Firemen’s Park Nears Finish Line After Delays; August Opening Targeted

Spread the love

After months of anticipation and unforeseen challenges, the major renovation of Firemen’s Park is scheduled for substantial completion by August 11, with a final completion date of August 22, project leaders announced at the Monee Village Board meeting Wednesday.

Engineers and contractors detailed a series of setbacks that have delayed the park’s opening, primarily citing unmarked underground utilities and significant backlogs at ComEd.

“Everyone’s anxious to have Firemen’s Park open and ready and be operational, and we’re getting close,” said Matt Bergher, an engineer with Farnsworth Group, who presented alongside Justin Goslin, president of Piggush Simoneau, Inc. (PSI), and site manager Jason Phillips.

The project team described the park’s subsurface as a maze of unexpected obstacles. “Some of the things have been underground utility lines that are just not marked,” Bergher explained. “And also ones that were not known to exist underneath there just from years and years of building out Firemen’s Park.”

Crews discovered unmarked sanitary laterals, fiber optic lines, and electrical wires that were not in conduit, posing a safety hazard. They also unearthed improperly connected drain pipes and a water main buried less than four feet deep, far shallower than the typical five-foot requirement, which forced a halt to some utility work to ensure future designs met state codes.

“Basically we’ll have all the concrete done minus where that transformer is, middle of next week,” Phillips said. “And then we’ll have to wait for that transformer to be decommissioned to finish that the concrete in that area.”

The most significant external hurdle has been with ComEd. Project leaders said the utility company’s layoffs last year after a failed rate hike request created a massive backlog of work orders.

“We’ve been told hopefully we would have service in advance, but that has delayed some things,” Bergher said. “We’re still waiting on them. They were supposed to be here last Friday. They put us off yet again and we still do not have an answer.”

This delay has forced the construction team to work out of sequence, completing available tasks while waiting for permanent power to be installed. Goslin noted that contingency plans are being developed to use temporary power to irrigate the new fields if necessary.

Another challenge emerged mid-construction when the Monee Historical Society raised concerns about the accessibility of the adjacent Creamery building. The existing mechanical lift has been unreliable, and a request was made to add a permanent ADA-compliant ramp. Because concrete walkways were already poured, adding a concrete ramp now would require costly demolition or concrete pumping.

“We probably had $60-70,000 in just getting the concrete up into the area,” Goslin said. PSI is now exploring more cost-effective alternatives, including a pre-fabricated galvanized steel ramp system similar to those used in stadiums, which would require less site disruption.

Despite the delays, visible progress is being made daily. The storage building and volleyball courts are largely finished, needing only nets. Most concrete work for walkways and paths is expected to be complete within a week. At the baseball field, fences for the batting cages are up, the infield is graded, and backstops are in place. The football fields are graded, with final restoration and seeding planned as one of the last steps to avoid damage from remaining construction traffic.

Work on the interiors of the restroom and concession buildings is also advancing, with finishing elements like wall coverings, flooring, and fixtures being installed. Substantial completion is expected by August 11, which means the park will be functional and usable. The following two weeks, until the August 22 final completion date, will be dedicated to addressing a “punch list” of minor finishing touches.

During the presentation, Trustee Chuck Rakis questioned the fit and finish on the concession stand, pointing to photos showing rust on the bottom of metal panels. Goslin acknowledged the issue, explaining that a drip edge was causing water to flow back under the panels. “Yes, we are addressing that issue,” he assured the board. “We might be pulling that metal up and readjusting that lower flashing.”

Monee Events

10 Dec

Village Board Meeting

December 10, 2025
6:30 pm - 11:59 pm
https://villageofmonee.org/calendar.aspx?EID=1537

Latest News Stories

solar panels photovoltaics in solar farm

County Rep Cites Solar Lawsuits, Grant Shortfalls as Key Issues Facing Will County

ARTICLE SUMMARY: Will County Board member Sherry Newquist reported that the county is navigating lawsuits related to solar farm approvals and anticipating budget challenges from the loss of federal grant money....
Assessor

Assessor’s Office Hires Staff to Handle Workload After 6% Multiplier Hits Property Owners

ARTICLE SUMMARY: Following the application of a 6% property assessment multiplier across Green Garden Township, the assessor's office has hired a new staff member to help manage the increased workload and...
SSUCv3H4sIAAAAAAAACnSRz07DMAzG70i8Q5XzKpY10I0jB248wcTBdcwaLUum/AGhae9O0rQjB7jFP9uf/cWX+7umYQN4hey5ueQoxUrr6IODoKxJeL2auSMjydWEpArWKdA1HCDgaOBECZqodcbXKcl8gBA9+TxsRgiBDkmjwJtE2Whf4mZJTMnUkVKMrSrm4zCxBRXxfzpfoleGvH94VQYM0l9Kb8ojaQ2GbPS/suXxvliFAxn8ntxULh1pguJyX0rZ8SuQO9W+IUplK8ufFkHngq5SOjuFyhyqNhvG6QRLG9pogssr3D6EaWvPMOj8/x9JkxY+gvepXC68GoTp4PZUzTE2TAZmVSbTmXLIu023E6Lre7HlohNPYi4opx1V0pnWWYRSjEcla+sqb8AIibbYb1qOXLZih7wdeNe3m+6Ry4H3fECRPv76AwAA//8DAJrJGBCkAgAA

Township Appoints Temporary FOIA Officer During Trustee’s Leave of Absence

ARTICLE SUMMARY: The Green Garden Township Board appointed resident Belinda Olszewski as a temporary, non-paid Administrative Assistant and FOIA Officer to fill the roles while Trustee Sarah Boxer is on a...
Meeting Briefs

Meeting Summary and Briefs: Green Garden Township Board for August 11, 2025

The Green Garden Township Board pushed forward with plans for a new town hall and approved key budget transfers to support the assessor's office during its August 11th meeting. Supervisor...
WCO-Finance-Aug-5.1

Will County Health Department Seeks $1 Million to Avert ‘Drastic’ Service Cuts from Expiring Grants

ARTICLE SUMMARY: The Will County Health Department is requesting an additional $1 million in county funding for its 2026 budget to prevent the elimination of 11 critical staff positions, warning...
WCO-Cap-Imp-8.5.1

Will County’s “First-in-Nation” Veterans Center to House Workforce Services, Sparking Debate

ARTICLE SUMMARY: The new Will County Veteran's Assistance & Support Center will also become the home for the county's Workforce Services department, a move officials say will save approximately $250,000 in...
WCO-Finance-Aug-5.2

Improved Vendor Service Creates $1.2 Million Shortfall in Sheriff’s Medical Budget

ARTICLE SUMMARY: The Will County Sheriff’s Office is facing a more than $1.2 million shortfall in its budget for inmate medical services, a problem officials attribute to an ironic cause:...
WCO-PZ-Aug-5.1

Will County Public Works Committee Unveils 25-Year Transportation Plan, Projects $258 Million Gap

ARTICLE SUMMARY: Will County officials have presented "Our Way Forward 2050," a new long-range transportation plan that provides a 25-year vision for infrastructure projects while forecasting a $258 million shortfall in...
WCO-Public-Safety.4

Will County Animal Protection Services Seeks New Facility Amid “Gaping Wound” of Space Crisis

Article Summary: Will County Animal Protection Services is seeking approval for a new facility, telling a county committee that its current building is critically inadequate for housing animals, leading to...
WCO-Cap-Imp-8.5.2

Board Confronts Animal Services Crowding, Explores Future Facility Options

ARTICLE SUMMARY: Will County officials are grappling with an ongoing animal housing crisis that has overwhelmed the county’s Animal Protective Services facility, prompting discussions about expansion, new construction, or even repurposing...
WCO-Finance-Aug-5.3

Will County Board Members Demand Transparency in Cannabis Tax Fund Allocation

ARTICLE SUMMARY: A debate over transparency and process erupted at the Will County Board’s Finance Committee meeting regarding the distribution of local cannabis tax revenue. Board members called for more...
WCO-PZ-Aug-5.2

Homer Glenn Residents Push Back on 143rd Street Widening as Officials Signal “Tentative Agreement”

ARTICLE SUMMARY: A Homer Glenn farm owner voiced strong opposition to the planned widening of 143rd Street during a county meeting, while committee members indicated a "tentative agreement" is in the...
WCO-LEG-8.5.1

Will County Forges 2026 Federal Agenda Amid D.C. Policy Shifts, ‘Big Beautiful Bill’ Impacts

ARTICLE SUMMARY: The Will County Board's Legislative Committee is reshaping its federal priorities for 2026, adding new language on environmental justice and LGBTQIA+ rights while creating a more transparent process for...
WCO-Public-Safety.3

Health Department Seeks $1 Million Levy Increase to Prevent “Weakened System”

Article Summary: The Will County Health Department is asking for a $1 million increase to its property tax levy to save 11 critical jobs that are at risk as post-pandemic...
WCO-Cap-Imp-8.5.3

County Rolls Out New “OneMeeting” Software to Improve Public Access

ARTICLE SUMMARY: Will County has officially launched a new agenda and meeting management software called "OneMeeting," aimed at improving transparency and making it easier for the public and officials to access...