Will County Board Graphic.03

Will County Approves $2.9 Million Engineering Contract for Bluff Road Reconstruction in Channahon

Spread the love

Will County Public Works & Transportation Committee Meeting | April 7, 2026

Article Summary: The county is advancing a massive overhaul of Bluff Road in Channahon, approving a nearly $3 million Phase I and II engineering contract to prepare the corridor for full reconstruction, storm sewers, and potential retaining walls.

Bluff Road Engineering Key Points:

  • The committee approved a $2,955,607 contract with Peralte-Clark, LLC.

  • The project covers Bluff Road (CH 77) from the I-55 West Frontage Road to US Route 6.

  • The design will convert the existing rural, ditch-lined road into an urban cross-section with curb, gutter, and storm sewers.

  • The contract includes extensive geotechnical and environmental investigations due to the likelihood of encountering shallow bedrock and utility conflicts.

The Will County Board Public Works & Transportation Committee on Tuesday, April 7, 2026, unanimously approved a sweeping $2,955,607 professional services agreement with Peralte-Clark, LLC to engineer the total reconstruction of Bluff Road in Channahon.

The project targets a 5,900-foot, 1.1-mile stretch of Bluff Road (County Highway 77) between US Route 6 and the West Frontage Road of Interstate 55. Currently a two-lane major collector carrying roughly 5,850 vehicles per day, the roadway suffers from pavement deterioration, geometric deficiencies, and drainage issues.

According to the project scope detailed in the agenda packet, Peralte-Clark will guide the project through both Phase I (Preliminary & Environmental Engineering) and Phase II (Design Engineering). The ultimate goal is to convert the existing rural cross-section—characterized by aggregate shoulders and open ditches—into a modernized urban section featuring concrete curbs, gutters, and an enclosed storm sewer system.

The engineering task is highly complex due to the corridor’s specific geography. The contract includes significant subsurface investigations by subconsultants to identify areas of shallow bedrock, which could severely impact drainage design, excavation costs, and the placement of proposed retaining walls.

The Phase I study will evaluate up to four geometric alternatives, including two-lane and three-lane configurations, while also designing pedestrian and bicycle accommodations. The engineering team will also be required to navigate substantial utility conflicts, requiring a dedicated Subsurface Utility Engineering (SUE) evaluation.

The $2.95 million contract will be funded through a combination of County Motor Fuel Tax, RTA Tax, Highway Tax, and Matching Tax funds. According to the preliminary schedule, Phase II design is slated for completion by March 2027, with construction potentially beginning in June 2027.

Leave a Comment





Latest News Stories

Screenshot 2025-11-26 at 8.19.53 AM

Monee Awards $1.6 Million Contract for Firemen’s Park Phase 2

Village of Monee Board Meeting | November 19, 2025 Article Summary: The Monee Village Board awarded a $1.59 million contract to Metropolitan Corporation for the second phase of improvements at...
Monee Township Graphic.3

Highway Commissioner Reports Completion of $600,000 Road Improvement Project

Monee Township Board Meeting | Oct. 2025 Article Summary: Highway Commissioner David E. Deutsche reported the completion of major road work within the township, totaling over half a million dollars. The...
Will County P&Z Logo Planning Zoning.2

Zoning Cases in Crete and Manhattan Townships Postponed to December 16

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:Two zoning cases, one in Crete Township and another in Manhattan Township, were postponed by the Will County...
Will County P&Z Logo Planning Zoning

Will County Commission Approves New Lenox Variances, Overriding Staff’s Denial Recommendation

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission approved three variances for a 5.02-acre property in New Lenox Township,...
Screenshot 2025-11-26 at 8.13.37 AM

Planning Board Backs Re-Zoning and Expansion for Iroquois Paving

Monee Planning & Zoning Meeting | November 19, 2025 Article Summary: The Monee Planning and Zoning Board of Appeals has recommended approval for a series of requests from Iroquois Paving...
Monee Township Logo.1

Monee Township Proposes 7.75% Tax Levy Increase Following TIF Fund Release

Monee Township Board Meeting | Oct. 2025 Article Summary: Supervisor Donna Dettbarn announced a tentative tax levy increase for the upcoming fiscal year, citing the release of funds from a local...
Screenshot 2025-11-19 at 9.29.37 AM

Will County Executive Committee Delays Vote on School Choice Referendum

Will County Board Executive Committee Meeting | November 13, 2025 Article Summary: The Will County Board’s Executive Committee on Thursday, November 13, 2025, postponed a decision on whether to place an...
solar panels photovoltaics in solar farm

New Lenox Solar Farm Gains County Committee Approval with Conditions

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: A 63-acre commercial solar energy facility on Spencer Road in New Lenox Township received a key endorsement...
Will County Board Land Use Committee Graphic.1

Committee Approves Frankfort Township Gaming Bar on Split Vote

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: Despite an objection from Frankfort Township, a proposed video gaming bar on West St. Francis Road is...
Will County Board Land Use Committee Graphic.3

Crete Township Senior Group Home Gets Unanimous Committee Support

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: A proposal to convert a single-family home in Crete Township into a shared living facility for up...
Will County Board Land Use Committee Graphic.4

Beecher-Area Rezoning and Variances Approved to Legalize Structure

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: The Will County Land Use and Development Committee approved a rezoning and two variances for a property...
Will County Board Land Use Committee Graphic.2

Committee Approves Wilton Township Land Division Despite Spot Zoning Concerns

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: The Will County Land Use and Development Committee approved a request to rezone a 1.75-acre parcel in...
Meeting Briefs

Meeting Summary and Briefs: Will County Capital Improvements & IT Committee for November 4, 2025

Will County Capital Improvements & IT Committee Meeting | November 4, 2025 The Will County Capital Improvements & IT Committee on Tuesday, November 4, 2025, reviewed a successful bond refinancing...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for November 2025

Will County Public Works & Transportation Committee Meeting | November 2025 The Will County Public Works & Transportation Committee on Tuesday approved a landmark agreement to consolidate the Central Will...
Screenshot 2025-11-06 at 3.37.39 PM

Will County Committee Members Debate Future Capital Priorities, Clash on Borrowing

Will County Capital Improvements & IT Committee Meeting | November 4, 2025 Article Summary: After learning Will County could borrow over $100 million for new projects, members of the Capital Improvements...