Monee VB July 9

Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

frankfort-square-park-district.2

Frankfort Square Park District Adopts Budget and Appropriation Ordinance, Updates Financial Policy

The Frankfort Square Park District Board of Commissioners formally adopted its Budget and Appropriation Ordinance for the 2025-2026 fiscal year on Thursday, finalizing the district's legal spending authority for the...
Will-County-Executive-Committee-Meeting-June-12-2025

County Board Approves Major Code Updates, Discusses Employee Benefits

The Will County Board Executive Committee approved several ordinance updates Wednesday while engaging in detailed discussions about employee compensation and benefits. The committee passed ordinances updating three chapters of the...
frankfort-square-park-district.1

Major Park District Projects Advance as Hunter Prairie Park Gets Green Light

Work on the Frankfort Square Park District's three major capital projects is hitting key milestones, with the long-awaited redevelopment of Hunter Prairie Park now officially underway. Executive Director Audrey Marcquenski...
Meeting Briefs

Executive Committee June 12 Meeting Briefs

Property Purchase Approved: The county authorized purchase of two parcels along Governor's Highway in Monee for $545,000 to establish a roadway maintenance facility for the eastern end of the county....
frankfort-square-park-district.2

Developer to Donate Land, Playground for New Park in Tinley Park

A new park is coming to a Tinley Park development thanks to a land and equipment donation from a local home builder. Frank Bradley, owner of Crana Homes, is donating...
Meeting Briefs

Meeting Briefs: Frankfort Square Park District for June 12, 2025

The Frankfort Square Park District Board of Commissioners formally adopted its annual Budget and Appropriation Ordinance on June 12, a key legal step that sets the district’s spending authority for...
frankfort-school-district-161.2-e1754272831494

Summit Hill Board Approves School Resource Officer for Two Schools in Contentious Vote

The Summit Hill School District 161 Board of Education voted to hire a School Resource Officer (SRO) to serve two of its schools, approving an annual expenditure of up to...
frankfort-school-district-161.1

Summit Hill School Board Reverses Controversial Principal Non-Renewal Decision

In a significant reversal, the Summit Hill School District 161 Board of Education voted to repeal previous resolutions that aimed to not renew the contract of an unnamed principal, effectively...
frankfort-school-district-161.2-e1754272831494

Meeting Briefs: Summit Hill School District 161 for June 11, 2025

The Summit Hill School District 161 Board of Education made several major decisions at its June 11 meeting, including the hiring of a School Resource Officer for two schools after...
Will-County-Ad-Hoc-Ordinance-Review-Committee-Meeting-June-10-2025

Will County to Draft New Harassment Policy Amid Debate Over Board Authority

The Will County Ad-Hoc Ordinance Review Committee will draft a new, county-wide general harassment policy after a lengthy debate on Tuesday revealed the complexities of the county’s legal obligations and...
Will-County-Ad-Hoc-Ordinance-Review-Committee-Meeting-June-10-2025

Committee Uncovers Gaps in County Asset Tracking, Calls for Better System

A review of Will County’s fiscal policies on Tuesday highlighted significant gaps in how the county tracks its physical assets, from office furniture to squad cars, prompting calls from the...
frankfort-park-district

Frankfort Park District in Dispute with Five Oaks HOA Over Park Development Rules

The Frankfort Park District is taking legal steps to untangle itself from the development rules of the Five Oaks homeowners association, asserting that as a public body, it "cannot be...
Meeting Briefs

In Brief: Ordinance Review Committee Actions

The Will County Ad-Hoc Ordinance Review Committee met June 10 to continue its comprehensive update of the county code. Here are some of the key actions and discussions: Court Fees...
frankfort-park-district.1

Frankfort Park District Kicks Off Busy Summer Season with Races and New Events

The Frankfort Park District is in full summer swing, with a packed schedule of programs and events that includes an expanded day camp, new community parties, and the 25th anniversary...
Will-County-Jail-e1750123778582

Will County Jail Faces Major Staffing Crisis as 70 Employees Eligible to Retire by 2030

County officials warn of potential budget impact as adult detention facility grapples with unprecedented turnover Will County's adult detention facility is heading toward a staffing crisis that could significantly impact...