Will County Awards $1.46 Million Contract for Kankakee Street Bridge Replacement in Manhattan Township
Article Summary
The Will County Board has awarded a $1.46 million contract to “D” Construction, Inc. of Coal City to replace the Kankakee Street Bridge over Jackson Creek in Manhattan Township. The project, set to begin in spring 2026, will require a full road closure and a posted detour during construction.
Manhattan Bridge Replacement Key Points:
-
Contractor: “D” Construction, Inc. was the low bidder for the project.
-
Project Cost: The total contract amount is $1,465,938.49.
-
Scope & Timeline: The project involves complete removal and replacement of the bridge, with construction estimated to run from April 2026 to August 2026.
-
Funding: The construction will be paid for using the Manhattan Road District’s motor fuel tax funds and Will County’s bridge tax funds.
JOLIET, IL – A crucial infrastructure project in Manhattan Township is set to move forward after the Will County Board awarded a nearly $1.5 million contract for the replacement of the Kankakee Street Bridge over Jackson Creek.
On Thursday, the board approved a resolution confirming the award to “D” Construction, Inc. of Coal City, which submitted the lowest bid at $1,465,938.49. The project is being funded through a combination of the Manhattan Road District’s motor fuel tax funds and county bridge tax funds.
The scope of the work is extensive and includes the complete removal of the existing bridge. The new structure will be a single-span, cast-in-place concrete slab bridge. The project also involves constructing new full-depth hot-mix asphalt pavement approaches, aggregate shoulders, guardrails, and stream regrading.
Construction is scheduled to begin in April 2026, with an estimated completion date of August 21, 2026. According to the project summary, the roadway will be closed to all traffic during construction, and a posted detour route will be implemented to guide drivers around the work zone. The Public Works and Transportation Committee recommended the contract award earlier this month before it received final approval from the full County Board.
Monee Events
Latest News Stories
Meeting Summary and Briefs: Will County Legislative Committee for November 4, 2025
Will County Saves $5.7 Million in Bond Refinancing, Maintains High Credit Ratings
Will County Saves Nearly $5.74 Million in Bond Refinancing, Explores Future Borrowing Options
Will County Board Advances New Speed Limits in Green Garden and Frankfort Townships
New Lenox Garage Variance Denied After Neighbor Cites ‘Massive’ Scale and Neighborhood Impact
State Veto Session Passes Energy Bill Limiting County Zoning, Approves Toll Hike for Mass Transit
Commission Approves Peotone-Area Farmhouse Split, Overruling Staff’s “Spot Zoning” Concerns
Will County Finance Committee Hits Impasse on 2025 Tax Levy, Postpones Budget Votes
Federal Lobbyists Brief Will County on Government Shutdown, Warn of SNAP and TSA Disruptions
Commission Approves Mokena-Area Garage Variance Over Village’s Objection
Will County Committee Advances Gougar Road Bridge Project with Over $540,000 in Agreements
Will County Committee Shapes 2026 Legislative Agendas on Housing, Energy, and Health
Commission Grants Green Garden Solar Farm Project Variance Extension
Will County Committee Advances Phased Takeover of Central Will Dial-A-Ride Service