Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Latest News Stories

IL House GOP asks “Have you had enough yet” following student’s murder

IL House GOP asks “Have you had enough yet” following student’s murder

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – After the alleged murder of a Loyola University student by a migrant who was in the country...
EXCLUSIVE: 5-year anniversary of Operation Lone Star, nearly 540,000 apprehended

EXCLUSIVE: 5-year anniversary of Operation Lone Star, nearly 540,000 apprehended

By Bethany BlankleyThe Center Square Texas’ border security mission, Operation Lone Star, reached a milestone in March, its five-year anniversary. Gov. Greg Abbott first launched OLS in March 2021, in...
Many Republicans say proposed bipartisan DHS funding deal 'impossible'

Many Republicans say proposed bipartisan DHS funding deal ‘impossible’

By Thérèse BoudreauxThe Center Square Senate Republican leaders appear close to reaching a Department of Homeland Security funding deal with Democrats, but many rank-and-file Republicans view the proposed compromise as...
Mullin sworn in as secretary of Homeland Security

Mullin sworn in as secretary of Homeland Security

By Sarah Roderick-FitchThe Center Square As the Department of Homeland Security nears 40 days since a government stalemate shut it down, Markwayne Mullin has been sworn in as the ninth...
Gas spike continues for Illinoisans; state leaders offer no plan to help yet

Gas spike continues for Illinoisans; state leaders offer no plan to help yet

By Sean Reed | The Center SquareThe Center Square (The Center Square) – As fuel prices continue rising, government leaders in Illinois have responded to growing concern over the impact...
BREAKING: Minnesota sues feds for evidence in Metro Surge shootings

BREAKING: Minnesota sues feds for evidence in Metro Surge shootings

By Elyse ApelThe Center Square Minnesota filed a lawsuit Tuesday against the U.S. Department of Justice and the U.S. Department of Homeland Security for refusing to share evidence regarding three...
Supreme Court appears to favor Trump's asylum border policy

Supreme Court appears to favor Trump’s asylum border policy

By Andrew RiceThe Center Square The U.S. Supreme Court appeared in favor of the Trump administration's policy to prevent immigrants making asylum claims from being processed if they are on...
Screenshot

Updated: St. John Woman Charged with Nine Counts of Murder in Crete Township Triple Homicide

Article Summary: Jenna Strouble, 30, of St. John, Indiana, has been charged with nine counts of first-degree murder following the shooting deaths of her former partner, Jacob Lambert, and his...
NASA plans to build $20 billion base on the Moon

NASA plans to build $20 billion base on the Moon

By Brett RowlandThe Center Square NASA has abandoned its plans to build a lunar-orbiting space station and will instead use those resources to construct a $20 billion permanent base on...
HUD launches investigation into race-based Washington housing program

HUD launches investigation into race-based Washington housing program

By Tim ClouserThe Center Square The U.S. Department of Housing and Urban Development launched a fair-housing investigation into the Washington State Housing Finance Commission Tuesday over its race-based Covenant Homeownership...
Illinois lagging the nation for entrepreneurship, economic growth

Illinois lagging the nation for entrepreneurship, economic growth

By Glenn Minnis | The Center Square contributorThe Center Square (The Center Square) – Illinois Policy Institute’s Josh Bandoch says he could have easily predicted the state would rank as...
Illinois Quick Hits: Iowa PA license wait times half of Illinois

Illinois Quick Hits: Iowa PA license wait times half of Illinois

By Jim Talamonti | The Center SquareThe Center Square (The Center Square) – The Iowa Department of Inspections, Appeals, and Licensing says the state’s average wait time for new physician...

Will County Previews ‘GuideWill’ Comprehensive Resource Management Plan

Will County Land Use & Development Committee Meeting | March 2026 Article Summary: Will County's Land Use Department unveiled the branding, interactive tools, and initial timeline for its updated Resource Management...
peotone library graphic logo.1

Peotone Library Board Rescinds Prior Decision, Returns to Werner’s Landscaping

Peotone Public Library District Meeting | February 19, 2026 Article Summary: The Peotone Public Library District Board voted to reverse a previous landscaping decision, opting instead to return to Werner's...
peotone library graphic logo.4

Peotone Library Board Seeks Applicants for Vacant Trustee Position, Approves Staff Promotion

Peotone Public Library District Meeting | February 19, 2026 Article Summary: The Peotone Public Library District Board is officially seeking candidates to fill a vacant trustee position, while also approving...