Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

Newsom predicts smaller budget shortfall than state agency

Newsom predicts smaller budget shortfall than state agency

By Madeline ShannonThe Center Square In his proposed budget, California Gov. Gavin Newsom is predicting a shortfall of $2.9 billion. That's much less than the $18 billion shortfall projected by...
Colorado ordered to pay $5.4M after abortion law blocked

Colorado ordered to pay $5.4M after abortion law blocked

By Elyse ApelThe Center Square Colorado must pay back legal fees after it was sued for a law banning abortion pill reversals, a federal court ruled this week. The state...
norovirus

Will County Health Department Reports Rise in Respiratory Illnesses, Updates on Facility Issues

Will County Board Public Health & Safety Committee Meeting | January 7, 2026 Article Summary: At the January 7, 2026, meeting, Executive Director Elizabeth Bilotta reported a spike in respiratory...
Will County Board Graphic.01

Public Works Committee Delays Vote on State Police License Plate Cameras Amid Privacy Concerns

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Article Summary: The Will County Board Public Works & Transportation Committee voted to postpone a decision on an...
Four Republicans certified for primary to take on Pritzker

Four Republicans certified for primary to take on Pritzker

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – The Republican primary election for who will take on Gov. J.B. Pritzker in November is set. Democrats...
Illinois quick hits: State sues over frozen funds; Nicor Gas seeks rate hike

Illinois quick hits: State sues over frozen funds; Nicor Gas seeks rate hike

By Jim Talamonti | The Center SquareThe Center Square State sues over frozen funds Illinois is one of five states suing the Trump administration over a freeze of more than...
Treasury, IRS ramp up investigation into Minnesota fraud

Treasury, IRS ramp up investigation into Minnesota fraud

By Morgan SweeneyThe Center Square The administration continues to ramp up its response to the massive social services fraud in Minnesota, with Treasury Secretary Scott Bessent enumerating steps his department...
Tariff authority decision still awaited from Supreme Court

Tariff authority decision still awaited from Supreme Court

By Brett RowlandThe Center Square Tariff authority by second-term Republican President Donald Trump was not decided by the U.S. Supreme Court on Friday, meaning the federal government can continue to...
Minneapolis schools offer remote learning while ICE operations continue

Minneapolis schools offer remote learning while ICE operations continue

By J.D. DavidsonThe Center Square Minneapolis Public Schools can choose remote learning for at least a month in the wake of the shooting of Renee Good by an ICE officer...
Trump administration sued for freezing child care funds

Trump administration sued for freezing child care funds

By Chris WadeThe Center Square New York is leading four other states in suing the Trump administration over a freeze of more than $10 billion in federal funding for child...
Minnesota authorities cut out of ICE shooting investigation

Minnesota authorities cut out of ICE shooting investigation

By J.D. DavidsonThe Center Square Hennepin County Attorney Mary Moriaty said the community could be left in the dark after the FBI refused to cooperate with local authorities to investigate...
WATCH: SCOTUS considers gun ban; Pritzker responds to funding freeze; Bailey’s blueprint

WATCH: SCOTUS considers gun ban; Pritzker responds to funding freeze; Bailey’s blueprint

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop discusses the status...
Illinois quick hits: Killeen stepping down from U of I in 2027

Illinois quick hits: Killeen stepping down from U of I in 2027

By Jim Talamonti | The Center SquareThe Center Square Killeen stepping down from U of I in 2027 University of Illinois System President Tim Killeen says he stepping down at...
Op-Ed: The Supreme Court must stop Louisiana’s retroactive lawsuits

Op-Ed: The Supreme Court must stop Louisiana’s retroactive lawsuits

By John ShuThe Center Square On Monday, the U.S. Supreme Court will hear oral arguments in Chevron v. Plaquemines Parish on a threshold jurisdictional question. The Court’s answer could have...
Trump requests $6.2M in attorney fees from Fulton County

Trump requests $6.2M in attorney fees from Fulton County

By Kim JarrettThe Center Square A 222-page document filed in Fulton County Superior Court outlines President Donald Trump's $6.2 million in legal fees spent defending himself in an election interference...