Article Summary: The Monee Village Board authorized a substantial payment of over $1.7 million to Iroquois Paving for the Ridgeland and Bruns Road water main improvements, a project designed to provide a redundant water feed under I-57. Officials emphasized the project’s importance for fire protection and business security on the village’s west side.
Monee Water Infrastructure Key Points:
-
Major Payment: The board approved a payout of $1,763,797.50 to Iroquois Paving for the Ridgeland and Bruns Road project.
-
Grant Funding: Administrator Ruben Bautista noted the village received a $500,000 federal grant to help offset the costs.
- Safety Upgrades: The new loop provides a secondary water source for the west side of the village, enhancing fire protection capabilities.
The Monee Village Board on Wednesday, August 13, 2025, approved a series of significant infrastructure payments, headlined by a $1.76 million disbursement for a water main project intended to secure the village’s water supply and fire safety.
Trustees voted unanimously to approve Pay Request #1 from Iroquois Paving in the amount of $1,763,797.50 for the Ridgeland and Bruns Road Water Main Improvements. According to Village Administrator Ruben Bautista, the total earned to date on the project is approximately $1.96 million, with the village holding back a 10 percent retention.
Bautista and trustees highlighted the strategic importance of the project, which creates a water loop providing redundancy under I-57. Previously, the west side of the village relied on a single feed.
“This project is going to give comfortability to those businesses that are looking to move… to the west side of the town,” Trustee Michael Wilson said. “It’s not a good time when things go bad… so having that capability or option of switching over so that way we can continue water supply services [is vital].”
Trustee Scott Youdris noted the public safety benefits, explaining that the increased water supply reliability could help improve the village’s ISO rating, potentially lowering insurance costs for residents and businesses due to better fire protection.
Public Works Trustee Doug Horne reported that the new main was pressurized on August 7 and that quality control testing is complete.
“This loop provides redundant water feed under I-57, as well as providing better flow characteristics and enhanced fire protection,” Horne said.
In addition to the Ridgeland project, the board approved final payouts to Iroquois Paving for two other completed projects: $57,397.80 for the Main Street Water Main Replacement and $606,404.53 for the 2023-2024 Roadway Maintenance Program.
Monee Events
Latest News Stories
Monee Implements Local Grocery Tax to Replace Expired State Tax
Monee Proposes Expansion of TIF District 5 to Spur Development
Your Ultimate Guide to the 2025 Frankfort Fall Fest: Everything to Know for the Nationally-Ranked Event
Meeting Summary and Briefs: Monee Township Board for July 2025
Meeting Summary and Briefs: Village of Monee Board for August 13, 2025
Clerk Reports Single Bid of $635,000 for Road Improvements
Board Advances Development Plans for Industrial Drive
After Initial Rejection and Tense Debate, Board Reconsiders and Approves Contested DuPage Township Business
Meeting Summary and Briefs: Will County Board for August 21, 2025
Will County Board Approves New Fee Schedule for Recorder of Deeds
Will County Board Formally Opposes Heavier, Longer Trucks on National Roadways
Will County Board Approves Permits for Landscaping Business and Restaurant Liquor Service in Frankfort Area