solar panels photovoltaics in solar farm

Will County Grants Extensions to Five Solar Projects Sold to New Developers

Spread the love

Article Summary: The Will County Board approved first-time permit extensions for five commercial solar projects across Monee, Crete, and Joliet townships, all of which were recently sold to larger energy developers. The new operators, Nautilus Solar and Madison Energy Infrastructure, now have until 2026 to begin construction as they work to secure final permits.

Solar Project Sales Key Points:

  • Projects Involved: Five separate solar farms in Peotone, Monee, Crete, and Joliet townships received 180-day extensions.

  • New Developers: Two projects were sold to Nautilus Solar, and three were sold to Madison Energy Infrastructure.

  • Action: The extensions give the new owners until February or April 2026 to secure construction permits and lawfully establish the facilities.

  • Status: While required variances for the projects have been established, construction permits submitted by the new developers remain under review by the county.

JOLIET — A pattern of smaller solar energy projects being sold to larger developers has prompted the Will County Board to grant permit extensions for five separate solar farms. The board unanimously approved the first 180-day extensions for the projects, which are now owned by Nautilus Solar and Madison Energy Infrastructure.

According to county memos, the original applicants for all five projects had successfully established required variances related to ground cover and mowing, but the special use permits were nearing their two-year expiration dates. The projects were subsequently sold to the new developers, who have since applied for construction permits that are still under review.

Nautilus Solar acquired two projects:

  • A facility from Aequo Foundation, Inc. on Kennedy Road in Peotone.

  • A facility from Felipe D. Recendez on South Will Center Road in Monee.
    Both permits are now valid through April 17, 2026.

Madison Energy Infrastructure acquired three projects:

  • Two facilities from Dart Farms, Inc. in Joliet Township at the northwest and southwest corners of Cherry Hill Road and W. Schweitzer Road/US 52.

  • A facility from The Moeller Trust on Torrence Avenue in Crete.
    These permits are now valid through February 13, 2026.

The board’s approval of the extensions provides the new operators additional time to finalize the permitting process and begin construction on the renewable energy facilities.

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Leave a Comment





Latest News Stories

Meeting-Briefs

Meeting Summary and Briefs: Crete-Monee School District 201-U for September 2025

Crete-Monee School District 201-U Meeting | September 2025 Overall Meeting SummaryThe Crete-Monee School District 201-U Board of Education met on Tuesday, September 16, 2025, to conduct essential business including the...
Screenshot 2025-11-26 at 7.54.47 AM

Monee Considers Major Solar Farm Proposal with $100,000 Incentive

Village of Monee Board Meeting | September 24, 2025 Article Summary: Representatives from Earthrise Energy presented plans for "Plum Valley Solar," a massive 2,400-acre solar facility proposed for the Monee...
Screenshot 2025-11-25 at 9.39.35 PM

Attendance Matters’ Campaign Kicks Off to Combat Truancy

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The district introduced a new "Attendance Matters" campaign led by Truancy Officer Eric Green, aimed at proactively improving student attendance...
Screenshot 2025-11-25 at 9.39.24 PM

District Launches ‘ParentSquare’ to Unify School Communications

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: Crete-Monee School District 201-U is rolling out ParentSquare, a new unified communication platform designed to replace multiple existing apps and...
Monee Township Logo.1

Public Hearings Set for I-57 Freight Route and Monee TIF District

Monee Township Board Meeting | August 2025 Article Summary: Local and county officials alerted the Monee Township Board to upcoming public hearings regarding major regional developments. The hearings concern a proposed...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for September 10, 2025

Village of Monee Board Meeting | September 10, 2025 Meeting Summary: The Monee Village Board of Trustees met on Wednesday, September 10, 2025, for a session focused on infrastructure spending...
Screenshot 2025-11-25 at 9.39.05 PM

Board Awards $4 Million Contract for Middle School Renovations

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The Board of Education awarded a $4 million contract to BEAR Construction for renovations at Crete-Monee Middle School, a project...
Monee Township Graphic.4

Monee Township Food Pantry Expansion Phase 2 Pushed to 2026

Monee Township Board Meeting | August 2025 Article Summary: The Monee Township Board announced a significant schedule adjustment for the ongoing food pantry expansion project. While the first phase is complete,...
peotone library graphic logo.1

Peotone Library to Install $25,000 Smart Lockers in Monee to Expand Service

Article Summary: The Peotone Public Library District is moving forward with a plan to purchase and install a $25,000 smart locker system in Monee, providing a convenient pickup point for residents...
Screenshot 2025-11-25 at 9.38.51 PM

Crete-Monee Board Approves 2025-2026 Budget with Focus on Capital Projects

Crete-Monee School District 201-U Meeting | September 2025 Article Summary: The Crete-Monee School District 201-U Board of Education voted to adopt the fiscal year 2025-2026 budget, which projects a deficit...
Screenshot 2025-11-26 at 7.49.21 AM

Village Officials Celebrate Fall Fest Success; Reappoint Key Staff

Village of Monee Board Meeting | September 10, 2025 Article Summary: Following a successful Fall Fest, Monee officials praised village staff and volunteers for a safe and well-attended event. The...
Screenshot 2025-11-26 at 7.49.14 AM

Monee Approves Nearly $700,000 for Sidewalks and Drainage Improvements

Village of Monee Board Meeting | September 10, 2025 Article Summary: The Monee Village Board awarded two major infrastructure contracts totaling nearly $700,000 to address sidewalk connectivity and pond remediation....
Screenshot 2025-11-26 at 7.49.02 AM

Monee Board Rejects “Up Front” Cash Requests from Hotel Developer

Village of Monee Board Meeting | September 10, 2025 Article Summary: The Monee Village Board reached a consensus to reject new terms proposed by the developer of the Quality Inn...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for August 27, 2025

Village of Monee Board Meeting | August 27, 2025 Meeting Summary:The Monee Village Board of Trustees met on Wednesday, August 27, 2025, to address significant financial and development matters. The...
Monee Graphic.1

Board Approves $1.2 Million Payout for Road Construction and New Park Accessibility Lift

Village of Monee Board Meeting | August 27, 2025 Article Summary:The Monee Village Board authorized a payment of over $1.2 million for the ongoing reconstruction of Industrial Drive and Cleveland...