Monee Board Approves Over $400,000 in Infrastructure Payments
The Monee Village Board authorized more than $400,000 in payments Wednesday for two major, ongoing infrastructure projects: the Village Hall remodel and the reconstruction of Industrial Drive and Cleveland Avenue.
Trustees approved Pay Request #8 to Piggush Simoneau, Inc. (PSI) for $196,457.08 for its work on the nearly completed Village Hall renovation. The payment brings the total amount billed for the project to over $1.3 million.
“All of the work that is for the Village Hall has been done, all but the sprinkler system,” said Mayor Dr. Therese M. Bogs.
The original fire sprinkler system, installed in 1997, experienced corrosion issues that became apparent during the remodel. The board plans to have the old system completely replaced with an upgraded one later this year. “That will be the hopefully the last remaining item that will be dealt with probably late fall, early winter,” Bogs said. An additional invoice for that work is expected at a later date.
The board also approved a $206,476.06 payment to Iroquois Paving Corporation for Pay Request #2 on the Industrial Drive and Cleveland Avenue Roadway Reconstruction Project. The payment was recommended by the village’s engineering firm, Robinson Engineering.
The project has a total earned-to-date value of over $1.29 million. After a 10% retainage of $129,286 and accounting for a previous payment, the approved amount was due. Both payment requests were approved unanimously by the board.
Monee Events
Latest News Stories
Peotone School Board Rejects Mandating Live-Streaming in 4-3 Vote
Meeting Summary and Briefs: Peotone Board of Education for August 18, 2025
Executive Committee Details Spending of $134 Million in Pandemic Relief Funds
Facing Budget Crisis, Peotone Committee Questions Athletic Field Project
Committee Summary and Briefs: Peotone Board of Education Committee of the Whole
Meeting Summary and Briefs: Crete-Monee School Board for August 12, 2025
Peotone Library Director’s Salary Set at $75,000 After Annual Evaluation
Peotone Library Director’s Salary Set at $75,000 After Annual Evaluation
Village Hall to Get $412,000 Fire Sprinkler Replacement After System Failure
Crete-Monee Board Adopts School Improvement Plans for 2025-2026
Executive Committee Considers $12,000 Strategic Planning Initiative with University of St. Francis
Board Approves Over $4.4 Million for Major Construction Projects