solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Spread the love

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy developers. The new operators, Nautilus Solar and Madison Energy Infrastructure, now have until 2026 to begin construction as they work to secure final permits.

Solar Project Sales Key Points:

  • Projects Involved: Five separate solar farms in Peotone, Monee, Crete, and Joliet townships received 180-day extensions.

  • New Developers: Two projects were sold to Nautilus Solar, and three were sold to Madison Energy Infrastructure.

  • Action: The extensions give the new owners until February or April 2026 to secure construction permits and lawfully establish the facilities.

  • Status: While required variances for the projects have been established, construction permits submitted by the new developers remain under review by the county.

JOLIET — A pattern of smaller solar energy projects being sold to larger developers has prompted the Will County Board to grant permit extensions for five separate solar farms. The board unanimously approved the first 180-day extensions for the projects, which are now owned by Nautilus Solar and Madison Energy Infrastructure.

According to county memos, the original applicants for all five projects had successfully established required variances related to ground cover and mowing, but the special use permits were nearing their two-year expiration dates. The projects were subsequently sold to the new developers, who have since applied for construction permits that are still under review.

Nautilus Solar acquired two projects:

  • A facility from Aequo Foundation, Inc. on Kennedy Road in Peotone.

  • A facility from Felipe D. Recendez on South Will Center Road in Monee.
    Both permits are now valid through April 17, 2026.

Madison Energy Infrastructure acquired three projects:

  • Two facilities from Dart Farms, Inc. in Joliet Township at the northwest and southwest corners of Cherry Hill Road and W. Schweitzer Road/US 52.

  • A facility from The Moeller Trust on Torrence Avenue in Crete.
    These permits are now valid through February 13, 2026.

The board’s approval of the extensions provides the new operators additional time to finalize the permitting process and begin construction on the renewable energy facilities.

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Leave a Comment





Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for August 5, 2025

The Will County Public Works & Transportation Committee received a detailed presentation on "Our Way Forward 2050," a new 25-year long-range plan designed to guide the region's transportation infrastructure through...
Fire-Ambulance-Rescue-Logo

Indiana Woman Identified as Victim in Fatal Wilmington-Peotone Road Crash

The Will County Coroner’s Office has officially identified the woman killed in Tuesday’s fatal crash on Wilmington-Peotone Road as 70-year-old Judith L. Stirm of Delphi, Indiana. In a statement, Coroner...
Frankfort-Police-Rescue

Multiple Agencies Rescue Person in Mental Health Crisis from Frankfort Pond

A person experiencing a mental health crisis was safely rescued from a pond near 80th Avenue in Lakeview Estates on Wednesday after a coordinated response by multiple emergency agencies. Frankfort...
Green-Garden-Logo.WP

Green Garden Township Forges Ahead with New Town Hall Plan, Faces Budget and Neighbor Concerns

The Green Garden Township Board is advancing an ambitious plan to build a new, larger town hall and community center on a six-acre parcel south of its current location, a...
Meeting-7.28.25

IT Consultant Urges Green Garden Township to Adopt Modern Cybersecurity Measures

Green Garden Township’s digital infrastructure is vulnerable to cybercrime and requires an immediate overhaul, including adopting a modern, secure email system and multifactor authentication, an IT consultant told the board...
Sanchez

Sanchez Family Unveils Major Redevelopment Plan for Monee Industrial Property

Article Summary: Developer Luis Sanchez, a key figure in Monee's commercial growth for two decades, presented a plan to revitalize an industrial property on Industrial Drive. The project, which includes...
Screenshot-2025-08-13-at-2.15.28-PM

Monee Approves Over $566,000 Payment for New Public Works Facility Nearing Completion

Article Summary: The Monee Village Board approved a payment of $566,134.16 for the ongoing construction of its new Public Works building. Officials reported the project is on track for a...
Screenshot-2025-08-13-at-2.11.44-PM

Sheepdog Firearms Gets Green Light for Special Use Permit in Monee

Article Summary: Sheepdog Firearms received final approval from the Monee Village Board for a special use permit to operate a retail and firearms range facility at 25812 S. Sunset Drive....
Screenshot-2025-08-13-at-2.15.28-PM

Monee to Receive $250,000 Donation in Solar Project Agreement

Article Summary: The Village of Monee will receive a $250,000 donation from TPE IL W1202, LLC, after the Village Board authorized a community benefit agreement for a planned 5-megawatt solar...
peotone library graphic logo.1

Peotone Library Weighs Potential $5M New Building Against $2M in Repairs

Article Summary: A Peotone Public Library District committee is confronting a major strategic decision: spend nearly $2 million on maintenance for the current building or invest an estimated $5 million...
peotone library graphic logo.1

Peotone Library Weighs Potential $5M New Building Against $2M in Repairs

Article Summary: A Peotone Public Library District committee is confronting a major strategic decision: spend nearly $2 million on maintenance for the current building or invest an estimated $5 million...
Screenshot-2025-08-13-at-2.11.44-PM

Monee Board Sets Spending Plan with 2025-2026 Appropriations Ordinance

Article Summary: The Monee Village Board has approved its annual appropriations ordinance, which acts as the village's legal spending authority for the fiscal year that began May 1, 2025. The...
peotone library graphic logo.4

Peotone Library to Survey Residents, Explores Book Lockers and Bookmobile for Monee

Article Summary: The Peotone Public Library District is planning a community survey this fall to gather public input on its future, with a focus on improving services to Monee and...
peotone library graphic logo.4

Peotone Library to Survey Residents, Explores Book Lockers and Bookmobile for Monee

Article Summary: The Peotone Public Library District is planning a community survey this fall to gather public input on its future, with a focus on improving services to Monee and...
Screenshot-2025-08-13-at-2.15.28-PM

Monee Officials Issue Pool Safety Alert Amid Summer Heat

Article Summary: Following an increase in new pool installations, Monee's Building Services department is reminding residents of mandatory permit and safety requirements. Officials are emphasizing life-safety measures to prevent drownings,...