Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

Meeting Briefs

Meeting Summary and Briefs: Will County Land Use & Development Committee for November 6, 2025

Will County Land Use & Development Committee Meeting | November 6, 2025 The Will County Land Use and Development Committee navigated a series of contentious zoning cases on Thursday, November...
Will County Board Land Use Committee Graphic.2

Will County Committee Approves Rezoning, Denies Landfill Permit for Former Joliet Beach Club Site

Will County Land Use & Development Committee Meeting | November 6, 2025 Article Summary: The Will County Land Use and Development Committee on Thursday narrowly approved rezoning the former Joliet Beach...
Meeting Briefs

Meeting Summary and Briefs: Will County Finance Committee for November 2025

Will County Finance Committee Meeting | November 2025 The Will County Finance Committee reached an impasse over the 2025 tax levy during a heated meeting on Tuesday, prompting the postponement...
Will County Board Graphic.03

Unpermitted Log Cabin and Stage Prompt Rezoning in Beecher

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved a zoning map amendment and variances for a property in Beecher to bring existing unpermitted structures...
Will County Board Graphic.02

Engineering Firm Hired for Gougar Road Bridge Replacement

Will County Board Meeting | November 2025 Article Summary: The Will County Board authorized a $301,000 contract for the design of a new bridge carrying Gougar Road over the Canadian...
Will County Logo Graphic

Speed Limits Lowered in Green Garden and Frankfort Neighborhoods

Will County Board Meeting | November 2025 Article Summary: The Will County Board adopted ordinances to establish new, lower speed limits in specific areas of Green Garden and Frankfort Townships....
Meeting Briefs

Meeting Summary and Briefs: Peotone Public Library District for October 2025

Peotone Public Library District Meeting | October 21, 2025 The Peotone Public Library District Board of Trustees on October 21, 2025, took significant action to expand services and handle key...
peotone library graphic logo.1

Library Board Takes Key Step in 2025 Tax Levy Process

Peotone Public Library District Meeting | October 21, 2025 Article Summary: The Peotone Public Library District Board of Trustees has formally approved its Certificate of Revenues, a legally required step...
Will County P&Z Logo Planning Zoning.2

Committee Grants Lenox Solar Farm Project Six-Month Variance Extension

Will County Planning and Zoning Commission Meeting | November 18, 2025 Article Summary:The Will County Planning and Zoning Commission has approved a 180-day extension for variances tied to a commercial...
Vance to visit Fort Campbell before Thanksgiving

Vance to visit Fort Campbell before Thanksgiving

By Brett RowlandThe Center Square Vice President J.D. Vance will visit Fort Campbell in Kentucky ahead of Thanksgiving to celebrate with Army service members. Vance, 41, and his family will...

WATCH: Trump calls Pritzker a ‘fat slob,’ Illinois governor blasts president

By Jim TalamontiThe Center Square President Donald Trump has revived his criticism of Illinois Gov. J.B. Pritzker over crime, and Pritzker has fired back by blasting Trump over Thanksgiving dinner...
D.C. Mayor Muriel Bowser won't seek reelection

D.C. Mayor Muriel Bowser won’t seek reelection

By Sarah Roderick-FitchThe Center Square Washington, D.C., Mayor Muriel Bowser announced she will not be seeking reelection. The Democratic mayor has served as the second female mayor of the nation’s...
Illinois business group warns of 'backbreaking' progressive income tax

Illinois business group warns of ‘backbreaking’ progressive income tax

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – Manufacturers say legislators at the Illinois State Capitol have done enough damage and a progressive tax would...
Trump's ACA tax credit extension proposal delayed after GOP pushback

Trump’s ACA tax credit extension proposal delayed after GOP pushback

By Thérèse BoudreauxThe Center Square After facing backlash from Republican leaders, the White House is backing away from its proposal to extend the enhanced Obamacare Premium Tax Credit for two...
EXCLUSIVE: Texas rep calls on Trump to get Texan released from Mexican prison

EXCLUSIVE: Texas rep calls on Trump to get Texan released from Mexican prison

By Bethany BlankleyThe Center Square Texas state Rep. Jay Dean, R-Longview, is calling on President Donald Trump, Gov. Greg Abbott, Secretary of State Marco Rubio, U.S. Senators Ted Cruz and...