Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

Illinois ‘RIFL’ act sparks fierce debate as lawmakers return to Springfield

Illinois ‘RIFL’ act sparks fierce debate as lawmakers return to Springfield

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – As Illinois lawmakers convene for the 2026 legislative session, House Bill 3320, Responsibility in Firearm Legislation...
SCOTUS declines to hear felony firearms cases

SCOTUS declines to hear felony firearms cases

By Andrew RiceThe Center Square The U.S. Supreme Court on Tuesday declined to take up two cases over whether individuals with felony records can be permanently disarmed under the Second...
Illinois Quick Hits: No injuries reported in Tuesday earthquake

Illinois Quick Hits: No injuries reported in Tuesday earthquake

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – No injuries have been reported after the U.S. Geological Survey reported a magnitude 3.8 earthquake near the...
One year in: Reviewing Trump's inaugural promises

One year in: Reviewing Trump’s inaugural promises

By Andrew RiceThe Center Square One year ago Tuesday, President Donald Trump told the nation its “golden age” had arrived, promising to spend his second term restoring stability at home...
Screenshot 2026-01-15 at 4.48.23 PM

Drones and Thermal Imaging Used to Locate Elusive Monee Water Main Break

Monee Village Board Meeting | January 14, 2026 Article Summary: A stubborn water main break on Route 50 required a multi-agency high-tech search operation to locate. Public Works officials utilized...
Will County Board Graphic.04

Frankfort Township Road Commissioner Warns County Panel Against Low-Speed Vehicles

Will County Ad-Hoc Ordinance Review Committee Meeting | Jan. 13, 2026 Article Summary: The Will County Board Ad-Hoc Ordinance Review Committee moved forward with a ban on low-speed vehicles on...
GOP hopefuls seek support, blast Pritzker at IL gubernatorial candidate forum

GOP hopefuls seek support, blast Pritzker at IL gubernatorial candidate forum

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – All four Illinois Republican gubernatorial candidates have no shortage of criticism for current Gov. J.B. Pritzker. 2022...
Illinois lawmaker questions IDHS over years-long data breach

Illinois lawmaker questions IDHS over years-long data breach

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – An Illinois lawmaker slammed the state agency as “incompetent” after the Department of Human Services revealed...
Will County Board Graphic.04

Draft County Federal Agenda Opposes Sharing Medicaid Patient Data with ICE

Article Summary: A proposed federal policy platform presented to the Will County Board takes a hard line against a federal agreement that allows Immigration and Customs Enforcement (ICE) to access...
Will County Logo Graphic

Northern Builders Development Brings Changes to Laraway and Gougar Roads in New Lenox

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board approved access permits for a new development by Northern Builders at the intersection of Laraway Road...

Meeting Summary and Briefs: Will County Public Works & Transportation Committee for January 6, 2026

Will County Public Works & Transportation Committee Meeting | January 6, 2026 Meeting SummaryThe Will County Board Public Works & Transportation Committee met on Tuesday, January 6, 2026, to discuss...
Beecher Fire Protection District graphic.2

Freezing Temperatures Complicate Beecher Garage Fire Battle

Article Summary: Beecher firefighters faced a fully involved garage fire and equipment challenges due to the cold weather on Saturday evening, eventually bringing the blaze under control without reported injuries....
Will County Board Graphic.03

County Board Debates Legislative Agendas; State Agenda Passes, Federal Agenda Sent Back

Will County Board Meeting | January 15, 2026 Article Summary: The Will County Board engaged in a vigorous and at times confusing debate over its 2026 legislative priorities, ultimately passing...
Congratulations to Corporal Kurtis Ingram

Corporal Ingram completes elite leadership training program

Corporal Kurtis Ingram has successfully completed the School of Police Staff and Command (SPSC) at Northwestern University’s Center for Public Safety. The SPSC is an intensive 10-week program focused on...
Meeting Briefs

Meeting Summary and Briefs: Will County Board Executive Committee for January 8, 2026

Will County Board Executive Committee Meeting | January 8, 2026 Overall Meeting SummaryThe Will County Board Executive Committee met on Thursday, January 8, 2026, tackling a heavy agenda that included...