.

The board action requested was a motion to approve the payment to Metropolitan Corporation in the amount of $455,580. Following a motion and a second, the board approved it on a 6-0 roll-call vote.

The payment continues a multi-phase buildout of Fireman’s Park. According to Mayor Therese Bogs’s State of the Village remarks earlier in the meeting, the park’s first phase was completed in September and included a football, soccer and lacrosse field; two sand volleyball courts; a youth baseball field with a retractable pitching mound and two batting cages; bleachers; a concession stand with restrooms; a new parking lot; an ADA-compliant playground; and connecting ADA sidewalks. A pet “micro pantry” was also installed. Trustee Heidi Gonzalez noted during the parks and recreation report that the Fireman’s baseball field recently held a grand opening.

Leave a Comment





Latest News Stories

Will County P&Z Logo Planning Zoning

Crest Hill Homeowner Granted Side Yard Setback Variance for Accessible Addition

Will County Planning and Zoning Commission Meeting | March 3, 2026 Article Summary: The Will County Planning and Zoning Commission approved a side yard setback variance for a Crest Hill...
will county Committee-Legislative.Graphic

State Update: County Officials Raise Alarms Over Pritzker’s ADU Zoning Push and Data Center Tax Breaks

Legislative Committee Meeting | March 2026 Article Summary: During a state legislative update, Will County Board members expressed deep concerns over Governor J.B. Pritzker's continued push to mandate Accessory Dwelling Units...
Will County Public Works Committee

Committee Approves $317K Guardrail Maintenance Contract Amid Discussion on Installation Dangers

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: Will County officials approved an annual guardrail maintenance contract Tuesday while addressing national concerns over improperly installed...
Will County Board Graphic.03

Will County Approves Diamond Enterprise Zone Expansion to Support $355 Million Energy Investment

Will County Executive Committee Meeting | March 12, 2026 Article Summary: The Will County Executive Committee unanimously approved ordinances expanding the Diamond Enterprise Zone to include the Village of Braceville. The...
will county Committee-Legislative.Graphic

Federal Update: DHS Shutdown, War Powers, and Housing Legislation Dominate Washington

Legislative Committee Meeting | March 3, 2026 Article Summary: Will County's federal lobbyists briefed the Legislative Committee on a turbulent week in Washington, D.C., highlighting the passage of a major bipartisan...
Will County Finance Logo

Will County Corporate Revenues Surpass Expectations, Igniting Debate Over Delinquent Tax Sales

Will County Finance Committee Meeting | March 3, 2026 Article Summary: A routine review of the county’s year-end corporate fund revealed that revenues exceeded budgeted expectations by millions, largely driven by...
Will County Public Works Committee

Meeting Summary and Briefs: Will County Public Works and Transportation Committee for March 3, 2026

Will County Public Works and Transportation Committee Meeting | March 3, 2026 The Will County Public Works and Transportation Committee met on Tuesday, March 3, advancing millions of dollars in...
solar panels photovoltaics in solar farm

Will County Grants Extensions for Seven Solar and Commercial Projects Amid Permitting Delays

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: The Will County Land Use and Development Committee approved a slate of extensions for seven previously authorized...
Screenshot 2026-03-14 at 2.12.52 PM

Monee Explores Federal and Regional Grants to Improve Village Walkability

Monee Village Board of Trustees Meeting | February 25, 2026 Article Summary: Monee officials recently met with the Chicago Metropolitan Agency for Planning to identify long-term funding sources for expanding...
Will County Board Graphic.03

Will County Committee Postpones Liquor, Ad-Hoc Committee: Gaming, and Tobacco Ordinance Updates Amid Extensive Revisions

Will County Board Ad-Hoc Ordinance Review Committee Meeting | March 10, 2026 Article Summary: A Will County Board committee paused the advancement of major updates to the county's liquor, video...
Monee Graphic.1

Monee Approves Over $950,000 in Contractor Payouts for Road and Sidewalk Projects

Monee Village Board of Trustees Meeting | February 25, 2026 Article Summary: The Monee Village Board approved major payouts for the ongoing Industrial Drive reconstruction and the 2025 sidewalk improvement...
solar panels photovoltaics in solar farm

Land Use Committee Approves 4.98-Megawatt Solar Facility on Eagle Lake Road Near Peotone

Will County Land Use & Development Committee Meeting | March 5, 2026 Article Summary: Reversing a deadlocked Planning and Zoning Commission, the Will County Land Use and Development Committee unanimously approved...
Will County Board Graphic.04

Will County Advances Nearly $1.5 Million in Right-of-Way and Improvement Agreements for Weber, Gougar, and Laraway Roads

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Public Works and Transportation Committee authorized a slate of professional services and construction agreements Tuesday to...
Screenshot 2026-03-14 at 2.12.52 PM

Monee Trustees Push to Rezone Commercial Properties to Alleviate Red Tape for Homeowners

Monee Village Board of Trustees Meeting | February 25, 2026 Article Summary: Trustee Heidi Gonzalez voiced frustration over the village's zoning map, arguing that residential homes stuck in commercial zones...
Will County Public Works Committee

Public Works Committee: Approves $1.59 Million Contract for Scheer Road Bridge Replacement in Green Garden Township

Will County Public Works and Transportation Committee Meeting | March 3, 2026 Article Summary: The Will County Public Works and Transportation Committee on Tuesday advanced a nearly $1.6 million contract to...