Homer Glen Landscape Business Granted Extension Due to Utility Delays
Will County Board Meeting | December 18, 2025
Article Summary: The Will County Board approved a second extension for a special use permit for a landscaping business in Homer Glen. The business owners cited delays in securing electricity from ComEd as the primary reason for the project’s stalled progress.
Extension Key Points:
-
Business: Matthuis Family Partnership LP (relocating “815 Mulch-It”).
-
Location: 17958 S. Cedar Road, Homer Glen.
-
Delay: Unforeseen challenges in getting ComEd to provide electricity to the site.
-
New Deadline: The permit is now valid until May 13, 2026.
The Will County Board on Thursday, December 18, 2025, voted to grant a second extension for a special use permit associated with a landscape and lawn maintenance business in Homer Glen.
The permit, originally approved in May 2023, allows the Matthuis Family Partnership LP to relocate its mulching business, “815 Mulch-It,” to a property at 17958 S. Cedar Road. Under county ordinances, special use permits typically lapse if the use is not established within two years.
According to the request submitted to the Land Use Department, the applicants have faced “unforeseen challenges” in working with ComEd to provide electricity to the property. This utility delay has hindered the completion of the permitting process required to legally establish the business on the site.
The County Board is authorized to grant up to four separate extensions for good cause. This second extension gives the business owners an additional 180 days, making the permit valid through May 13, 2026, to resolve the utility issues and finalize development.
Latest News Stories
Public Works Facility and Firemen’s Park Set for Grand Openings
Meeting Summary and Briefs: Will County Board for September 18, 2025
Monee Approves 5-Year Police Contract with Retroactive Pay
County Board Abates Over $25 Million in Property Taxes for Bond Payments
Trucking Facility Proposal Sparks Debate Over Pavement and De-Annexation
Meeting Summary and Briefs: Monee Township Board for Aug. 2025
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign
“Federal Policy Uncertainty” Blamed for Delay of Peotone Solar Farm; County Grants Second Extension
Will County Grants Extensions to Five Solar Projects Sold to New Developers
Will County Board Approves Controversial Drug Recovery Retreat in Crete Township
Attorney Advises Board Against Reissuing 18-Year-Old Check