Renovations at Veterans Assistance Commission and Court Annex on Track for Winter Completion

Spread the love

Article Summary: Will County’s new Veterans Assistance Commission facility in Joliet is projected to be completed by December, while major renovations for the State’s Attorney’s office in the Court Annex are on schedule for a November move-in. Director of Facilities Bill Fern updated a county committee on the progress of these and other key capital projects across the county.

Capital Projects Update Key Points:

  • Interior renovations at the Veterans Assistance Commission buildout at 1300 Copperfield are underway, with a target completion of December 2025.

  • The Court Annex renovations for the State’s Attorney’s office at 57 N. Ottawa are nearing completion and on track for a November 2025 move-in.

  • A potential delay in the delivery of rooftop air handlers for the VAC building is being monitored by the facilities department.

  • Other completed projects include exterior stone repairs at the new courthouse and the installation of speed bumps at the county office building.

JOLIET, IL — Two major Will County building projects are nearing the finish line, with the new Veterans Assistance Commission (VAC) facility expected to open by December and the State’s Attorney’s office set to move into its renovated space in November.

Will County Director of Facilities Bill Fern provided the updates to the Capital Improvements & IT Committee on Tuesday, October 7, 2025.

The buildout of the former Copperfield building at 1300 Copperfield for the VAC is progressing well, with mechanical, lighting, and security systems currently being installed. Fern noted one potential issue that staff is monitoring closely. “The air handling units for the rooftop… the timeline for shipment has been delayed twice,” he said. “We’re coming into the critical point where we’re going to need to condition the space for heat, not air.” Despite the potential delay, the project is still aiming for completion by the end of the year.

Meanwhile, renovations on the second level of the Court Annex building at 57 N. Ottawa for the State’s Attorney’s office are moving quickly. “We’re in a finished space now with the carpet down,” Fern reported, adding that the project is on track for its November move-in date. The remodel includes opening up previously sealed windows to provide natural light to the new offices.

Fern also reported on several smaller projects, including the recent installation of speed bumps and fresh striping in the parking lot of the Will County Office Building to improve pedestrian safety. He also noted that exterior stone repairs on the new courthouse are complete, with scaffolding now removed, at no cost to the county.

Monee Weather Full forecast →
Today Jun 8
Chance Showers And Thunderstorms then Slight Chance Showers And Thunderstorms
85° 69°

Chance Showers And Thunderstorms then Slight Chance Showers And Thunderstorms

💨 5 to 10 mph 💧 32%

Leave a Comment





Latest News Stories

Will County P&Z: Washington Township Lot Variance Granted

A variance to reduce the minimum lot area from 10 acres to 5 acres was unanimously approved for a property at 1444 E. Corning Road in Washington Township. The owner,...
solar panels photovoltaics in solar farm

Will County P&Z Approves Crete Solar Farm, Overruling Township’s General Opposition

Article Summary: The Will County Planning and Zoning Commission recommended approval for a new commercial solar farm in Crete Township, moving the project forward despite being informed by staff of...
P&Z 8.19.25

Will County Board Approves Controversial Recovery Retreat in Crete Township Amid Strong Resident Opposition

Article Summary: The Will County Planning and Zoning Commission approved a special use permit for a long-term residential recovery program on a 68-acre horse farm, despite vocal opposition from Crete...

Will County P&Z: Green Garden Township Variances Granted in Monee

Roy F. Erikson received unanimous approval for two variances for his property at 26409 S. 80th Avenue in Monee. The Will County Planning and Zonning Commission approved reducing the minimum...

Will County P&Z: Manhattan Township Rezoning Approved

The Will County Planning and Zonning Commission unanimously approved a map amendment for a vacant property on South Kankakee Street in Manhattan Township. The request, brought by James and Julie...
Planning & Zoning Graphic.4

Will County P&Z: Green Garden Township Rezoning Approved Amid Concerns Over Lack of a Final Plan

Article Summary: The Will County Planning and Zoning Commission unanimously approved rezoning a large agricultural parcel in Green Garden Township for potential residential development, despite a township official expressing concern...
Two orange map markers on city map

Zoning Commission Overrules Staff, Approves Greeen Garden Twp Variance for 3-Acre Agricultural Lot

Article Summary: The Will County Planning and Zoning Commission approved a variance for a 3-acre lot in an agricultural zone, going against a staff recommendation to deny the request in...
Monee Township Graphic.3

Monee Township Board Authorizes $300,000 Loan for Food Pantry Construction

Monee Township Board Meeting | July 2025 Article Summary: The Monee Township Board approved a measure allowing the Supervisor to secure a loan of up to $300,000 to complete the construction...
Screenshot 2025-11-26 at 7.32.27 AM

Monee Acquires Properties, Postpones Governor’s Highway Bid

Village of Monee Board Meeting | August 13, 2025 Article Summary: The Village of Monee moved forward with strategic real estate acquisitions on Monee-Manhattan Road but decided to postpone action...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for August 14, 2025

The Will County Board Executive Committee received a comprehensive update on the county's expenditure of $134 million in federal ARPA pandemic relief funds, learning that 61% of the total has...
Peotone-Committee-8.18.25.2

Peotone Schools Face ‘Fiscal Cliff,’ Board Considers School Closures and New Construction

Committee of the Whole Article Summary: Facing a severe financial crisis and a rapidly approaching deadline from a major road project, the Peotone School District 207-U board is now seriously...
Screenshot-2025-08-19-at-6.16.25-PM

Committee of the Whole Eyes School Closures and New Construction Amid Budget Crisis

Committee of the Whole Article Summary: Facing a severe financial crisis with a projected $4.2 million operating deficit, the Peotone School District 207-U board is now seriously exploring the closure...
Screenshot-2025-08-19-at-6.11.05-PM

Acting, Consulting Superintendents to Lead Peotone Schools During Owens’ Absence

Article Summary: Superintendent Brandon Owens is recuperating at home following a vehicle accident, prompting the Peotone Board of Education to establish an interim leadership team. Assistant Superintendent Carole Zurales will...
Screenshot-2025-08-19-at-6.09.01-PM

Peotone School Board Rejects Mandating Live-Streaming in 4-3 Vote

Article Summary: The Peotone school board has opted against requiring its meetings to be live-streamed, finalizing a new committee policy after a 4-3 vote defeated the mandate. The decision followed...
Meeting Briefs

Meeting Summary and Briefs: Peotone Board of Education for August 18, 2025

The Peotone Board of Education’s August 18 meeting was defined by the district’s precarious financial situation. With a projected $4.2 million operating deficit and its borrowing capacity nearly exhausted, the...