Will County Explores Multi-Million Dollar Downtown Joliet Consolidation and City Partnership

Spread the love

Will County Capital Improvements & IT Committee Meeting | April 7, 2026

Article Summary: The Will County Capital Improvements and IT Committee reviewed four sweeping architectural options to consolidate county government facilities in downtown Joliet, including a potential partnership to build a joint complex with the City of Joliet. Financial advisors also presented bonding scenarios that could fund up to $142.8 million in construction without raising the county’s current annual debt service.

Facilities Master Plan Key Points:

  • Space projections indicate the County Office Building needs to grow from its current 62,260 square feet to 118,000 square feet by 2050.

  • Wight & Company presented four consolidation options for downtown Joliet, ranging from a standalone county facility on the old courthouse site to a “mega consolidation” housing both county and city government.

  • City of Joliet City Manager Beth Beatty addressed the committee, expressing strong support for a joint “one-stop shop” facility.

  • Speer Financial presented three borrowing scenarios, showing the county could issue between $103.9 million and $142.8 million in new bonds while maintaining its targeted $25 million annual debt service.

  • The county currently leases the “PACE building” at 9 Osgood Street to the City of Joliet for $1 a year on a 99-year lease.

The Will County Board Capital Improvements & IT Committee on Tuesday, April 7, 2026, took its first major step toward a massive overhaul of its downtown Joliet footprint, reviewing four architectural consolidation scenarios that could fundamentally reshape local government operations.

Jason Dwire of Wight & Company presented the updated Facilities Master Plan, highlighting the urgent need to replace or expand the current County Office Building (COB) and the MCO Building, which currently houses the State’s Attorney and Probation departments. According to the data, the county’s core government functions currently occupy 62,260 square feet but will require 118,000 square feet by 2050.

“This building here, it doesn’t really accommodate all of the county government functions,” Dwire said, referencing a map showing county offices scattered across downtown. “It certainly doesn’t meet any of the projected needs going forward. The same is true in the MCO building… Both buildings are going to need significant continued investment to maintain them, and they’re not in the best layout or best shape to begin with.”

Dwire outlined four distinct options for the committee, all of which heavily utilize the site of the now-demolished old courthouse:

  • Option 1: Consolidate all county government functions into a new 164,100-square-foot building on the old courthouse site. A separate Judicial Annex and parking garage (260,700 sq. ft.) would be built south of the new courthouse for the State’s Attorney and Public Defender.

  • Option 2: Build a joint 247,100-square-foot facility on the old courthouse site housing both Will County Government and the City of Joliet. A 269,800-square-foot Judicial Annex would be built south of the new courthouse.

  • Option 3: Consolidate all county needs—including the State’s Attorney and Public Defender—into one massive 277,200-square-foot building. This would allow the county to abandon the MCO site entirely, potentially offering it to the City of Joliet for a new City Hall (estimated 82,400 sq. ft.).

  • Option 4: A “mega consolidation” placing Will County Government, Judicial Agency Offices, and the City of Joliet into a single 385,600-square-foot complex on the old courthouse site, accompanied by a 230,400-square-foot parking garage.

The prospect of a joint county-city complex drew significant interest from the committee and the City of Joliet. Joliet City Manager Beth Beatty attended the meeting to confirm the city’s willingness to partner.

“The council, the mayor, and I… we have a wonderful working relationship with the county, and we are struggling just as you are with our city hall. I don’t have enough places to put people that we’re hiring now,” Beatty said. “We love the idea of a combined building with the county, so it’s a one-stop shop for constituents.”

Mike Mahony, speaking on behalf of the county executive’s office, noted that a joint facility would offer massive economies of scale, from sharing a single HVAC system and security entrance to utilizing a shared civic boardroom for both County Board and City Council meetings.

To fund such a monumental project, the committee reviewed a debt update prepared by Anthony Miceli of Speer Financial. Following a highly successful bond refinancing in October 2025 that saved the county $5,739,302.60, the county’s debt service payments are positioned to drop off significantly after 2031.

Assuming the issuance of 20-year General Obligation (Alternate Revenue Source) bonds, Speer Financial provided three scenarios that would allow the county to fund construction while keeping its overall annual debt payments level at a targeted $25 million:

  • Scenario 1: A single 20-year issuance in 2027 generating $103,995,000.

  • Scenario 2: A two-part issuance in 2027 and 2030 generating a combined $131,415,000.

  • Scenario 3: A three-part issuance in 2027, 2029, and late 2030 generating $142,810,000.

“You have space and capability to bond out,” Mahony explained. “These are all hypothetical scenarios. We don’t know if we are going to do anything. We don’t know what option we will be looking at… this was just to give you an idea that there is debt service capability for the county that would pay for a project of this magnitude.”

Board Member Steve Balich (R-Homer Glen) suggested an alternative to new construction: expanding the county-owned “PACE building” at 9 Osgood Street.

Mahony countered that the building is currently leased to the City of Joliet for $1 a year on a 99-year lease—an exchange that saved the county nearly $100,000 annually in lease space for problem-solving courts. Furthermore, Mahony noted the building features a 1950s wood roof structure and houses vehicle maintenance on the first floor, making vertical expansion highly problematic due to structural integrity, emissions, and noise.

Despite the logistical hurdles, Balich requested that Wight & Company officially review the PACE building’s expansion feasibility, a request the committee honored.

Board Member David G. Oxley (R-Lockport) requested a comprehensive breakdown of the county’s current lease costs versus the projected savings of consolidation. Mahony noted that the county has aggressively reduced its leased footprint recently—moving the Veterans Assistance Commission and Workforce Services into owned buildings—leaving only Land Use, the Public Defender, and a small ~500-square-foot office for the Workforce Investment Board in leased spaces.

No final decisions were made, as the committee directed staff to return next month with refined cost estimates for the various architectural options.

Monee Weather Full forecast →
Today Jun 8
Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms
85° 71°

Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms

💨 10 mph 💧 18%

Leave a Comment





Latest News Stories

Screenshot 2025-11-26 at 7.56.09 AM

Public Works Facility and Firemen’s Park Set for Grand Openings

Village of Monee Board Meeting | September 24, 2025 Article Summary: Monee officials announced upcoming grand opening celebrations for two major capital projects: the new Public Works facility and the...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
Screenshot 2025-11-26 at 7.55.56 AM

Monee Approves 5-Year Police Contract with Retroactive Pay

Village of Monee Board Meeting | September 24, 2025 Article Summary: The Monee Village Board unanimously approved a new collective bargaining agreement with Teamsters Local Union #700, representing village police...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Screenshot 2025-11-26 at 7.54.57 AM

Trucking Facility Proposal Sparks Debate Over Pavement and De-Annexation

Village of Monee Board Meeting | September 24, 2025 Article Summary: The Monee Village Board reviewed a preliminary annexation agreement for a 56-acre industrial development across from Amazon, which includes...
Meeting Briefs

Meeting Summary and Briefs: Monee Township Board for Aug. 2025

Monee Township Board Meeting | August 2025 The Monee Township Board met on Thursday, August 21, 2025, to handle monthly administrative business and plan for upcoming fall community events. Supervisor...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
Monee Township Graphic.3

Attorney Advises Board Against Reissuing 18-Year-Old Check

Monee Township Board Meeting | August 2025 Article Summary: The Monee Township Board discussed a request to reimburse a vendor for an uncashed check dating back to 2007. The Township Attorney...
Meeting-Briefs

Meeting Summary and Briefs: Crete-Monee School District 201-U for September 2025

Crete-Monee School District 201-U Meeting | September 2025 Overall Meeting SummaryThe Crete-Monee School District 201-U Board of Education met on Tuesday, September 16, 2025, to conduct essential business including the...
Screenshot 2025-11-26 at 7.54.47 AM

Monee Considers Major Solar Farm Proposal with $100,000 Incentive

Village of Monee Board Meeting | September 24, 2025 Article Summary: Representatives from Earthrise Energy presented plans for "Plum Valley Solar," a massive 2,400-acre solar facility proposed for the Monee...