Will County Board Graphic.03

Committee Approves $740,000 Compressor to Boost RNG Plant Uptime

Spread the love

Will County Landfill Committee Meeting | February 10, 2026

Article Summary: The Landfill Committee approved the purchase of a fourth feed compressor for the Renewable Natural Gas (RNG) facility to address equipment failures that cause 35% of the plant’s downtime. While the facility reported record production in late 2025, financial reports indicate the plant is still operating at a net loss when debt service is included.

RNG Facility Key Points:

  • $740,000 Investment: The committee approved the purchase of a fourth compressor, which has a 36-to-40-week delivery lead time.

  • Operational Record: The plant achieved a record production month in November 2025 with nearly 74,000 MMBtu and 97% uptime.

  • Financial Status: While the plant generated $4 million in net operations income for FY2025, debt service costs of $4.6 million pushed the final balance to a loss of approximately $609,860.

  • Future Costs: Installation of the new compressor is expected to cost an additional $1 million, which will be budgeted for Fiscal Year 2027.

The Will County Landfill Committee on Tuesday, February 10, 2026, unanimously approved the $740,000 purchase of a fourth feed compressor for the county’s Renewable Natural Gas (RNG) facility, a move designed to stabilize revenue and reduce downtime.

Dave Hartke, Director of the Resource Recovery & Energy Division, told the committee that 35% of the facility’s downtime is attributed to issues with the existing three feed compressors. The plant was originally designed to house four units, but the fourth was cut from the original construction budget due to cost overruns.

“If we had that fourth compressor there, it would increase our uptime and therefore increase our revenue generated for the year,” Hartke said.

The purchase will be funded using approximately $500,000 from the building expense account and funds from the machinery account. Hartke noted that the equipment has a lead time of nearly 10 months, placing delivery in October or November. The installation, including electrical work and plumbing, is estimated to cost an additional $1 million. Hartke stated this installation cost would be included in the Fiscal Year 2027 budget request.

“By purchasing the compressor now, budgeting for 2027 the install… it’s not a big headache,” Committee Chair Daniel Butler (R-Frankfort) said.

The committee also reviewed the Fiscal Year 2025 operational report presented by RNG Project Manager Greg Komperda. The facility has seen steady improvement, with uptime averages increasing from 82.3% in 2023 to 90% in 2025. November 2025 marked a high point for the facility, producing nearly 74,000 MMBtu of gas.

However, the financial report highlighted the burden of the facility’s construction debt. For FY2025 (as of November 30), the plant reported total revenues of $11.29 million against operating expenses of $7.28 million, resulting in a net operations income of just over $4 million. However, after accounting for $4.6 million in debt service payments, the facility ended the fiscal year with a net loss of $609,860.

Hartke warned that purchasing the compressor now leaves the division with a slim emergency cushion of approximately $130,000 for the remainder of the fiscal year. He indicated he may approach the Finance Committee in March to transfer $100,000 from the contingency fund to bolster the equipment account.

“It removes some cushion for us if there’s something else that catastrophically fails,” Hartke said.

Monee Weather Full forecast →
Today Jun 8
Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms
85° 71°

Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 20%

Leave a Comment





Latest News Stories

Screenshot 2025-11-26 at 7.56.09 AM

Public Works Facility and Firemen’s Park Set for Grand Openings

Village of Monee Board Meeting | September 24, 2025 Article Summary: Monee officials announced upcoming grand opening celebrations for two major capital projects: the new Public Works facility and the...
WCO 2025-09-27 at 9.04.36 AM

Meeting Summary and Briefs: Will County Board for September 18, 2025

The Will County Board navigated a contentious meeting on September 18, 2025, marked by narrow votes on two highly debated land use issues in Crete and Homer Glen. The board...
Screenshot 2025-11-26 at 7.55.56 AM

Monee Approves 5-Year Police Contract with Retroactive Pay

Village of Monee Board Meeting | September 24, 2025 Article Summary: The Monee Village Board unanimously approved a new collective bargaining agreement with Teamsters Local Union #700, representing village police...
WCO 2025-09-27 at 9.05.04 AM

County Board Abates Over $25 Million in Property Taxes for Bond Payments

Article Summary: Will County property taxpayers will be spared over $25 million in taxes for the 2026 payment year after the County Board voted to abate taxes for six separate...
Screenshot 2025-11-26 at 7.54.57 AM

Trucking Facility Proposal Sparks Debate Over Pavement and De-Annexation

Village of Monee Board Meeting | September 24, 2025 Article Summary: The Monee Village Board reviewed a preliminary annexation agreement for a 56-acre industrial development across from Amazon, which includes...
Meeting Briefs

Meeting Summary and Briefs: Monee Township Board for Aug. 2025

Monee Township Board Meeting | August 2025 The Monee Township Board met on Thursday, August 21, 2025, to handle monthly administrative business and plan for upcoming fall community events. Supervisor...
WCO 2025-09-27 at 9.04.56 AM

Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale

Article Summary: The Will County Board unanimously approved a request to rezone a 10.08-acre portion of a property in Will Township back to agricultural use, reversing a 2023 zoning change....
Enbridge Energy

Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements

Article Summary: Will County will reimburse Enbridge Energy for costs associated with relocating its pipeline facilities to make way for roadway improvements on Exchange Street in the Monee and Crete...
diamond shaped orange red reflector street sign that reads road

Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign

Article Summary: The Will County Board approved a supplemental agreement worth $468,374 for additional design and engineering work on the major Laraway Road expansion project. The funds are needed for...
solar panels photovoltaics in solar farm

“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension

Article Summary: The Will County Board has granted a second permit extension for a solar farm in Peotone Township after the developer, Trajectory Energy Partners, cited "ongoing uncertainty regarding federal...
solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy...
WCO 2025-09-27 at 9.04.10 AM

Will County Board Approves Controversial Drug Recovery Retreat in Crete Township

Article Summary: The Will County Board has approved a special use permit for The Second Story Foundation to operate a long-term residential recovery program for men on a 68-acre horse...
Monee Township Graphic.3

Attorney Advises Board Against Reissuing 18-Year-Old Check

Monee Township Board Meeting | August 2025 Article Summary: The Monee Township Board discussed a request to reimburse a vendor for an uncashed check dating back to 2007. The Township Attorney...
Meeting-Briefs

Meeting Summary and Briefs: Crete-Monee School District 201-U for September 2025

Crete-Monee School District 201-U Meeting | September 2025 Overall Meeting SummaryThe Crete-Monee School District 201-U Board of Education met on Tuesday, September 16, 2025, to conduct essential business including the...
Screenshot 2025-11-26 at 7.54.47 AM

Monee Considers Major Solar Farm Proposal with $100,000 Incentive

Village of Monee Board Meeting | September 24, 2025 Article Summary: Representatives from Earthrise Energy presented plans for "Plum Valley Solar," a massive 2,400-acre solar facility proposed for the Monee...