Monee Village Board of Trustees Meeting | February 25, 2026
Article Summary: The Monee Village Board approved major payouts for the ongoing Industrial Drive reconstruction and the 2025 sidewalk improvement projects, keeping local infrastructure upgrades on schedule for the spring.
Infrastructure Payouts Key Points:
-
Iroquois Paving Corporation received an $886,457.37 payout for the Industrial Drive and Cleveland Avenue Road Reconstruction Project.
-
M&J Underground, Inc. received $70,354.44 for the 2025 Monee Sidewalk Improvements.
-
The village expects to be partially reimbursed for the roadway paving by neighboring property owners.
MONEE, Ill. — The Monee Village Board of Trustees on Wednesday, February 25, 2026, unanimously approved two major contractor payouts totaling more than $956,000 to cover recent progress on the village’s road and sidewalk networks.
Village Administrator Ruben Bautista presented the fourth pay request from Iroquois Paving Corporation for the Industrial Drive and Cleveland Avenue Road Reconstruction Project. The board approved a payout of $886,457.37.
According to agenda documents provided by Robinson Engineering, the project has seen a total earned value to date of $3,663,387.12. The village is currently holding a 10% retainage of $366,338.71.
While the payout represents a significant municipal expense, Bautista informed the board that the village will recoup a portion of the funds from local businesses.
“There are a few of the partial owners on Industrial Drive and Cleveland that are actually paying for the roadway proportionate to their property,” Bautista said. “So even though these numbers show what the amount is, we’ll be receiving money back… from Iroquois Paving and from Northern Builders that are on that roadway.”
The board also unanimously approved the first pay request for the 2025 Monee Sidewalk Improvements. M&J Underground, Inc. was awarded $70,354.44. The total earned to date on the sidewalk project is $78,171.60, with $7,817.16 held in retainage.
Trustee Doug Horne, reporting for Public Works, noted that M&J Underground has already flagged the next phase of the project. Weather permitting, crews are scheduled to resume sidewalk construction on Will Center Road and Linden Avenue beginning the second week of March.
Latest News Stories
Meeting Summary and Briefs: Monee Planning & Zoning Board of Appeals for April 15, 2026
Meeting Summary and Briefs: Will County Board Executive Committee for April 9, 2026
On the road to 100 years: How the Forest Preserve District expanded
Peotone Library Board Appoints Rebecca Markus to Fill Vacant Trustee Seat
Aggen’s Perfect Day at the Plate, Late Surge Power Tinley Park Past Crete-Monee 15-9
P&Z Advances Residential Variances for Garage and Aluminum Fence Additions
Executive Committee Advances Sweeping Updates to Adult Entertainment and Wireless Facilities Ordinances
Ramirez, Robinson Power Crete-Monee’s 25-Hit Barrage in Wild 28-17 Win Over Bloom
Love’s Shutout, Offensive Explosion Propel Crete-Monee Past Bloom 18-0