Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

Screenshot 2025-11-25 at 9.54.08 PM

Board Moves to Create Policy Ensuring Sustainability of Early Learning Center

Crete-Monee School District 201-U Meeting | November 2025 Article Summary: Following a presentation on the success of the Early Learning Center (ELC), Board President Maurice Brown directed the creation of...
Meeting Briefs

Meeting Summary and Briefs: Village of Monee Board for November 19, 2025

Village of Monee Board Meeting | November 19, 2025 Meeting Summary: The Monee Village Board of Trustees met on Wednesday, November 19, 2025, for a session highlighted by major investments...
Will County Board Graphic.01

Frankfort Turns to County for Wildlife & Dangerous Animal Control

Will County Board Meeting | November 2025 Article Summary: The Village of Frankfort has entered into a two-year agreement with Will County Animal Protection Services to handle calls regarding bats...
joliet junior college foundation

JJC Foundation Director Kristin Mulvey to Retire After 25 Years of Transformative Leadership

Joliet Junior College Meeting | November 12, 2025 Article Summary:Kristin Mulvey, the longtime Executive Director of Institutional Advancement and the JJC Foundation, was honored by the Board of Trustees as...
Will County Logo Graphic

Crete “Group Care” Home Approved for Senior Living

Will County Board Meeting | November 2025 Article Summary: The Will County Board unanimously approved a special use permit for a senior group care home in Crete Township. The facility...
Meeting Briefs

Meeting Summary and Briefs: Monee Township Board for Oct. 2025

Monee Township Board Meeting | Oct. 2025 The Monee Township Board met on Thursday, October 16, 2025, to handle monthly business, including the approval of the tax levy hearing schedule...
Screenshot 2025-11-26 at 8.20.00 AM

Monee Public Works Handles Water Leaks and Winter Prep

Village of Monee Board Meeting | November 19, 2025 Article Summary: The Monee Public Works Department has been busy addressing multiple water main breaks while transitioning to winter operations. Crews...
will county board graphic

New Bar Approved in Frankfort Despite Board Opposition

Will County Board Meeting | November 2025 Article Summary: The Will County Board narrowly approved a special use permit for a new bar in Frankfort Township, paving the way for...
joliet junior college logo

JJC Board Approves Grundy County Land Purchase Amid Heated Debate

Joliet Junior College Meeting | November 12, 2025 Article Summary:The Joliet Junior College Board of Trustees voted 6-2 to approve a real estate contract for a new campus in Grundy...
Screenshot 2025-11-25 at 9.53.48 PM

District Proposes “Balloon Levy” to Capture Expiring TIF Revenue

Crete-Monee School District 201-U Meeting | November 2025 Article Summary: The Board of Education discussed the 2025 Tax Levy, opting to request a higher amount than expected to ensure the...
Georgia prosecutor drops Trump election interference case

Georgia prosecutor drops Trump election interference case

By Kim JarrettThe Center Square Election interference charges in Georgia against second-term Republican President Donald Trump have been motioned for dismissal by the Prosecuting Attorney's Council. Unable to find a...
IL congressman’s retirement announcement sparks calls for election fixes

IL congressman’s retirement announcement sparks calls for election fixes

By Catrina Barker | The Center Square contributorThe Center Square (The Center Square) – Common Cause Illinois is urging lawmakers to close what it calls an “anti-democratic” loophole after Rep....
WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

WATCH: Trump calls Pritzker ‘fat slob;’ Talk of reviving progressive tax criticized

By Greg Bishop | The Center SquareThe Center Square (The Center Square) – In today's edition of Illinois in Focus Daily, The Center Square Editor Greg Bishop shares highlights from...
Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

Illinois quick hits: Man arrested for threating legislator; vigilance urged during shopping season

By Jim Talamonti | The Center SquareThe Center Square Man arrested for threating legislator Illinois State Police Division of Criminal Investigation special agents have arrested a Chicago man on charges...
Will County Board Graphic.01

County Takes Over “Central Will” Dial-A-Ride in Major Consolidation

Will County Board Meeting | November 2025 Article Summary: The Will County Board approved an intergovernmental agreement to absorb the "Central Will" Dial-A-Ride system into the county-wide "Access Will County"...