Article Summary: The Will County Public Works Committee approved a $1.9 million engineering contract for improvements to a dangerous stretch of Wilmington-Peotone Road. Officials confirmed the project will add safety features like passing lanes but rejected a suggestion to simultaneously run utility lines to spur development.
Wilmington-Peotone Road Project Key Points:
-
Phase I Engineering: The board approved a $1,989,737 contract with Alfred Benesch and Company for design engineering.
-
Scope of Work: The project covers the stretch from US Route 45/52 to Center Road in Peotone Township.
-
Safety Features: Planned improvements include 10-foot wide shoulders and passing lanes to accommodate heavy truck traffic; the road will not be expanded to four lanes.
-
Utility Cost: A proposal to run natural gas main lines during construction to attract housing was deemed too expensive by the county engineer.
JOLIET, Ill. — A project to improve safety along a heavily trafficked corridor in Peotone Township moved forward Tuesday, December 2, 2025, as the Will County Board Public Works Committee authorized a nearly $2 million contract for design engineering.
The project targets Wilmington-Peotone Road between US Route 45/52 and Center Road. Director of Transportation Jeff Ronaldson noted that public feedback on the corridor has been polarized, with residents split between wanting “no trucks” and requesting a massive expansion to five lanes.
Ronaldson confirmed the county is taking a middle ground focused on safety.
“There’s going to be passing lanes through there to allow opportunities to get around some trucks. Wide 10-foot shoulders,” Ronaldson said. “It is not going to be a multi-lane, four-lane highway.”
Board Member Mark Revis (R-Plainfield) asked if the road construction offered an opportunity to work with utilities to run a natural gas main line down the corridor, suggesting it could help homeowners currently on propane and potentially attract residential development.
Ronaldson pushed back on the idea, citing the immense cost.
“The main line… would be very expensive,” Ronaldson said. “You need thousands of homes in order for that to make sense for a utility company.”
Ronaldson added that current residents in the agricultural area generally oppose dense subdivisions. “I think people in that area want to see more homes… they certainly don’t think they want to see a bunch of subdivisions,” he said.
The committee also approved a speed zone extension for Channahon-Minooka Road (CH 32) and a new speed zone for Golfview Drive in Green Garden Township.
Latest News Stories
Sheriff’s Office Reports Crime Down 10%, Cites Body Cam Footage as Main Challenge of Safety Act
Will County Considers Moving Land Use Public Hearings Away from Full Board Meetings
Meeting Summary and Briefs: Village of Monee Board for September 24, 2025
Public Works Facility and Firemen’s Park Set for Grand Openings
Meeting Summary and Briefs: Will County Board for September 18, 2025
Monee Approves 5-Year Police Contract with Retroactive Pay
County Board Abates Over $25 Million in Property Taxes for Bond Payments
Trucking Facility Proposal Sparks Debate Over Pavement and De-Annexation
Meeting Summary and Briefs: Monee Township Board for Aug. 2025
Will County Reverses Zoning on Peotone Farmland to Facilitate 10-Acre Sale
Will County to Pay Enbridge $82,000 to Relocate Pipeline Equipment for Exchange Street Improvements
Laraway Road Widening Project in New Lenox and Frankfort Gets Additional $468,000 for Redesign