County Board Approves Peotone Solar Farm Amid Debates Over Union Labor and Tornado Safety

Spread the love

Will County Board Meeting | March 19, 2026

Article Summary: A 52-acre commercial solar energy facility in Peotone was approved by the Will County Board despite concerns raised by members regarding the use of local union labor and the vulnerability of solar panels to severe weather.

Peotone Solar Farm Key Points:

  • The board approved Ordinance #26-063 for a special use permit for a 4.98-megawatt solar facility at 5949 W. Eagle Lake Road in Peotone.

  • Developer BAP Power assured the board that it utilizes union labor, anticipating new state laws requiring triparty labor agreements starting in June.

  • Board members debated the safety of solar farms following recent tornadoes, with conflicting reports on the extent of damage to existing arrays.

  • The board also approved extensions for previously permitted solar farms in Peotone, Monee, and Joliet townships.

The Will County Board on Thursday, March 19, 2026, granted a special use permit for a new commercial solar farm in Peotone, though the approval sparked extensive debate regarding labor practices and storm resiliency.

The board voted 14-1 to approve Ordinance #26-063, granting a special use permit for a commercial solar energy facility on 52.65 acres located at 5949 W. Eagle Lake Road in Peotone (Will Township). The applicant, BAP Power (doing business as Cenergy Power), plans to construct a 4.98-megawatt ground-mounted solar photovoltaic system.

Prior to the vote, Member David G. Oxley requested that the developer address the board regarding their hiring practices.

“The question is, what percentage of local labor will be used on this project?” Oxley asked.

Chad Chabazi, representing BAP Power, stated that while he did not have an exact percentage, the company tries to use as much local union labor as possible. He also noted that under the state’s new Climate and Equitable Jobs Act (CEJA) rules, which go into effect on June 1, 2026, any project over three megawatts receiving a renewable energy contract from the state will be legally required to have a triparty labor agreement.

“Pretty much all the work that we do on these sites are union labor,” Chabazi said.

Member Frankie Pretzel noted that the board frequently receives letters from local unions, such as the Carpenters Union Local 174, asking the county to ensure these projects employ local workers.

“I don’t love these solar projects when we have people from the community coming and saying I don’t want this,” Pretzel said. “What I do love about these is that it can create local jobs… I just wish that we could condition these requests somehow to say that they have to use local unions to do the work.”

Assistant State’s Attorney Kevin Meyers advised the board that under current state law, the county does not have the legal authority to mandate a project labor agreement as a condition of a special use permit.

Safety concerns were also raised regarding the physical durability of solar farms. Member Judy Ogalla referenced a recent tornado that severely damaged a solar facility, noting that cleanup crews were seen wearing hazmat suits.

“I’d like to know more from land use as, you know, what’s the impact going to be if one of these gets destroyed here in an EF4 or EF5 [tornado]?” Ogalla asked.

Member Mica Freeman offered a different perspective, stating she recently drove past a large solar farm in Kankakee County that had been struck by a tornado.

“I can tell you that the houses across the street were in much worse damage than the solar panels that were on the ground,” Freeman said.

In addition to the new Peotone facility, the board approved several extensions for previously permitted solar farms, giving developers more time to secure building permits. These included Resolution #26-064 (SEXT-26-001) for Prairie Solar LLC on West Kennedy Road in Peotone Township, and Resolutions #26-069 (SEXT-26-006) and #26-070 (SEXT-26-007) for two Dralle Sun LLC facilities located on Dralle Road in Monee Township.

Leave a Comment





Latest News Stories

will county board meeting.6

Crete Township Community Center to Get New Digital Sign

Article Summary: The Will County Board approved a special use permit and two variances for Crete Township, allowing for the installation of a new on-premise dynamic display sign at its...
WCO Board Aug 21.1

Will County Executive Proposes $791 Million Budget Focused on Stability Amidst Economic Uncertainty

Article Summary: Will County Executive Jennifer Bertino-Tarrant presented a balanced $791 million budget proposal for Fiscal Year 2026 that aims to maintain services and prepare for potential economic challenges without...
Planning & Zoning Graphic.3

Will County P&Z: Washington Township Lot Variance Granted

A variance to reduce the minimum lot area from 10 acres to 5 acres was unanimously approved for a property at 1444 E. Corning Road in Washington Township. The owner,...

Will County P&Z: Washington Township Lot Variance Granted

A variance to reduce the minimum lot area from 10 acres to 5 acres was unanimously approved for a property at 1444 E. Corning Road in Washington Township. The owner,...
solar panels photovoltaics in solar farm

Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition

Article Summary: The Will County Planning and Zoning Commission recommended approval for a new commercial solar farm in Crete Township, moving the project forward despite being informed by staff of...
P&Z 8.19.25

Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition

Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a long-term residential recovery program on a 68-acre horse farm, despite vocal opposition from Crete...

Will County P&Z: Green Garden Township Variances Granted in Monee

Roy F. Erikson received unanimous approval for two variances for his property at 26409 S. 80th Avenue in Monee. The Will County Planning and Zonning Commission approved reducing the minimum...

Will County P&Z: Manhattan Township Rezoning Approved

The Will County Planning and Zonning Commission unanimously approved a map amendment for a vacant property on South Kankakee Street in Manhattan Township. The request, brought by James and Julie...
Planning & Zoning Graphic.4

Will County P&Z: Green Garden Township Rezoning Approved Amid Concerns Over Lack of a Final Plan

Article Summary: The Will County Planning and Zoning Commission unanimously approved rezoning a large agricultural parcel in Green Garden Township for potential residential development, despite a township official expressing concern...
Two orange map markers on city map

Zoning Commission Overrules Staff, Approves Greeen Garden Twp Variance for 3-Acre Agricultural Lot

Article Summary: The Will County Planning and Zoning Commission approved a variance for a 3-acre lot in an agricultural zone, going against a staff recommendation to deny the request in...
Monee Township Graphic.3

Monee Township Board Authorizes $300,000 Loan for Food Pantry Construction

Monee Township Board Meeting | July 2025 Article Summary: The Monee Township Board approved a measure allowing the Supervisor to secure a loan of up to $300,000 to complete the construction...
Screenshot 2025-11-26 at 7.32.27 AM

Monee Acquires Properties, Postpones Governor’s Highway Bid

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Village of Monee moved forward with strategic real estate acquisitions on Monee-Manhattan Road but decided to postpone action...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for August 14, 2025

The Will County Board Executive Committee received a comprehensive update on the county's expenditure of $134 million in federal ARPA pandemic relief funds, learning that 61% of the total has...
Peotone-Committee-8.18.25.2

Peotone Schools Face ‘Fiscal Cliff,’ Board Considers School Closures and New Construction

Committee of the Whole Article Summary: Facing a severe financial crisis and a rapidly approaching deadline from a major road project, the Peotone School District 207-U board is now seriously...
Screenshot-2025-08-19-at-6.16.25-PM

Committee of the Whole Eyes School Closures and New Construction Amid Budget Crisis

Committee of the Whole Article Summary: Facing a severe financial crisis with a projected $4.2 million operating deficit, the Peotone School District 207-U board is now seriously exploring the closure...