will county board meeting.6

Capital Imp Committee: Health Dept Elevator Repair Costs Significantly Lower Than Estimates

Spread the love

Will County Capital Improvements & IT Committee Meeting | Jan. 6, 2026

Article Summary: A malfunctioning elevator at the Will County Health Department has been repaired for approximately $18,000 to $20,000, avoiding a potential replacement cost of over $1 million. Facilities staff confirmed the unit is suitable for the building’s needs.

Facilities Key Points:

  • Repair Cost: The final repair bill is estimated between $18,000 and $20,000.

  • Cost Avoidance: Initial fears suggested a full replacement could have exceeded $1 million.

  • In-House Projects: Facilities staff saved money by framing and hanging judge photos at the courthouse internally.

  • Efficiency: The department completed over 750 work orders in the last month with a 98% completion rate.

JOLIET — A potentially budget-breaking elevator issue at the Will County Health Department was resolved for a fraction of the feared cost, Facilities Director William Fern reported to the Capital Improvements and IT Committee on Tuesday, Jan. 6, 2026.

During a facilities update, Chair Mica Freeman (D-Plainfield) requested the final cost for the elevator repair, noting that previous discussions had raised concerns about the unit’s suitability and the potential need for a total replacement.

“I think it was about $18,000 to $20,000,” Fern said.

Freeman noted this was significantly under the $30,000 to $40,000 estimates discussed previously, and far below the cost of a full replacement.

“Or the over million to replace, right?” Fern added. “So I think they got to the root cause of the issue from the initial install and were able to repair it.”

Fern confirmed that the existing elevator was deemed suitable for the space, eliminating the need for major construction.

In other facilities news, Fern highlighted a project at the Will County Courthouse where maintenance staff framed and hung photos of current and past judges on the third floor.

“Originally, we got a quote. It was pretty expensive. It was over like $18,000 for a contractor to do it,” Fern said.

By utilizing the Sheriff’s carpentry staff and county facilities personnel, the project was completed in-house for a “fraction of the cost.” However, Fern noted that a few photos were hung out of order and will be corrected.

Fern also reported that the department continues to operate efficiently, saving the county over $118,000 in evaporation credits on cooling towers at the courthouse to date.

Monee Weather Full forecast →
Today Jun 8
Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms
85° 71°

Slight Chance Rain Showers then Slight Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 20%

Leave a Comment





Latest News Stories

Meeting Summary and Briefs: Will County Planning and Zoning Commission for August 5, 2025

The Will County Planning and Zoning Commission backed two controversial projects at its August 5 meeting, unanimously approving a large-scale landscaping business on a residential lot in DuPage Township despite...
Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for August 5, 2025

The Will County Public Works & Transportation Committee received a detailed presentation on "Our Way Forward 2050," a new 25-year long-range plan designed to guide the region's transportation infrastructure through...
Fire-Ambulance-Rescue-Logo

Indiana Woman Identified as Victim in Fatal Wilmington-Peotone Road Crash

The Will County Coroner’s Office has officially identified the woman killed in Tuesday’s fatal crash on Wilmington-Peotone Road as 70-year-old Judith L. Stirm of Delphi, Indiana. In a statement, Coroner...
Frankfort-Police-Rescue

Multiple Agencies Rescue Person in Mental Health Crisis from Frankfort Pond

A person experiencing a mental health crisis was safely rescued from a pond near 80th Avenue in Lakeview Estates on Wednesday after a coordinated response by multiple emergency agencies. Frankfort...
Green-Garden-Logo.WP

Green Garden Township Forges Ahead with New Town Hall Plan, Faces Budget and Neighbor Concerns

The Green Garden Township Board is advancing an ambitious plan to build a new, larger town hall and community center on a six-acre parcel south of its current location, a...
Meeting-7.28.25

IT Consultant Urges Green Garden Township to Adopt Modern Cybersecurity Measures

Green Garden Township’s digital infrastructure is vulnerable to cybercrime and requires an immediate overhaul, including adopting a modern, secure email system and multifactor authentication, an IT consultant told the board...
Sanchez

Sanchez Family Unveils Major Redevelopment Plan for Monee Industrial Property

Article Summary: Developer Luis Sanchez, a key figure in Monee's commercial growth for two decades, presented a plan to revitalize an industrial property on Industrial Drive. The project, which includes...
Screenshot-2025-08-13-at-2.15.28-PM

Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion

Article Summary: The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a...
Screenshot-2025-08-13-at-2.11.44-PM

Sheepdog Firearms Gets Green Light for Special Use Permit in Monee

Article Summary: Sheepdog Firearms received final approval from the Monee Village Board for a special use permit to operate a retail and firearms range facility at 25812 S. Sunset Drive....
Screenshot-2025-08-13-at-2.15.28-PM

Monee to Receive $250,000 Donation in Solar Project Agreement

Article Summary: The Village of Monee will receive a $250,000 donation from TPE IL W1202, LLC, after the Village Board authorized a community benefit agreement for a planned 5-megawatt solar...
peotone library graphic logo.1

Peotone Library Weighs Potential $5M New Building Against $2M in Repairs

Article Summary: A Peotone Public Library District committee is confronting a major strategic decision: spend nearly $2 million on maintenance for the current building or invest an estimated $5 million...
peotone library graphic logo.1

Peotone Library Weighs Potential $5M New Building Against $2M in Repairs

Article Summary: A Peotone Public Library District committee is confronting a major strategic decision: spend nearly $2 million on maintenance for the current building or invest an estimated $5 million...
Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
peotone library graphic logo.4

Peotone Library to Survey Residents, Explores Book Lockers and Bookmobile for Monee

Article Summary: The Peotone Public Library District is planning a community survey this fall to gather public input on its future, with a focus on improving services to Monee and...
peotone library graphic logo.4

Peotone Library to Survey Residents, Explores Book Lockers and Bookmobile for Monee

Article Summary: The Peotone Public Library District is planning a community survey this fall to gather public input on its future, with a focus on improving services to Monee and...