Village of Monee Board of Trustees Meeting | May 13, 2026
Article Summary: The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for work completed on the second phase of improvements at Fireman’s Park, after the village’s engineer and staff certified the invoice.
Fireman’s Park Phase 2 Key Points:
- The board approved Pay Request No. 2 to Metropolitan Corporation in the amount of $455,580.
- The payment covers work completed through the pay period ending April 30, 2026.
- Farnsworth Group and village staff reviewed the invoice and found the work in substantial compliance with the contract and engineering plans.
- The vote was 6-0.
MONEE — The Monee Village Board on Tuesday, May 13, 2026, approved a $455,580 payment to Metropolitan Corporation for ongoing construction at Fireman’s Park, advancing the second phase of improvements at the village’s growing recreation complex.
The payment, processed as Pay Request No. 2, covers work completed during the pay period ending April 30, 2026, the village administrator told the board in presenting the item. He said the Farnsworth Group, the village’s engineering consultant, and village staff had reviewed the invoice and found the work to be in substantial compliance with the contract and engineering plans, certifying it for payment.
The board action requested was a motion to approve the payment to Metropolitan Corporation in the amount of $455,580. Following a motion and a second, the board approved it on a 6-0 roll-call vote.
The payment continues a multi-phase buildout of Fireman’s Park. According to Mayor Therese Bogs’s State of the Village remarks earlier in the meeting, the park’s first phase was completed in September and included a football, soccer and lacrosse field; two sand volleyball courts; a youth baseball field with a retractable pitching mound and two batting cages; bleachers; a concession stand with restrooms; a new parking lot; an ADA-compliant playground; and connecting ADA sidewalks. A pet “micro pantry” was also installed. Trustee Heidi Gonzalez noted during the parks and recreation report that the Fireman’s baseball field recently held a grand opening.
Latest News Stories
Signature process begins to ban large data centers in Ohio
U.S. Supreme Court agrees to hear veteran’s benefits challenge
Supreme Court declines to hear challenge to Illinois public transport gun ban
Illinois Quick Hits: Report says Pekin Bowling Center ‘taxed out of business’
Tiffany vows to end subsidies for data centers in Wisconsin
Meeting Summary and Briefs: Crete-Monee School District 201-U for March 10, 2026
Meeting Summary and Briefs: Monee Village Board of Trustees for March 25, 2026
Monee Township Reports Over $4,200 in General Assistance, Highlights Community Programs
Firefighter age bill stalled despite union backing
County Board Members Pitch “Granny Flats,” Hobby Farm Zoning, and Farmland Mitigation in LRMP Brainstorm
Financing Fails for MEC Property Buyer, Board Weighs Keeping Earnest Money
Will County Board Approves Tax Abatement for $345 Million Hyundai Translead Project