Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

Metra

Metra Announces No Fare Hikes; Highlights Bridge Projects in Joliet and Mokena

Will County Committee of the Whole Meeting | December 2025 Article Summary: Metra officials presented a balanced 2026 budget to the Will County Board, confirming that riders will not see...
Rent collusion suit tossed vs manufactured home community operators

Rent collusion suit tossed vs manufactured home community operators

By Scott Holland | Legal NewslineThe Center Square A federal judge has dismissed, for now, a class action accusing some of the nation’s largest manufactured home community landlords of rent...
Illinois quick hits: Planned vigil opposes physician-assisted suicide; NFIB urges veto of energy bill

Illinois quick hits: Planned vigil opposes physician-assisted suicide; NFIB urges veto of energy bill

By Jim Talamonti | The Center SquareThe Center Square Planned vigil opposes physician-assisted suicide A vigil is planned Thursday afternoon outside the State of Illinois building in Chicago’s West Loop,...
Screenshot 2025-12-10 at 12.07.00 PM

Crete-Monee School District 201-U Proposes 2025 Tax Levy; Tax Rate Projected to Decrease

Article Summary: The Crete-Monee School District 201-U Board of Education held a public hearing regarding its 2025 property tax levy, projecting a decrease in the overall tax rate due to...

Public Works Committee: Will County Consolidates Paratransit Services Amid Funding Debates

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Board’s Public Works Committee advanced an agreement to consolidate paratransit services into a single countywide...
Will County P&Z Logo Planning Zoning

P&Z Commission: Peotone Area Variances Forwarded for Garage and Pole Barn

Will County Planning and Zoning Commission Meeting | December 2, 2025 Article Summary: The Will County Planning and Zoning Commission approved variance requests for two properties in Peotone Township, allowing...

Peotone License Plate Camera Renewal Sparks Privacy Debate in Public Works Committee

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: A renewal of an agreement allowing license plate reading (LPR) cameras in Peotone passed the Public Works Committee,...
After Kirk assasination, students less comfortable with ‘controversial’ events on campus

After Kirk assasination, students less comfortable with ‘controversial’ events on campus

By Tate MillerThe Center Square Following the assassination of Charlie Kirk, half of the nation’s college students report feeling less comfortable attending controversial public events on campus and nearly half...
Everyday Economics: The case for a December rate cut

Everyday Economics: The case for a December rate cut

By Orphe DivounguyThe Center Square Last week brought the delayed September numbers on personal income, consumption, and the Fed’s preferred inflation gauge, the Personal Consumption Expenditures (PCE) price index. It’s...
Screenshot 2025-12-05 at 12.00.30 PM

Joliet Unity Movement Criticizes Board’s Handling of Cannabis Tax Revenue

Will County Board Meeting | December 4, 2025 Article Summary: During public comment, the Joliet Unity Movement denounced a recent board vote that redirected cannabis tax revenue away from community...
Republicans divided over how to address rising health care costs

Republicans divided over how to address rising health care costs

By Thérèse BoudreauxThe Center Square The U.S. Senate will hold a doomed vote next week on Democrats’ bill to extend the enhanced Obamacare subsidies for three more years. Senate Republicans,...
Obama-era 'Welcoming Cities' program overlaps with illegal border crosser crimes

Obama-era ‘Welcoming Cities’ program overlaps with illegal border crosser crimes

By Bethany BlankleyThe Center Square A program launched in partnership with the Obama administration more than a decade ago that certifies localities to “improve immigrant inclusion” overlaps with crimes being...
Expert blasts Illinois Congressman’s push to double H-1Bs as 'tone-deaf'

Expert blasts Illinois Congressman’s push to double H-1Bs as ‘tone-deaf’

By Catrina BarkerThe Center Square A renewed push to double H-1B visas is touted as a talent win, but critics warn it could reshape the tech market by driving down...

Safety Upgrades Planned for Wilmington-Peotone Road; Gas Line Proposal Rejected

Public Works & Transportation Committee Meeting | December 2, 2025 Article Summary: The Will County Public Works Committee approved a $1.9 million engineering contract for improvements to a dangerous stretch...
Afghans arrested by ICE released into the country by the Biden administration

Afghans arrested by ICE released into the country by the Biden administration

By Bethany BlankleyThe Center Square Federal and local law enforcement officers have been arresting Afghan men since they were released into the country by the Biden administration in 2021. Key...